ML13262A339
| ML13262A339 | |
| Person / Time | |
|---|---|
| Site: | Diablo Canyon |
| Issue date: | 09/19/2013 |
| From: | Catherine Kanatas NRC/OGC |
| To: | Abramson P, Karlin A, Nicholas Trikouros Atomic Safety and Licensing Board Panel |
| SECY RAS | |
| References | |
| RAS 25055, 50-275-LR, 50-323-LR, ASLBP 10-900-01-LR-BD01 | |
| Download: ML13262A339 (3) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 September 19, 2013 Administrative Judge Administrative Judge Alex S. Karlin, Chair Paul B. Abramson Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Mail Stop: T-3F23 Washington, DC 20555-001 Washington, DC 20555-0001 Administrative Judge Nicholas G. Trikouros Atomic Safety and Licensing Board Panel Mail Stop: T-3F23 Washington, DC 20555-0001 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)
Docket Nos. 50-275-LR and 50-323-LR RE: Projected Schedule for Completion of the Safety and Environmental Evaluations
Dear Administrative Judges:
Pursuant to the Boards Revised Scheduling Order of November 19, 2012, this letter informs the Board of the NRC Staffs current milestone schedule for the Diablo Canyon Units 1 and 2 license renewal safety evaluation and environmental review. In light of Pacific Gas and Electric Companys (PG&E) status report filed with the Board on September 10, 2013, the Staff expects to issue the DSEIS in September of 2014. Subsequent to issuing the DSEIS, the Staff expects to finalize its safety and environmental reviews, to include issuance of the supplemental environmental impact statement (SEIS) and any necessary supplements to the safety evaluation report, by the end of April 2015. This estimate is based on PG&Es intent to issue a written final report on the seismic studies in June 2014, as stated in PG&Es Updated Best Estimate Schedule for Seismic Studies attached to PG&Es September 10, 2013 Status Report issued to the Board.
Sincerely,
/Signed (electronically) by/
Catherine Kanatas Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop O15-D21 Washington, DC 20555 Telephone: (301) 415-2321 E-mail: Catherine.Kanatas@nrc.gov Date of signature: September 19, 2013
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )
)
PACIFIC GAS AND ELECTRIC COMPANY ) Docket No. 50-275-LR/ 50-323-LR
)
(Diablo Canyon Nuclear Power Plant, ) ASLBP No. 10-900-01-LR-BD01 Units 1 and 2) )
CERTIFICATE OF SERVICE Pursuant to 10 C.F.R. § 2.305 (revised), I hereby certify that a copy of the foregoing letter PROJECTED SCHEDULE FOR COMPLETION OF THE SAFETY AND ENVIRONMENTAL EVALUATIONS, dated September 19, 2013, has been served upon the Electronic Information Exchange, the NRCs E-Filing System, in the above captioned proceeding, this 19th day of September, 2013.
/Signed (electronically) by/
Catherine Kanatas Counsel for the NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop O15-D21 Washington, DC 20555 Telephone: (301) 415-2321 E-mail: Catherine.Kanatas@nrc.gov Date of signature: September 19, 2013