November 5, 2013 Ms. Lesa Hill, Chairman Boiling Water Reactor Owners Group Southern Nuclear Operating Company PO Box 1295 Bin B048 Birmingham, AL 35201-1295
SUBJECT:
FEEDBACK ON BOILING WATER REACTOR OWNERS GROUP DRAFT REPORT BWROG-ECCS-TA08-001 DOCUMENTING DAMAGE PRESSURE AND ZONE OF INFLUENCE FOR BOILING WATER REACTOR COATINGS
Dear Ms. Hill:
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the Boiling Water Reactor (BWR) Owners Group (BWROG) draft report BWROG-ECCS-TA08-001, Damage Pressure and Zone of Influence for BWR Coatings, and offers the following feedback:
The NRC staff reviewed the methodology used by the BWROG to determine the coatings Zone of Influence (ZOI) and determined that the methodology used was appropriate. The NRC staff did not verify the calculations performed in the report, but validated that the results were consistent with previously performed ZOI calculations for BWR and pressurized water reactor (PWR) thermal hydraulic conditions. Therefore, the staff concluded that the ZOIs determined in the report are representative of destruction pressures consistent with those used for PWRs and that the ZOI sizes are properly defined for BWR conditions.
However, the BWROG has not shown that its original calculation for coatings amount or mass is bounding or representative of the amount that would be generated within the volume defined by the ZOIs calculated for BWRs. The report did not state how the ZOIs would be used to evaluate the amount of coatings debris that may be generated during a loss-of-coolant accident.
The NRC staff was unable to determine whether the default Utility Resolution Guide amount of coating debris bounds the potential for coating debris generation based on the new ZOIs. Therefore, the issue regarding the assumptions on coatings amounts remains open.
L. Hill If you have any questions regarding the above staff feedback, please contact Joe Golla at 301-415-1002 or at joe.golla@nrc.gov.
Sincerely,
/RA/
Anthony J. Mendiola, Chief Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 691 cc: See next page
ML13280A347 NRR-106 OFFICE PLPB/PM PLPB/LA ESGB/BC DSS/SSIB/BC(A)
PLPB/BC NAME JGolla DBaxley GKulesa (EWong for)
JStang AMendiola DATE 10/17/2013 10/9/2013 10/25/2013 10/28/2013 11/5/2013 Boiling Water Reactor Owners Group Project No. 691 cc:
BWROG Chairman Lesa Hill Southern Nuclear Operating Company PO Box 1295 Bin B048 Birmingham, AL 35201-1295 lphill@southernco.com BWROG Project Manager Michael Iannantuono GE-Hitachi Nuclear Energy PO Box 780 M/C A-70 3901 Castle Hayne Road Wilmington, NC 28402 Michael.iannantuono@ge.com BWROG Program Manager Kenneth McCall GE-Hitachi Nuclear Energy PO Box 780 M/C A-70 3901 Castle Hayne Road Wilmington, NC 28402 Kenneth.mccall@ge.com BWROG ECCS Suction Strainers Committee Chairman Steve Scammon slscammon@energy-northwest.com