UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
March 11, 2014
Mr. Michael J. Pacilio
Senior Vice President
Exelon Generation Company, LLC
President and Chief Nuclear Officer (CNO)
Exelon Generation Company, LLC
4300 Winfield Road
Warrenville, IL 60555
SUBJECT:
BYRON STATION, UNITS 1 AND 2, REQUEST FOR INFORMATION FOR AN
NRC TRIENNIAL PERMANENT MODIFICATIONS AND 10 CFR 50.59
(MOD/50.59) BASELINE INSPECTION 05000454/20140007; 05000455/2014007
Dear Mr. Pacilio:
On June 9, 2014, the U.S. Nuclear Regulatory Commission (NRC) will begin a MOD/50.59
Baseline inspection at the Byron Station, Units 1 and 2. This inspection will be performed in
accordance with the NRC baseline Inspection Procedure (IP) 71111.17T. The onsite portion of
the inspection will take place on June 9 - 13 and June 23 - 27, 2014.
Experience has shown that these baseline inspections are extremely resource intensive, both
for the NRC inspectors and the licensee staff. In order to minimize the inspection impact on
the site and to ensure a productive inspection for both parties, we have enclosed a request for
documents needed for the inspection. These documents have been divided into three groups.
The first group of information is necessary to ensure that the inspection team is adequately
prepared for the inspection. This information should be made available via compact disc and
delivered to the regional office no later than April 25, 2014. The inspection team will review this
information and, by May 9, 2014, will request specific items that should be provided for review in
the regional office by May 23, 2014.
The second group of requested documents contains additional items that the team will review,
or need access to, during the inspection. Certain documents contained within Group II (i.e.,
Item 1), will be requested for review in the regional office prior to the inspection by May 23,
2014, as identified above. The remaining documents should be available by the first day of the
onsite inspection, June 9, 2014.
The third group lists information necessary to aid the inspection team in tracking issues
identified as a result of the inspection. It is requested that this information be provided to the
lead inspector as the information is generated during the inspection. It is important that all of
these documents are up to date and complete in order to minimize the number of additional
documents requested during the preparation and/or the onsite portions of the inspection.
Mr. Pacilio
-2-
The lead inspector for this inspection is John V. Bozga. We understand that our regulatory
contact for this inspection is Lisa Zurawski of your organization. If there are any questions
about the inspection or the material requested, please contact the lead inspector at 630-829-
9613 or via e-mail at john.bozga@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150-
0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a
request for information or an information collection requirement unless the requesting document
displays a currently valid Office of Management and Budget control number.
In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390 of the NRC's
"Rules of Practice," a copy of this letter and its enclosure will be available electronically for
public inspection in the NRC Public Document Room or from the Publicly Available Records
(PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC
Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket Nos. 50-454; 50-455
Enclosure:
Modification and 50.59 Inspection Document Request
cc w/encl: Distribution via ListServ'
MODIFICATION AND 50.59 INSPECTION DOCUMENT REQUEST
Enclosure
1
Inspection Report: 05000454/2014007; 05000455/2014007
Inspection Dates:
June 9 - 13 and June 23 - 27, 2014
Inspection Procedure:
Inspection Procedure 71111.17T, Evaluations of Changes, Tests,
and Experiments and Permanent Plant Modifications
Lead Inspector:
John V. Bozga
(630) 829-9613
john.bozga@nrc.gov
I.
Information Requested for In-Office Preparation Week
The following information is requested by April 25, 2014, or sooner, to facilitate the
selection of specific items that will be reviewed during the onsite inspection week. The
inspection team will select specific items from the information requested below and
submit a list to your staff by May 9, 2014. We will request that certain items be made
available to the regional office prior to the inspection by May 23, 2014. We request that
the remaining items selected from the lists be available and ready for review on the first
day of inspection. All requested information should identify the associated system and
cover the time frame from the receipt of information for the last MOD/50.59 inspection to
the present.
The required information identified below should be provided on compact disc (CD).
Please provide three copies of each CD submitted (i.e., one for each inspector). The
preferred file format is a searchable pdf file. The CDs should be indexed and hyper-
linked to facilitate ease of use, if possible. If you have any questions regarding this
information, please call the inspection team leader as soon as possible.
1).
List of permanent plant modifications to systems, structures, or components that
are field work complete. (For the purpose of this inspection, permanent plant
modifications include permanent: plant changes, design changes, set point
changes, equivalency evaluations, suitability analyses, and commercial grade
The list should contain the number of each document, the title, the revision
(or date), and the affected system. In addition to the list, please provide a
description of each modification and a list of associated calculations and affected
procedures.
MODIFICATION AND 50.59 INSPECTION DOCUMENT REQUEST
Enclosure
2
2).
List of all 10 CFR 50.59 completed evaluations involving (a) calculations,
(b) procedure revisions, (c) changes to the facility (modifications), (d) non-routine
operating configurations, or (e) departures in methods of analyses. This list
should include 10 CFR 50.59 evaluations for the following:
a.
Changes that have been made under the provisions of 10 CFR 50.59
that have been updated in accordance with 10 CFR 50.71(e)(4) since the
last MOD/50.59 inspection;
b.
Modifications that are field work complete; and
c.
Changes to calculations (or initiation of new calculations) that have been
issued. The list should contain the number and title of each document, a
brief description of the change, and the corresponding number and type
of the affected document (i.e., the modification or procedure to which the
evaluation applies). The list should NOT include any evaluations in
which prior NRC approval was sought and obtained.
3).
A list of all 10 CFR 50.59 changes that have been screened out as not requiring a
full evaluation involving: (a) calculations; (b) procedure revisions; (c) changes to
the facility (modifications); (d) non-routine operating configurations; or
(e) departures in methods of analyses.
The list should contain the number and title of each document, a brief
description of the change, and the corresponding number and type of the
affected document (i.e., the modification or procedure to which the evaluation
applies).
4).
A list of any modifications, procedure revisions, or UFSAR changes where it was
determined that 10 CFR 50.59 did not apply.
5).
A list of calculation changes that have been issued for use.
6).
A list of corrective action documents (open and closed) that address permanent
plant modifications or 10 CFR 50.59 issues, concerns, or processes. These
documents should also include the corrective action documents associated with
the modification and the 50.59 change implementation.
The list should contain the number, title and revision (or date) of each document,
the affected system and corresponding documentation (if applicable), and
should be sorted in order of significance.
7).
Copies of procedures addressing the following: modifications, design changes,
set point changes, equivalency evaluations or suitability analyses, commercial
grade dedications, post-modification testing, 10 CFR 50.59 evaluations and
screenings, and Updated Final Safety Analysis Report (UFSAR) updates.
8).
Updated Final Safety Analysis Report updates submitted in accordance with
10 CFR 50.71(e)(4). Provide copies of the complete submittal.
MODIFICATION AND 50.59 INSPECTION DOCUMENT REQUEST
Enclosure
3
9).
Copy of the UFSAR change log or a synopsis of the changes. This should
include all of the changes made to the UFSAR that were incorporated in the last
10 CFR 50.71(e)(4) submittal.
10).
Electronic copy of the UFSAR and Technical Specifications, if available.
11).
Name(s) and phone numbers for the regulatory and technical contacts.
12).
Current management and engineering organizational chart.
II.
Information Requested to be Available Prior to Inspection. Requests will be Made
for Section II Item 1) Documents by May 9, 2014, for Availability of Requested
Documents in Section II Item 1) in Regional Office by May 23, 2014, and Section II
Items 2.), 3), and 4) Documents on First Day of Inspection (June 9, 2014).
1).
Copies of all selected items from Section I. This includes copies of
associated documents such as calculations, post-modification test packages,
10 CFR 50.59 evaluations, or screenings, and any corrective action documents.
2).
Copies of these documents do not need to be solely available to the inspection
team as long as the inspectors have easy and unrestrained access to them.
a.
Updated Final Safety Analysis Report (UFSAR), if not previously provided;
b.
Original FSAR Volumes;
c.
Original SER and Supplements;
d.
FSAR Question and Answers;
e.
Quality Assurance Plan;
f.
Technical Specifications, if not previously provided;
g.
Latest IPE/PRA Report;
h.
Vendor Manuals; and
i.
The latest 10 CFR 50.59 UFSAR Update Submittal.
3).
Please ensure that other supporting documents for the selected items have
been located and are readily retrievable, as the inspection team will likely be
requesting these documents during the inspection. Examples of supporting
documents are:
a. Drawings supporting the modifications;
b. Procedures affected by the modifications; and
c. UFSAR change papers generated due to a 10 CFR 50.59 evaluation
MODIFICATION AND 50.59 INSPECTION DOCUMENT REQUEST
Enclosure
4
4).
Assessment and Corrective Actions:
a. The most recent MOD/50.59 Quality Assurance (QA) audit and/or
self-assessment; and
b. Corrective action documents (e.g., condition reports, including status
of corrective actions) generate as a result of the most recent
MOD/50.59 Quality Assurance (QA) audit and/or self-assessment.
5).
A discussion of scheduling fire drills which may occur during the
inspection so that the inspectors may be able to observe a fire drill, if
possible.
III.
Information Requested to be provided throughout the inspection
1).
Copies of any corrective action documents generated as a result of the
inspection teams questions or queries during this inspection.
2).
Copies of the list of questions submitted by the inspection team members
and the status/resolution of the information requested (provide daily
during the inspection to each inspection team member).
If you have any questions regarding the information requested, please contact the
inspection team leader.
Mr. Pacilio
-2-
The lead inspector for this inspection is John V. Bozga. We understand that our regulatory contact for
this inspection is Lisa Zurawski of your organization. If there are any questions about the inspection or
the material requested, please contact the lead inspector at 630-829-9613 or via e-mail at
john.bozga@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements
were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not
conduct or sponsor, and a person is not required to respond to, a request for information or an
information collection requirement unless the requesting document displays a currently valid Office of
Management and Budget Control Number.
In accordance with Title 10, Code of Federal Regulations (CFR), Section 2.390 of the NRC's "Rules of
Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's
document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Robert C. Daley, Chief
Engineering Branch 3
Division of Reactor Safety
Docket Nos. 50-454; 50-455
Enclosure:
Modification and 50.59 Inspection Document Request
cc w/encl: Distribution via ListServ'
DISTRIBUTION:
RidsNrrDorlLpl3-2 Resource
RidsNrrPMByron Resource
RidsNrrDirsIrib Resource
Cynthia Pederson
DRPIII
DRSIII
Patricia Buckley
DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress/Ltr 031114 Byron MOD 50 59 RFI JVB.docx
Publicly Available
Non-Publicly Available
Sensitive
Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE
RIII
RIII
NAME
JBozga:ls
RDaley
DATE
03/11/14
03/11/14
OFFICIAL RECORD COPY