Requal Program Inspection 60 Day Letter
ML13267A005
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 09/23/2013
From: Diane Jackson
Operations Branch I
To: George Gellrich
Calvert Cliffs, Constellation Energy Nuclear Group
Jackson D
References
Download: ML13267A005 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 September 23, 2013 Mr. George H. Gellrich, Vice President Calvert Cliffs Nuclear Power Plant, LLC Constellation Energy Nuclear Group, LLC 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION CALVERT CLIFFS POWER PLANT UNITS 1 AND 2

Dear Mr. Gellrich:

In a telephone conversation on September 6, 2013, Mr. D. Silk, Senior Operations Engineer, and Mr. N. Lavato, Principal Operations Instructor/Lead Exam Author, made arrangements for the U.S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at Calvert Cliffs, Units 1 and 2. The inspection is planned for the week of November 18, 2013, which coincides with the scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with 10 CFR 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: 1) an index or summary of condition reports written in the past two years in which licensed operator errors were determined to be the root or contributing cause; 2) an index or summary of condition reports written in the past two years on simulator performance problems; 3) an index or summary of simulator performance test results in the past two years; and 4) the examination schedule, sample plan, written examinations and operating test scheduled for the week of the inspection to the NRC by November 4, 2013.

Mr. Lavato has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S.

Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, D.C.

20503.

G. Gellrich 2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. D. Silk at (610) 337-5372.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-317 and 50-318 cc: Distribution via ListServ

G. Gellrich 2 The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number. In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system, Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. D. Silk at (610) 337-5372.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-443 cc: Distribution via ListServ Distribution w/encl:

W. Dean, RA E. Torres, DRP, RI D. Lew, DRA C. Fragman, DRP, AA D. Roberts, DRP V. Campbell, RI, OEDO M. Scott, DRP RidsNrrPMCalvertCliffs Resource R. Lorson, DRS RidsNrrDorlLpl1-1 Resource J. Rogge, DRS ROPreports Resource D. Schroeder, DRP DRS Operations Branch Chief A. Rosebrook, DRP D. Silk, DRS B. Scrabeck, DRP D. Jackson, DRS S. Kennedy, DPR, SRI C. Bixler, DRS (OL Facility File ADAMS PKG: ML13164A229 ADAMS NO.: ML13267A005 DOCUMENT NAME: G:\DRS\Operations Branch\Silk\Requal FY14-CC Nov13\60dayrpi.doc Publicly Available Non-Sensitive SUNSI Review Non-Publicly Sensitive Available OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CBixler DSilk DJackson DATE 09/13/2013 09/ /2013 09/ /2013 OFFICIAL RECORD COPY