MONTHYEARML23341A2002023-12-0707 December 2023 Email - Indian Point Energy Center Generating Units 1, 2, and 3 Implementation Notice of Amendment No. 67, 300 and 276 to Independent Spent Fuel Storage Installation Only Emergency Plan (Ioep) ML23332A0802023-11-0808 November 2023 Email from State of New York on the Revised License Amendment for Indian Point Energy Center ISFSI Only Emergency Plan ML23325A1632023-11-0808 November 2023 State of New York Comments on the Revised License Amendment for Indian Point Unit 2 and 3 Technical Specification Changes Reflecting Permanent Removal of Spent Fuel ML23331A9542023-11-0808 November 2023 Email - State of New York Comments on the Revised License Amendment for Indian Point Unit 2 and 3 Technical Specification Changes Reflecting Permanent Removal of Spent Fuel ML23144A3452023-05-25025 May 2023 Adam Kahn of Monsey, New York Email Against Treated Water Release from Indian Point Site ML23144A3442023-05-25025 May 2023 Peggy Kurtz of Rockland County, New York Email Against Treated Water Release from Indian Point Site ML23144A3392023-05-25025 May 2023 David Morris of New City, New York Email Against Treated Water Release from Indian Point Site ML23144A3502023-05-25025 May 2023 Dan Kwilecki of Montebello, New York Email Against Treated Water Release from Indian Point Site ML23144A3422023-05-25025 May 2023 Peter Duda of Pearl River, New York Email Against Treated Water Release from Indian Point Site ML23144A3382023-05-25025 May 2023 Dawn Giambalvo of Jersey City, New Jersey Email Against Treated Water Release from Indian Point Site ML23136B1622023-05-15015 May 2023 Town of North Salem, County of Westchester, New York Board Resolution Letter Regarding Treated Water Release from Indian Point Site ML23109A0632023-04-17017 April 2023 Email Acceptance Review for IP2 and IP3 Amended Facility License and Technical Specification to Reflect Permanent Removal of Spent Fuel from Spent Fuel Pits ML23055A1112023-02-23023 February 2023 Alyse Peterson Email- NYSERDA No Comments on Indian Point Unit 2 - Regarding Holtec License Amendment Request to Revise Permanently Defueled Technical Specifications and Staffing Requirements with Spent Fuel Transfer to ISFSI (Dockets 50-24 ML23049A0032023-02-14014 February 2023 NRC Acceptance Email to Holtec for License Amendment Request for Approval of New ISFSI-Only Emergency Plan and Associated EAL Scheme ML22313A1682022-11-0909 November 2022 NRC Response to Updates to the Proposed Amended IP2 Master Trust ML22308A0912022-11-0303 November 2022 Email Acknowledgement for IP2 and IP3 Amended Facility License and Technical Specification to Reflect Permanent Removal of Spent Fuel from Spent Fuel Pits ML22276A1642022-09-29029 September 2022 New York State Revised Draft EA Response E-Mail ML22271A8492022-09-28028 September 2022 E-Mail Transmitting Revised Indian Point Exemption Draft EA ML22269A3452022-09-22022 September 2022 Email Objection to Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2, EPID L-2022-LLA-0072 ML22259A1992022-09-0202 September 2022 Acceptance for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage ML22265A0142022-08-31031 August 2022 Email Acknowledgement for Amended and Restated Holtec IP3 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 3 ML22242A2592022-08-19019 August 2022 E-mail from K. Sturzebecher, NRC, to B. Noval, HDI, Acknowledgement for Amended and Restated Holtec IP2 Master Decommissioning Trust Agreement for Indian Point Nuclear Generating Facility Unit 1 and 2 ML22228A1332022-08-0909 August 2022 Acknowledgement for License Amendment Request to Modify Staffing Requirements Following SFP Transfer to Dry Storage ML22215A0432022-08-0101 August 2022 E-Mail Transmitting NYS NSA Exemption Comments & Draft EA Review Completion ML22208A0292022-07-19019 July 2022 E-Mail Transmitting Indian Point Exemption Draft EA ML22168A0072022-06-16016 June 2022 Acceptance Review for License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML22112A0102022-04-21021 April 2022 Acceptance Review: Request for Exemption from 10 CFR 50.54(w)(1) Concerning Indian Point Energy Center Onsite Property Damage Insurance ML22112A0122022-04-21021 April 2022 Acceptance Review: Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance for Indian Point Energy Center ML22103A2432022-04-13013 April 2022 E-mail - Request for Additional Information - License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme for Permanently Defueled Condition for Indian Point Energy Center ML22104A0342022-04-13013 April 2022 E-mail from Z. Cruz, NRC to J. Fleming, Holtec - Request for Additional Information Related to Request for Exemption from Portions of 10 CFR 50.47 and Part 50 Appendix E for Indian Point Energy Center ML22038A2572022-02-0707 February 2022 E-mail from Z. Cruz, NRC, to J. Fleming, HDI - Acceptance Review: License Amendment Request to Revise Emergency Plan and Emergency Action Level Scheme to Address Permanently Defueled Condition for Indian Point Energy Center ML22035A1862022-02-0404 February 2022 E-mail to J. Fleming, Holtec, from Z. Cruz Perez, NRC - Acceptance Review: Exemption Requests from Portions of 10 CFR 50.47 and 10 CFR Part 50, Appendix E, Section IV for Indian Point Energy Center ML22028A1032022-01-28028 January 2022 E-mail Dated 1/28/2022, Transmittal of Draft Safety Evaluation for Proposed License Amendment Revision to Licensing Basis to Incorporate the Installation and Use of of New Auxiliary Lifting Device ML22038A1592022-01-24024 January 2022 NRR E-mail Capture - (External_Sender) 2021 IPEC Annual Sturgeon Impingement Report ML22006A0442022-01-0505 January 2022 Email from Z Cruz to J Fleming Request for Additional Information - HDI Indian Point Post-Shutdown Decommissioning Activities Report ML21337A2952021-12-0303 December 2021 Subsequent Request for Additional Information License Amendment Request to Revise Licensing Basis for New Auxiliary Lifting Device (E-mail Dated 12/3/2021) ML21335A3692021-12-0101 December 2021 Acceptance Review: Indian Point Energy Center - Exemption Request from 10 CFR Part 20 App G Section Iii.E ML21266A2972021-08-18018 August 2021 8/18/2021 E-mail from H. Specter to R. Guzman Public Comments to NRC, Indian Point Post-Shutdown Decommissioning Activities Report Public Meeting on July 29, 2021 ML21225A6142021-08-0909 August 2021 Email from NRC to the Tuscarora Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5682021-08-0909 August 2021 Email from NRC to the Stockbridge-Munsee Community Band of Mohican Indians Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5012021-08-0909 August 2021 Email from NRC to the Shinnecock Indian Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21224A3032021-08-0909 August 2021 Email from NRC to the Mashantucket Pequot Tribe of Connecticut Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A4252021-08-0909 August 2021 Email from NRC to the Oneida Nation of Wisconsin Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A3142021-08-0606 August 2021 Email from NRC to the Oneida Indian Nation Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A4402021-08-0606 August 2021 Email from NRC to the Onondaga Nation of Wisconsin Announcing the IPEC PSDAR Meeting on August 18, 2021 ML21225A5462021-08-0606 August 2021 Email from NRC to the St. Regis Mohawk Tribe Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21225A5352021-08-0606 August 2021 Email from NRC to the Tonawanda Band of Seneca Announcing the IPEC PSDAR Public Meeting on August 18, 2021 ML21266A2942021-07-25025 July 2021 E-mail from Paul Blanch to NRC (N. Sheehan, D. Screnci) Public Comments to NRC, Indian Point Post-Shutdown Decommissioning Activities Report Public Meeting, July 29, 2021 ML21197A2002021-07-16016 July 2021 (E-mail 7/16/2021) NRC Staff Assessment and RAI Closeout HDI Fleet Decommissioning Quality Assurance Program and Indian Point Energy Center Quality Assurance Program Manual ML21194A4082021-07-13013 July 2021 (7-13-2021) E-mail NRR Review Hour Estimate Change Supporting the Hi-Lift Crane Proposed License Amendment Request Review 2023-05-25
[Table view] |
Text
IPRenewal NPEmails From: Green, Kimberly Sent: Thursday, March 06, 2014 9:59 AM To: Waters, Roger M. (rwater1@entergy.com)
Cc: IPRenewal NPEmails; Poehler, Jeffrey; Hiser, Allen
Subject:
Draft RAI on RVI Program and Inspection Plan Attachments: IP Draft Follow-up RAI on RVI re Split Pins Clevis Bolts and AI7 03-05-14.docx
- Roger, Attached is a draft RAI containing three questions on the RVI program and inspection plan. After Entergy has had a chance to review the draft RAI, please let me know if you will need a phone call for clarification.
- Thanks, Kim 1
Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 4499 Mail Envelope Properties (F5A4366DF596BF458646C9D433EA37D70167E91C3AEA)
Subject:
Draft RAI on RVI Program and Inspection Plan Sent Date: 3/6/2014 9:58:59 AM Received Date: 3/6/2014 9:58:59 AM From: Green, Kimberly Created By: Kimberly.Green@nrc.gov Recipients:
"IPRenewal NPEmails" <IPRenewal.NPEmails@nrc.gov>
Tracking Status: None "Poehler, Jeffrey" <Jeffrey.Poehler@nrc.gov>
Tracking Status: None "Hiser, Allen" <Allen.Hiser@nrc.gov>
Tracking Status: None "Waters, Roger M. (rwater1@entergy.com)" <rwater1@entergy.com>
Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 254 3/6/2014 9:58:59 AM IP Draft Follow-up RAI on RVI re Split Pins Clevis Bolts and AI7 03-05-14.docx 24342 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
D-RAI 11-C Applicant/Licensee Action Item 7 from the staffs final safety evaluation (SE) of MRP-227 requires the applicants/licensees of Babcock & Wilcox (B&W), CE, and Westinghouse reactors to develop plant-specific analyses to be applied for their facilities to demonstrate that B&W IMI guide tube assembly spiders and control guide rod tube (CRGT) assembly spacer castings, CE lower support columns, and Westinghouse lower support column bodies will maintain their functionality during the period of extended operation, and states that these analyses should also consider the possible loss of fracture toughness in these components due to thermal embrittlement (TE) and irradiation embrittlement (IE). For Indian Point Nuclear Generating Unit Nos. 2 and 3 (IP2 and IP3), the equivalent component to the lower support column bodies are the lower internals assembly - column caps (column caps).
By letter dated January 28, 2014, Entergy provided plant-specific information on the ferrite content and susceptibility to TE for the Indian Point Nuclear Generating Unit Nos. 2 and 3 lower internals assembly - column caps. Based on its evaluation of the plant-specific material information for the column caps, Entergy concluded that the IP2 and IP3 column caps are not susceptible to TE.
Entergys conclusion related to TE notwithstanding, the column caps remain susceptible to IE.
The staff is concerned that the linked Primary component for the column caps, the CRGT assembly lower flange welds, is not a good predictor of IE for the column caps since the CRGT lower flange welds receive substantially lower neutron fluence than the column caps (based on the estimated neutron fluence tabulated in MRP-191 for the two components). Irradiation assisted stress corrosion cracking (IASCC) is the only mechanism of cracking that screened in for the column caps. The CRGT lower flange welds are also not a good predictor for IASCC of the column caps, because the lower flange welds are susceptible to stress corrosion cracking (SCC) and fatigue cracking, but not IASCC.
The staff, therefore, requests that Entergy modify its Reactor Vessel Internals Inspection Plan (RVI Inspection Plan) to provide a link to a Primary component or components that is an appropriate predictor of IE and IASCC of the column caps.
D-RAI 16-B In its September 27, 2013 response to RAI 16-A, Entergy proposed Commitment No. 50 stating that it would provide the NRC staff a detailed inspection plan for the IP2 split pins, including inspection methods, inspection coverage, and inspection frequency, by March 31, 2015, if the planned replacement of the IP2 split pins will not be accomplished in 2016. In order to resolve MRP-227-A Applicant/Licensee Action Item 3, the NRC staff requests Entergy submit the schedule for initial inspection, inspection methods, inspection coverage, and inspection frequency for the IP2 split pins in the event the IP2 split pins are not replaced by 2016, and that Commitment No. 50 be modified accordingly.
D-RAI 17-A In its September 27, 2013 response to RAI 17, Entergy provided a technical justification for the adequacy of the existing inspection requirements specified in MRP-227-A for the clevis insert bolts, which relies on its American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI Inservice Inspection (ISI) Program. Entergys response included the statement, [t]he video camera visual inspections at a ten-year interval by qualified
personnel that are specified in the ASME Code Section XI and MRP-227-A are capable of identifying wear or dislodged components of the clevis insert cap screws or dowel pins at any location, if they exist. To assure that the type of degradation documented in Westinghouse InfoGram IG-10-1 would be reliably detected at IP2 and IP3, the staff requests the following additional information:
- 1. Provide the ASME Section XI, Table IWB-2500 Examination Category and Item Number under which the IP2 and IP3 clevis insert bolts are classified.
- 2. Verify that the ASME Code,Section XI examination of the clevis inserts directly views all the clevis insert bolt heads, dowel pins and locking devices for each clevis insert.
- 3. If the ASME Code,Section XI examination does not directly view all the clevis insert bolts heads, locking devices, and dowel pins, propose a modification to Entergys ASME Code,Section XI ISI Program to do so.
- 4. State when the most recent ASME Code,Section XI inspection of the clevis insert bolts was conducted at IP2 and IP3. Summarize the findings of that inspection for the clevis insert bolts.