MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
See also: IR 05000275/2014003
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD.
ARLINGTON, TX 76011-4511
February 24, 2014
Mr. Edward D. Halpin
Senior Vice President and
Chief Nuclear Officer
Pacific Gas and Electric Company
Diablo Canyon Power Plant
P.O. Box 56, Mail Code 104/6
Avila Beach, CA 93424
SUBJECT: DIABLO CANYON POWER PLANT - NOTIFICATION OF EVALUATIONS OF
CHANGES, TESTS, OR EXPERIMENTS, AND PERMANENT PLANT
MODIFICATIONS INSPECTION (INSPECTION REPORT 05000275/2014003
AND 05000323/2014003) AND REQUEST FOR INFORMATION
Dear Mr. Halpin:
From May 5 - 16, 2014, reactor inspectors from NRCs Region IV office will perform the baseline
inspection of changes, tests, experiments, and permanent plant modifications at your Diablo
Canyon Power Plant, using NRC Inspection Procedure 71111.17, Evaluations of Changes,
Tests, or Experiments and Permanent Plant Modifications.
Experience has shown that this inspection is resource intensive both for the NRC inspectors
and your staff. In order to minimize the impact to your onsite resources and to ensure a
productive inspection, we have enclosed a request for documents needed for this inspection.
Upon review of these documents, the inspectors will select additional documentation for review
upon arrival. It is important that all of these documents are up to date and complete in order to
minimize the number of additional documents requested during the preparation and/or the
onsite portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Mike McCoy of your licensing organization.
If there are any questions about this inspection or the material requested, please contact the
lead inspector, Wayne Sifre, by telephone at 817-200-1193 or by e-mail at
Wayne.Sifre@nrc.gov.
E. Halpin -2-
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
Dockets: 50-275; 50-323
Licenses: DPR-80; DPR-82
Enclosure: Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications
Request for Information
cc: Electronic Distribution for Diablo Canyon Power Plant
E. Halpin -3-
ML14055A346
Non-Sensitive Publicly Available TRF
SUNSI Review
Sensitive Non-Publicly Available
SRI:EB1 C:EB1
WSifre TFarnholtz
/RA/ /RA/
02/20/2014 02/24/2014
OFFICIAL RECORD COPY
Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications
Inspection Request for Information
Inspection Report: 05000275/2014003 and 05000323/2014003
Inspection Dates: May 5 - 16, 2014
Inspection Procedure: IP 71111.17, Evaluation of Changes, Tests, or Experiments and
Permanent Plant Modifications
Lead Inspector: Wayne Sifre, Senior Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
format (Certrec IMS preferred), to the attention of Wayne Sifre, by April 21, 2014, to facilitate the
selection of specific items that will be reviewed during the onsite inspection week. The
inspectors will select specific items from the information requested below and then request from
your staff additional documents needed during the onsite inspection weeks. We ask that the
specific items requested be available and ready for review on the first day of inspection. Also,
we request that you categorize the documents in your response with the numbered list below.
Please provide requested documentation electronically, if possible. If requested documents are
large and only hard copy formats are available, please inform the inspector(s), and provide
subject documentation during the first day of the onsite inspection. If you have any questions
regarding this information request, please call the lead inspector as soon as possible.
1. A list, with descriptions of all 10 CFR 50.59 screenings (or equivalent) performed since
September 30, 2011, which did not result in an evaluation. Note: Description of
screenings should be brief, but of sufficient detail so that inspectors can determine the
significance of the issue.
2. A list, with descriptions, of all 10 CFR 50.59 evaluations performed which did not result
in an application for license amendment since September 30, 2011. Note: Description of
evaluations should be brief, but of sufficient detail so that inspectors can determine the
significance of the issue.
3. Diablo Canyon procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
4. A list with descriptions of all Corrective Action documents related to 10 CFR 50.59
activities, including screenings and evaluations from September 30, 2011, to the
present.
5. A list, with descriptions of all permanent plant modifications since September 30, 2011.
Include sufficient detail to enable the inspector to determine the significance of each
modification. For this inspection, permanent plant modifications include permanent plant
-1- Enclosure
changes, design changes, setpoint changes, procedure changes, equivalency
evaluations, suitability analyses, calculations, and commercial grade dedications.
6. Diablo Canyon procedure for implementing and controlling permanent plant
modifications.
7. A list, with descriptions of all Corrective Action documents related to your permanent
plant modification program and its implementation since September 30, 2011. Include
sufficient detail to enable the inspector to determine the significance of each
modification.
8. A listing of personnel qualified to prepare 50.59 screenings and evaluations, including
qualification dates.
9. A listing of personnel qualified to review and approve 50.59 screenings and/or
evaluations, including qualification dates.
Inspector Contact Information:
Wayne Sifre Robert Latta John Watkins
Senior Reactor Inspector Senior Reactor Inspector Reactor Inspector
817-200-1193 817-200-1532 817-200-0170
Wayne.Sifre@nrc.gov Robert.Latta@nrc.gov John.Watkins@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Wayne Sifre
1600 East Lamar Blvd.
Arlington, TX 76011-4125
-2-