UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 EA-13-058 Mr. Kevin Mulligan Site Vice President Grand Gulf Nuclear Station Entergy Operations, Inc.
P.O. Box 756 Port Gibson, MS 39150 October 23, 2013
SUBJECT:
GRAND GULF NUCLEAR STATION, PREDECISIONAL ENFORCEMENT CONFERENCE
SUMMARY
Dear Mr. Mulligan:
On July 16, 2013, the U.S. Nuclear Regulatory Commission (NRC) staff held a Predecisional Enforcement Conference (PEC) with you and members of your staff at NRC Headquarters in Rockville, Maryland. The NRC requested that Entergy Operations, Inc., participate in the PEC in a letter describing an apparent violation of 10 CFR 54.13, "Completeness and Accuracy of Information," related to responses from your staff to several requests for additional information by the NRC. That letter, dated June 11, 2013, is available from the NRC's website, www.nrc.gov, under the Agencywide Documents Access and Management System Accession No. ML13133A229. In addition, on August 1, 2013, the NRC staff conducted a telephone conference with you and members of your staff, in which you provided additional information to the NRC. A brief summary of the PEC proceedings and the telephone conference is enclosed.
No response to this letter is required. An administrative oversight delayed the issuance of this letter. Please contact John Daily of my staff at 301-415-3873 if you have any questions regarding this matter.
Docket Nos. 50-416
Enclosure:
PEC Summary cc: Listserv
Package ML13239A197 Letter ML13238A396 Attendance List ML13238A397 *concurrence via email OFFICE PM:DLR/RAPB
- LA:DLR/RPB2*
BC:DLR/RAPB OE NAME JGavula YEdmonds SBioom RCarpenter DATE 9/11/13 9/11/13 9/12/13 9/17/13
Letter to Mr. Kevin Mulligan from J. Lubinski dated October 23, 2013
SUBJECT:
GRAND GULF NUCLEAR STATION, PREDECISIONAL ENFORCEMENT CONFERENCE
SUMMARY
DISTRIBUTION:
E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrDraApla Resource ELeeds JUhle DOorman HNieh A Howe DWillis MHalter RCarpenter JLubinski MGalloway DPelton SBioom JGavula LLund DORLPM (Alan Wang)
RBrowder HGepford CMaier GMiller JCiark JQuichocho RSmith BRice
PREDECISIONAL ENFORCEMENT CONFERENCE
SUMMARY
ENTERGY:
Entergy Operations, Inc.
FACILITY:
Grand Gulf Nuclear Station (GGNS)
LICENSE NO.
Facility Operating License No.: NPF-29 DOCKET NO:
50-416 EA-13-058 On July 16, 2013, representatives of Entergy Operations, Inc. (Entergy) met with NRC personnel at NRC Headquarters located in Rockville, Maryland, to discuss the apparent violation of 10 CFR 54.13 in three responses to NRC requests for additional information identified in an NRC letter dated June 11, 2013. The conference was held at the request of the NRC. The requests for additional information related to the ongoing reviews of the Grand Gulf license renewal application and addressed two of the aging management programs in the application.
Entergy presented a summary of the causes of the apparent violation and its corrective actions.
The presentation material used by Entergy is available from the NRC's website, www.nrc.gov, under the Agencywide Documents Access and Management System (ADAMS) Accession No. ML13199A350. The accession number can be entered in the search box at the upper right of the home page in order to locate the document. Entergy acknowledged the validity of the three examples of the apparent violation, but did not state its opinion on the significance of the apparent violation.
The purpose of this conference was to obtain information from Entergy to assist the NRC in determining the appropriate enforcement decision. As noted in its presentation, Entergy had not yet finalized its root cause evaluation. In addition, based on discussions during the conference, Entergy needed to confirm additional information before it would provide its perspective on the significance of the apparent violation. At the conclusion of the conference, the NRC requested Entergy to provide additional information, before making a final enforcement decision. The NRC staff subsequently conducted a telephone conference with Entergy, on August 1, 2013, during which it provided the additional information which was requested by the NRC at the PEC. The information provided by Entergy during the follow-up teleconference is available at ADAMS Accession No. ML13221A272.
The list of people that attended the Predecisional Enforcement Conference and the subsequent telephone conference is attached to this summary. Additional members of the public participated by teleconference. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this summary and its attachment will be made available to the public.
Attachment:
Attendance List ENCLOSURE
UNITED STATES NUCLEAR REGULATORY COMMISSION MEETING ATTENDANCE FORM
Subject:
Grand Gulf Nuclear Station Predecisional Enforcement Conference Date: July 16, 2013 Location: NRC HQ OWFN Room 0-1384 NAME ORGANIZATION Jennifer Uhle*
NRC/NRR David Pelton*
NRC/NRR/DLR Melanie Galloway*
NRC/NRRIDLR Steve Bloom NRC/NRRIDLR Jim Gavula*
NRC/NRR/DLR John Daily*
NRC/NRR/DLR Mandy Halter*
NRC/NRRIDIRS Allen Howe NRC/NRRIDIRS Rani Franovich*
NRC/NRRIDIRS Alan Wang NRC/NRR/DORL Rob Carpenter*
NRC/OE Jeff Clark*
NRC/RIV (via telephone)
Jesse Quichocho NRC/RIV (via telephonej Rachel Browder NRC/RIV (via telephone)
Kevin Mulligan*
Entergy, Site Vice President GGNS Christina Perino*
Entergy, Director, Nuclear Safety Assurance, GGNS Chris Robinson*
Entergy, Licensing Manager, GGNS Linda Patterson*
Entergy, Manager Eng Prog & Components, GGNS Randy Douet Entergy, Vice Pres Nuclear Business Development Garry Young*
Entergy, Director License Renewal Services Alan Cox*
Entergy, License Renewal Services Ted Ivy*
Entergy, License Renewal Services Bryan Ford*
Entergy, Senior Manager Licensing Sarah Kovaleski Ameren (via telephone)
Rich Scarborough Entergy (via telephone)
Eric Blocher STARS (via telephone)
- Indicates individuals that also participated in the telephone conference on August 1, 2013.