(l Xcel Energy NOV 2 5 2013 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Unit 2 Docket 50-306 Renewed License No. DPR-60 L-PI-13-107 Prairie Island Nuclear Generating Plant (PINGP) Readiness for 95001 Inspection
Reference:
Letter from the Nuclear Regulatory Commission to Mr. Jim Lynch, Site Vice President, Prairie Island Nuclear Generating Plant, dated February 25, 2013, "Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Unit 2" (ADAMS Accession Number ML13056A511)
In December 2012, the Unit 2 Mitigating System Performance Indicator (MSPI) for Emergency Alternating Current (AC) power systems at PINGP changed from green to white.
The NRC requested that Northern States Power Company, a Minnesota corporation, doing business as Xcel Energy (hereafter "NSPM"), provide notification when PINGP is prepared to undergo the supplemental 95001 inspection. This letter provides notification to the NRC that NSPM is prepared for the inspection.
If there are any questions or if any additional information is needed, please contact Ms.
Ingrid Nordby, P.E., at 651-267-1755.
Summary of Commitments This letter contains no new commitments and no revisions to existing commitments
!/.,_;~
~Davison Site Vice President, Prairie Island Nuclear Generating Plant Northern States Power Company - Minnesota cc:
Regional Administrator, Region Ill, USNRC
Document Control Desk Page 2 Project Manager, Prairie Island Nuclear Generating Plant, USNRC Resident Inspector, Prairie Island Nuclear Generating Plant, USNRC