UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 - EXTENSION OF BRANCH CHIEF REASSIGNMENT

Dear Sir or Madam:

By letter dated May 31,2013 (Agencywide Documents Access and Management System No. ML13136A093), the U. S. Nuclear Regulatory Commission issued a Branch Chief reassignment letter for Licensing Branch 1-1 in the Division of Operating Reactor licensing of the Office of Nuclear Reactor Regulation.

This letter is to inform you that Mr. Robert Beall's assignment as Acting Branch Chief for Licensing Branch 1-1 has been extended from August 24,2013 to November 16,2013.

Mr. Beall may be reached at 301-415-3874 or via e-mail at Robert.Beall@nrc.gov.

Sincerely,

(/)

.-/

\\L-...

~

G-,~'<~_l Louise Lund, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-247 and 50-286 cc: Distribution via Listserv

August 26, 2013 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 - EXTENSION OF BRANCH CHIEF REASSIGNMENT

Dear Sir or Madam:

By letter dated May 31, 2013 (Agencywide Documents Access and Management System No. ML13136A093), the U. S. Nuclear Regulatory Commission issued a Branch Chief reassignment letter for Licensing Branch 1-1 in the Division of Operating Reactor Licensing of the Office of Nuclear Reactor Regulation.

This letter is to inform you that Mr. Robert Beall's assignment as Acting Branch Chief for Licensing Branch 1-1 has been extended from August 24,2013 to November 16,2013.

Mr. Beall may be reached at 301-415-3874 or via e-mail at Robert.Beall@nrc.gov.

Sincerely, IRA!

Louise Lund, Deputy Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-247 and 50-286 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC RidsNrrPMlndianPoint Resource RidsNrrDorl Resource RidsRegion1 MailCenter Resource LPL1-1 r/f RidsNrrLAKGoldstein Resource RidsDor1LPLI-1 Resource RidsOd Resouce ADAMS Accession No.: ML132198009 ICE NRRlLPLI-1/PM NRRlLPLI-1/LA NRRlLPLI-1/BC NRRlDORLlDD DPickett KGoldstein RBeall LLund 08/12/13 08/13/13 08/13/13 8/26/13 OFFICIAL RECORD COpy