Response to Sections Iii.A, Iii.B, and Iii.C of the Order Related to Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation
ML13234A342
Person / Time
Site: Pilgrim
Issue date: 08/12/2013
From: Dent J
Entergy Nuclear Operations
To:
Document Control Desk, NRC/NMSS/SFST
References
2.13.068, EA-13-132
Download: ML13234A342 (3)


Text

a

'~

En tergy Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 John A. Dent, Jr.

Site Vice President August 12, 2013 Attn: Document Control Desk Director, Division of Spent Fuel Storage and Transportation, Office of Nuclear Material Safety and Safeguards, U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station Docket No. 50-293 License No. DPR-35 Response to Sections Ill.A, Ill.B, and IIl.C of the Order Related to Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation EA-1 3-132, "Issuance of Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation", dated July 23, 2013

REFERENCE:

ENTERGY LETTER: 2.13. 068

Dear Sir or Madam,

This letter provides Entergy Operations Inc., (hereafter, Entergy) response to the subject Order for Implementation of Additional Security Measures and Fingerprinting for Unescorted Access for Pilgrim Nuclear Power Station Independent Spent Fuel Storage Installation, dated July 23, 2013.

As ordered, Entergy hereby provides responses to the Sections Ill.A, Ill.B, and III.C of the Order as follows:

Response to Section Ill.A:

The proposed Pilgrim Nuclear Power Station (PNPS)

Independent Spent Fuel Storage Installation (ISFSI) is planned to be located inside the PNPS Protected Area, as such Entergy will comply with the requirements of Attachments 1 and 2 of the Order within 365 days from the date of the Order or 90 days before the first day that spent fuel is initially placed in the ISFSI.

Paae 2 of 2. Enterav Letter No 2.13.068 Response to Section Ill.B:

This Section is not applicable for Pilgrim Nuclear Power Station in light of affirmative response to Section III.A.

Response to Section I11.C: Entergy will comply with the requirements of Attachments 1 and 2 of the Order for the Pilgrim ISFSI within the schedule stated in the Response to Section III.A. Additionally, Entergy will notify the NRC upon achieving full compliance with the requirements of Attachments 1 and 2 of the Order.

Since the PNPS ISFSI is located inside the Protected Area, all employees and contractors having access to the Pilgrim Station and ISFSI will comply with the Access Authorization and Fingerprinting requirements.

This letter makes specific regulatory commitments, as identified in Attachment 1 to this letter.

If you have any questions concerning the above subject matter, please contact Pilgrim Security Manager, Mr. David Burke at (508) 830-8320 or Pilgrim Licensing Manager, Mr. Joseph Lynch at (508) 830-8403.

Sincerely, n A. Dent, Jr Site Vice President : Regulatory Commitments (1 page) cc:

Ms. Catherine Haney, Director, Office of Nuclear material safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Mr. Richard Guzman, Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North O-8C2 11555 Rockville Pike Rockville, MD 20852 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 NRC Resident Inspector Pilgrim Nuclear Power Station

ATTACHMENT 1 To Entergy Letter No. 2.13.068

Reference:

EA-13-132. NRC Order Modifvina Pilarim License Related to PNPS ISFSI.

dated July 23, 2013 Reaulatorv Commitments Commitment No.

Description Compliance Schedule Implements the requirements of By July 22, 2014 or 90 days before LR-LAR-2013-00227-01 Attachments 1 and 2 of the first day spent fuel is initially placed Referenced Order in the ISFSI, whichever occurs first.

Notify the NRC NMSS upon By July 22, 2014 or 90 days before LR-LAR-2013-00227-02 achieving full compliance with first day spent fuel is initially placed Attachments 1 and 2 of the in the ISFSI, whichever occurs first.

Referenced Order