February 10, 2014
Mr. Fadi Diya, Senior Vice
President and Chief Nuclear Officer
Union Electric Company
P.O. Box 620
Fulton, MO 65251
SUBJECT:
CALLAWAY PLANT - NOTIFICATION OF NRC INITIAL OPERATOR
LICENSING EXAMINATION 05000483/2014301
Dear Mr. Diya:
In a telephone conversation on January 28, 2014 between Messrs. Mark Otten, Exam Group
Supervisor, and Thomas Farina, NRC Chief Examiner, arrangements were made for the
administration of licensing examinations at the Callaway Plant during the week of
December 8, 2014.
As agreed during the telephone conversation, your staff will prepare the examinations based on
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for
Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will
discuss with your staff any changes that might be necessary before the examinations are
administered.
To meet the above schedule, it will be necessary for your staff to furnish the examination
outlines by September 19, 2014. The draft written examinations, operating tests, and supporting
reference materials identified in Attachment 3 to ES-201 will be due by October 20, 2014, and
final exam materials will be due by November 24, 2014. Pursuant to Title 10, Section
55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the outlines, examinations, and tests before
they are submitted to the NRC for review and approval. All materials shall be complete and
ready-to-use. We request that any personal, proprietary, sensitive unclassified, or safeguards
information in your response be contained in a separate enclosure and appropriately marked.
Any delay in receiving the required examinations and reference materials, or the submittal of
inadequate or incomplete materials, may cause the examinations to be rescheduled. In addition,
your support for on-site validation of the examinations is required during the week of
November 3, 2014.
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above. In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
NUC LEAR RE GULATOR Y C OM MI S SI ON
R E G IO N I V
1600 EAST LAMAR BLVD
AR L INGTON , TEXAS 76011- 4511
F. Diya
- 2 -
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary operator and
senior operator license applications (Office of Management and Budget (OMB) approval number
3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if
any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If
the applications are not received at least 30 days before the examination date, a postponement
may be necessary. Signed applications certifying that all training has been completed should be
submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018. The public reporting burden for this collection of information is
estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions,
gathering and maintaining the data needed, and completing and reviewing the collection of
information. Send comments regarding this burden estimate or any other aspect of these
information collections, including suggestions for reducing the burden, to the Records and
FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRCs Public Document Room or from the
Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access
and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room
page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Farina has been advised of the policies and
guidelines referenced in this letter. If you have any questions regarding the NRCs examination
procedures and guidelines, please contact Mr. Farina at 817-200-1117, or myself at
817-200-1159.
Sincerely,
/RA/
Vincent Gaddy, Chief
Operations Branch
Division of Reactor Safety
Docket: 50-483
License: NPF-30
F. Diya
- 3 -
DISTRIBUTION:
Electronic distribution by RIV:
Regional Administrator (Marc.Dapas@nrc.gov)
Deputy Regional Administrator (Steven.Reynolds@nrc.gov)
DRP Deputy Director (Troy.Pruett@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
Acting DRS Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (Thomas.Hartman@nrc.gov)
Resident Inspector (Zachary.Hollcraft@nrc.gov)
Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)
Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)
Project Engineer, DRP/B (David.You@nrc.gov)
CW Administrative Assistant (Dawn.Yancey@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Project Manager (Fred.Lyon@nrc.gov)
Branch Chief, DRS/OB (Vincent.Gady@nrc.gov)
Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov)
RITS Coordinator (Marisa.Herrera@nrc.gov)
ACES (R4Enforcement.Resource@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Technical Support Assistant (Loretta.Williams@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Ernesto.Quinones@nrc.gov)
R:\\ Reactors\\CW\\2014\\CW2014301LT-tjf.pdf
ADAMS: No Yes
SUNSI Review Complete
Reviewer Initials: TJF
Publicly Available
Non-Sensitive
Non-publicly Available
Sensitive
OE:OB
C:OB
TFarina
VGaddy
/RA/T-VGaddy
/RA/
2/10/14
2/10/14