Submittal of 2013 Annual Operating Report for the Alan J. Blotcky Reactor Facility
ML14069A410
Person / Time
Site: 05000131
Issue date: 02/27/2014
From: Mylan M, Romberger D
US Dept of Veterans Affairs, Nebraska-Western Iowa Health Care System
To:
Document Control Desk, NRC/FSME
References
Download: ML14069A410 (2)


Text

Omaha 4101 Woolworth Avenue Omaha NE 68105-1873 DEPARTMENT OF VETERANS AFFAIRS NEBRASKA-WESTERN IOWA HEALTH CARE SYSTEM Lincoln 600 S 70th Street Lincoln NE 68510-2493 Grand Island S --- 2201 N Broadwell Avenue Grand Island NE 68803-21f February 27, 2014 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Re: 2013 Annual Operating Report for the Alan J. Blotcky Reactor Facility, License R-57, Docket # 50-131 This annual operating report is being submitted in compliance with technical specification 6.7.1, "Annual Operating Report".

Summary of Reactor Operating Experience during 2013.

The reactor remained shutdown with no fuel onsite throughout 2013. The reactor was permanently shutdown on 11/5/2001. All fuel was transferred to the USGS TRIGA facility during June of 2002. The fission chambers used in the reactor's nuclear instrumentation system were transferred to USGS during December 2002.

The reactor's Am-Be neutron sources were removed from the reactor facility and transferred to the Department of Energy's Off-Site Source Recovery Program on 7/24/2003. The Po-Be neutron source (Source No. 0-178) remains at the AJBRF.

On March 14, 2013 the "2012 Annual Operating Report' was sent to the NRC Document Control Desk.

On May 16, 2013 a letter was sent to the NRC Document Control Desk in regards to a "Requestfor License Termination for the Alan J. Blotcky Reactor Facility".

On July 15, 2013 a letter was sent to the NRC Document Control Desk in regards to a "Notification of level I PersonnelChange".

On September 16, 2013 a letter was sent to the NRC Document Control Desk in regards to a "Notification of level I PersonnelChange".

Unscheduled Shutdowns

The reactor was maintained in a scheduled secured shutdown condition throughout 2013.

Maior preventative and corrective maintenance No major safety related maintenance was performed during 2013.

Changes, Tests and Experiments Changes to level 1 personnel occurred and were reported to the NRC in July and September of 2013.

There were no other changes, tests or experiments conducted during 2013.

Radioactive Effluents No radioactive effluents associated with the AJBRF were released or discharged beyond the effective control of the Medical Center during 2013.

Environmental Surveys There were no environmental surveys conducted during 2013.

Radiation Exposures There were no radiation exposures received by AJBRF personnel or visitors exceeding 25% of allowable limits during 2013.

DR. MARCI MYLAN Director of the Nebraska-Western Iowa Health Care System DR. DEBRA ROMB R R Associate Chief of Staff Research RSC Chairman Cc: TED SMITH