MONTHYEARML24010A0032024-01-30030 January 2024 Exemption from Select Requirements of 10 CFR Part 73 - Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24026A0532024-01-30030 January 2024 Notification of an NRC Fire Protection Team Inspection- (Report 05000348/2024011, 05000364/2024011) and Request for Information IR 05000348/20230402024-01-24024 January 2024 95001 Supplemental Inspection Report 05000348/2023040 and Follow-Up Assessment Letter ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) NL-24-0011, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-01-11011 January 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23346A2222023-12-22022 December 2023 Transmittal of Dam Inspection Report - Public NL-23-0901, 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers2023-12-15015 December 2023 30-Day 10 CFR 21 Notification - Framatome Supplied Siemens Medium Voltage (Mv) Circuit Breakers NL-23-0908, Cycle 30 Core Operating Limits Report2023-12-13013 December 2023 Cycle 30 Core Operating Limits Report NL-23-0877, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23228A1432023-11-22022 November 2023 Issuance of Amendment Nos. 249 and 246 to Revise TS 3.6.3, Surveillance Requirement 3.6.3.5 to Eliminate Event-Based Testing of Containment Purge Valves with Resilient Seals NL-23-0825, Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection2023-11-14014 November 2023 Reply to Notice of Violation EA-23-080 and Readiness for 95001 Inspection ML23318A0672023-10-31031 October 2023 1 to Updated Final Safety Analysis Report, Updated NFPA 805 Fire Protection Program Design Basis Document, Technical Specification Bases Changes, Technical Requirements Manual Changes, IR 05000348/20230032023-10-24024 October 2023 Integrated Inspection Report 05000348/2023003 and 05000364/2023003 IR 05000348/20230912023-10-19019 October 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letter NRC Inspection Report 05000348/2023091 IR 05000348/20234022023-10-18018 October 2023 Security Baseline Inspection Report 05000348/2023402 and 05000364/2023402 IR 05000348/20234412023-10-12012 October 2023 Supplemental Inspection Report 05000348/2023441 and 05000364/2023441 and Follow-Up Assessment Letter (Cover Letter) ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report NL-23-0739, Response to NRC Inspection Report and Preliminary White Finding2023-09-0808 September 2023 Response to NRC Inspection Report and Preliminary White Finding IR 05000348/20230902023-08-31031 August 2023 NRC Inspection Report 05000348/2023090 and Preliminary White Finding and Apparent Violation ML23164A1202023-08-30030 August 2023 Proposed Inservice Inspection Alternative FNP-ISI-ALT-05-05, Version 1.0, to the Requirements of the ASME Code ML23240A0012023-08-30030 August 2023 Correction to Issuance of Amendment Nos. 241, 242, 243, and 244 ML23235A2962023-08-24024 August 2023 Issuance of Amendment Nos. 247 and 244, Regarding License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, (EPID L-2023-LLA-0116) (Emergency Circumstances) NL-23-0716, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0713, Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-23023 August 2023 Response to Request for Additional Information Regarding Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit NL-23-0704, Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit2023-08-22022 August 2023 Emergency License Amendment Request: Technical Specification 3.6.5, Containment Air Temperature, One-Time Temporary Change to Limit IR 05000348/20330012023-08-14014 August 2023 NRC Operator License Examination Report 05000348/203301 and 05000364/2023302 NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal IR 05000348/20230022023-08-10010 August 2023 Integrated Inspection Report 05000348/2023002 and 05000364/2023002, and Apparent Violation ML23221A3062023-08-0909 August 2023 Notification of NRC Supplemental Inspection (95002) and Request for Information (Cover Letter) NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis ML23202A1122023-08-0202 August 2023 Units, 1 and 2; and Vogtle Units 1 and 2 - Request to Use a Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI NL-23-0628, Readiness for Supplemental Inspection EA-22-1012023-07-26026 July 2023 Readiness for Supplemental Inspection EA-22-101 NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0506, to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications2023-07-0505 July 2023 to Non-Voluntary License Amendment Request: Technical Specification Revision to Adopt WCAP-17661-P-A, Improved RAOC and CAOC Fq Surveillance Technical Specifications ML23136B1542023-07-0303 July 2023 Issuance of Amendment Nos. 246 & 243, Regarding License Amendment Request to Revise Technical Specification 4.3, Fuel Storage, to Correct Tabulated Values from the Associated Spent Fuel Pool (SFP) Criticality Analysis IR 05000348/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection (CETI) Baseline Inspection Report 05000348/2023010 and 05000364/2023010 NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal ML23164A2182023-06-14014 June 2023 Draft Safety Evaluation for License Amendment Request to Revise Technical Specification 4.3, Fuel Storage, to Correct Tabulated Values from the Associated SFP Criticality Analysis (EPID L-2022-LLA-0138) - Letter NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0449, National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application2023-06-0202 June 2023 National Pollutant Discharge Elimination System (NPDES) Permit Renewal Application NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0337, Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.52023-05-0505 May 2023 Response to Request for Additional Information Related to License Amendment Request to Revise the Frequency of Surveillance Requirement 3.6.3.5 IR 05000348/20234402023-05-0505 May 2023 Reissue Farley Units-Final Significance Determination for a Security-Related Greater than Green Finding, Nov and Assessment Followup LTR, IR 05000348/2023440 and 05000364/2023440 - Cover IR 05000348/20230012023-05-0404 May 2023 Integrated Inspection Report 05000348/2023001 and 05000364/2023001 NL-23-0295, Reply to a Notice of Violation; EA-22-1012023-05-0101 May 2023 Reply to a Notice of Violation; EA-22-101 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 2024-01-30
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 January 31, 2014 Mr. T. A. Lynch Vice President Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500 Ashford, AL 36312
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION - JOSEPH M. FARLEY NUCLEAR PLANT
Dear Mr. Lynch:
In a telephone conversation on January 27, 2014, Mr. Phillip G. Capehart, Senior Operations Examiner, and Mr. Randy Odom, Lead Instructor for Operations Continuing Training, arranged for the U.S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at Farley Nuclear Plant. The inspection is planned for the week of March 10, 2014, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program. It is our understanding that you have committed to maintain your plant-referenced simulator in accordance with ANSI/ANS-3.5-1985, American National Standard for Nuclear Power Plant Simulators for Use in Operator Training and Examination.
In accordance with 10 CFR 55.59, the NRC has requested that you submit (by February 17, 2014, or make ready upon arrival), the material as specified in the Enclosure, in order to support the NRC's inspection program needs. Mr. Odom has been advised of this request and was provided the name and address of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501, et seq.). These information collections were approved by the Office of Management and Budget, approval number Part 55 (3150-0018), which expires on April 30, 2016.
The public reporting burden for this collection of information is estimated to average four hours per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, DC 20503.
T. Lynch 2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB approval number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter, and its Enclosure will be available electronically for public inspection in the NRC Public Document Room, or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection please contact Mr. Phillip Capehart at (404) 997-4626, (Internet E-mail:
Phillip.Capehart@nrc.gov), or me at (404) 997-4550, (Internet E-mail:
Malcolm.Widmann@nrc.gov).
Sincerely,
/RA: Eugene Guthrie for/
Malcolm T. Widmann, Chief Operations Branch 1 Division of Reactor Safety Docket Nos. 50-348, 50-364 License Nos. NPF-2, NPF-8
Enclosure:
Materials Request List cc: Distribution via Listserv
ML14035A538 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRS RII:DRS SIGNATURE RA VIA EMAIL RA VIA EMAL NAME CAPEHART WIDMANN DATE 1/31/2014 1/31/2014 E-MAIL COPY YES NO YES NO Letter to T. A. Lynch from Malcolm T. Widmann dated January 31, 2014.
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION - JOSEPH M. FARLEY NUCLEAR PLANT DISTRIBUTION:
C. Evans, RII EICS L. Douglas, RII EICS RIDSNRRDIRS PUBLIC RidsNrrPMFarley Resource
Materials Request List The items listed below are necessary to support the Licensed Operator Requalification Program inspection (IP-71111.11) in March 2014 at the Farley Nuclear Plant. Items listed under In-office inspection material, must be received in the NRC Region II office by February 17, 2014. Items listed under On-site inspection material, should be ready for review upon arrival of the inspectors on March 10, 2014.
A. In-office inspection material:
- 1. Complete list of all licensed individuals (active and inactive; RO and SRO) including license restrictions.
- 2. Copy of an Organizational Chart for the training department including simulator staff.
- 3. Spreadsheets and/or test outlines which show the usage of written examination questions, JPMs, and simulator scenarios (i.e. outlines/sample plans).
- 4. Copy of the weekly examination schedules for the weeks that the 2014 annual operating exams will be administered, including a list of personnel scheduled for testing the week of March 10, 2014.
- 5. Copies of the written examinations that were, or will be, administered for the 2014 biennial requalification examination (for all weeks), including all re-take examinations, if applicable (exam security related item).
- 6. Ten (10) job performance measures (JPMs), both simulator and in-plant, and six (6) simulator scenarios associated with the current annual operating test. The scenarios to be reviewed should include those that will be administered the week of March 10, 2014, with any remaining JPMs and scenarios reviewed selected from other weeks of the annual operating test (exam security related item).
- 7. Self-assessment reports, corrective action reports, and Licensee Event Reports, written since the last requalification inspection, resulting from, or concerning human performance errors, including any examination security issues.
- 8. A copy of site procedure(s) governing the conduct (process and content) of license operator requalification training (classroom and simulator), examination development/administration, remedial training, and examination security.
- 9. A copy site procedure(s) governing simulator configuration control, maintenance, and fidelity, including all testing methods used to fulfill ANSI/ANS-3.5-1985 requirements.
- 10. Copy of the program evaluation of the previous biennial requalification cycle.
B. On-site inspection material:
- 1. Requalification training attendance records for the current biennial training cycle.
- 2. Examination results since last requalification inspection (weekly operating & written examinations), copies of examinations with pass/failure rates outside the average.
Enclosure
2
- 3. Simulator scenarios and JPMs (in-plant and simulator) that have been, or will be, administered for this requalification exam (exam security related item).
- 4. All training feedback forms since the last requalification inspection.
- 5. Documentation regarding all remedial training conducted for examination failures since the last requalification inspection.
- 6. Complete list of all individuals that reactivated their licenses since the last requalification inspection.
- 7. Records associated with license reactivation, including:
- a. Documentation of time on shift under instruction.
- b. Security system and HP/dosimetry records for plant areas toured by reactivating individual and accompanying licensed operator.
- 8. Records providing documentation of maintenance of active license status (time on shift) for all licensed operators since last requalification inspection.
- 9. Medical records for all licensed (active and inactive) operators.
- 10. Simulator maintenance and testing records, including:
- a. List of all open simulator discrepancies.
- b. List of all simulator discrepancies closed within the past 12 months.
- c. List of simulator performance tests.
- d. Simulator performance testing records and associated documentation.