Ltr - Assessment Follow-Up for Prairie Island Nuclear Generating Plant, Unit 2
ML13056A511
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 02/25/2013
From: Stephanie West
Division Reactor Projects III
To: Jeffery Lynch
Northern States Power Co
References
Download: ML13056A511 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 February 25, 2013 Mr. James E. Lynch Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089

SUBJECT:

ASSESSMENT FOLLOW-UP LETTER FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 2

Dear Mr. Lynch:

As a result of its quarterly review of plant performance, which was completed on January 31, 2013, the Nuclear Regulatory Commission (NRC) updated its assessment of Prairie Island Nuclear Generating Plant, Unit 2. The NRCs evaluation consisted of a review of performance indicators and inspection results. This letter informs you of the NRCs assessment of your facility. This letter supplements, but does not supersede, the mid-cycle letter issued on September 4, 2012.

The NRCs review of Prairie Island Nuclear Generating Plant, Unit 2 identified that the Emergency A/C Power Mitigating Systems Performance Indicator has crossed the Green-to-White threshold. Specifically, during a baseline inspection review, the resident inspectors questioned the data provided in your January 21, 2013, performance indicator submittal.

Following this questioning, your staff identified that the Unit 2 D6 emergency diesel generator fan failure, occurring in December 2012, was not included in the most recent performance indicator data submittal to the NRC.

On February 18, 2013, your staff submitted revised data to the NRC for the Unit 2 Emergency A/C power Mitigating Systems Performance Indicator. The NRC completed a review of this data on February 20, 2013, and concluded that performance indicator was appropriately classified as White. Therefore, Unit 2 will transition from the Licensee Response column to the Regulatory Response column of the NRC Action Matrix as of the 4th quarter of 2012. The NRC will be in contact with your staff to discuss planning and scheduling activities in anticipation of an Inspection Procedure 95001 inspection for this performance indicator.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Kenneth Riemer at (630) 829-9628 with any questions you have regarding this letter.

Sincerely,

/RA/

Steven West, Director Division of Reactor Projects Docket Nos. 50-282; 50-306;72-010 License Nos. DPR-42; DPR-60; SNM-2506 cc: Distribution via ListServ'

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Kenneth Riemer at (630) 829-9628 with any questions you have regarding this letter.

Sincerely,

/RA/

Steven West, Director Division of Reactor Projects Docket Nos. 50-282; 50-306;72-010 License Nos. DPR-42; DPR-60; SNM-2506 cc: Distribution via ListServ' DISTRIBUTION:

John Cassidy RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3-1 Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Allan Barker Christine Lipa Carole Ariano Linda Linn DRPIII DRSIII Tammy Tomczak ROPassessment.Resource@nrc.gov DOCUMENT NAME: Prairie Island Follow Up Letter Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E

RIII NAME MZiolkowski for KRiemer:rj SWest DATE 2/22/13 2/25/13 OFFICIAL RECORD COPY