MONTHYEARML24281A0072024-10-0202 October 2024 NRR E-mail Capture - Acceptance Review Results for the Sequoyah License Amendment Request to Modify the FHA Analysis, Tech Spec TS 3.9.4 and Tech Spec 3.3.6 (L-2024-LLA-0117) ML24274A2762024-09-24024 September 2024 Email from K.Green to S.Hughes, Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, Hydrologic LAR to Revise the UFSAR ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24215A3152024-07-24024 July 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-276-A, Revision 2 TS 3.8.1, AC Sources ML24177A1412024-06-11011 June 2024 NRR E-mail Capture - Audit Plan Related to Review of the Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, LAR to Revise Technical Specification Table 3.3.2-1 Function 5 ML24157A3152024-06-0303 June 2024 2024 Sequoyah Commercial Grade Dedication Inspection Information Request ML24152A1542024-05-31031 May 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-03 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24156A0062024-05-22022 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Recapture Low-Power Testing Time ML24128A1802024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review for Sequoyah License Amendment Request to Modify TS 3.8.1 and TS 3.8.2 (L-2024-LLA-0047) ML24130A0132024-05-0707 May 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.7.11 for MCR Chiller Completion Time ML24123A0882024-05-0202 May 2024 NRR E-mail Capture - Correction Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24122B4872024-04-30030 April 2024 NRR E-mail Capture - Acceptance Review Results for the Browns Ferry, Sequoyah, and Watts Bar License Amendment Request to Revise TS 5.4.1 or 5.7.1 (L-2024-LLA-0039) ML24144A2322024-04-20020 April 2024 Tennessee Multi-Sector Permit (Tmsp), 2024 Annual Discharge Monitoring Report for Outfalls SW-3, SW-3, and SW-9 ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24082A0662024-04-17017 April 2024 Email to Stuart Rymer on Exemption Decision for Watts Bar ML24082A0682024-04-10010 April 2024 Email to Stuart Rymer Re_ Availability of EA-FONSI for Watts Bar ML24100A8392024-04-0909 April 2024 Response from State of Tn Regarding Review of Environmental Assessment for Watts Bar Exemption Request ML24100A8402024-04-0808 April 2024 Email to State of Tn Requesting Review of Environmental Assessment for Watts Bar Exemption Request ML24074A4252024-03-14014 March 2024 NRR E-mail Capture - Sequoyah Hydrologic Analysis License Amendment Request - Notification of Change to Estimated Completion and Hours ML24071A0982024-03-0707 March 2024 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate ML24059A4052024-02-28028 February 2024 Document Request for Sequoyah Nuclear Plant - Radiation Protection Inspection - Inspection Report 2024-02 ML24058A0962024-02-26026 February 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant License Amendment Request to Revise UFSAR for Hydrologic Analysis ML24053A0302024-02-21021 February 2024 NRR E-mail Capture - Request for Steam Generator (SG) Tube Inspection Call for Sequoyah, Unit 1 ML24047A2792024-02-15015 February 2024 RAI Related to the Exemption Request for 10 CFR 37.11 ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24045A1002024-02-13013 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Sequoyah Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML24033A0562024-02-0101 February 2024 NRR E-mail Capture - Correction Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Adopt TSTF-427-A, Revision 2 Regarding Degraded Barriers ML24032A0202024-01-31031 January 2024 NPDES Biocide/Corrosion Treatment Plan Annual Report, Cy 2023 ML24036A0132024-01-23023 January 2024 NRR E-mail Capture - Acceptance Review Results for Sequoyah and Watts Bar Nuclear Plants, License Amendment Request to Revise TS Table 3.3.2-1, Function 5, Turbine Trip and Feedwater Isolation ML24022A2592024-01-22022 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Revise TS LCO 3.8.2 to Remove Note C-S Diesel Generator ML24016A0762024-01-16016 January 2024 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2 - License Amendment Request to Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications ML23347A0642023-12-13013 December 2023 12-13-23 Email from Kimberly Green to Wells, Russell, Subject: Results of NRC SUNSI Review of Watts Bar Nuclear Plant Dual-Unit UFSAR, Amendment 5 ML23334A0932023-11-28028 November 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Surveillance Requirement 3.9.5.1 to Reduce RHR Flow Rate During Mode 6 ML23319A1662023-11-0202 November 2023 NRR E-mail Capture - Acceptance Review Results for Browns Ferry Nuclear Plant, Sequoyah Nuclear Plant, and Watts Bar Nuclear Plant, Exemption Request Related to 10 CFR 37.11(c)(2) ML23275A0272023-09-29029 September 2023 Submittal of Discharge Monitoring Report (DMR) Quality Assurance Study 43 Final Report 2023 ML23254A2872023-09-11011 September 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise TS Table 1.1-1 Re Number of Required Rvh Closure Bolts ML23236A2562023-08-24024 August 2023 NRR E-mail Capture - Acceptance Review Results for the Sequoyah and Watts Bar License Amendment Request to Adopt TSTF-567 (L-2023-LLA-0106) ML23191A8672023-07-10010 July 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1 and 2, License Amendment Request to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23165A2862023-06-14014 June 2023 Tennessee Multi-Sector Permit (Tmsp), 2023 Annual Discharge Monitoring Report for Outfalls SW-1, SW-16, SW-17, SW-18, SW-19, and SW-21 ML23150A2472023-05-25025 May 2023 NRR E-mail Capture - Audit Plan Related to Review of the Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23116A1492023-04-21021 April 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Increase the Number of Tritium Producing Burnable Absorber Rods ML23075A0032023-03-13013 March 2023 NRR E-mail Capture - Acceptance Review Results for Watts Bar, Units 1, 2, and 3, License Amendment Request to Revise TS 3.7.11, Required Actions A.1 and E.1 Footnotes Re Date for the Modification ML23072A0722023-03-10010 March 2023 NRR E-mail Capture - (External_Sender) State Consultation - Sequoyah Nuclear Plant, Units 1 and 2; and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23058A1312023-02-27027 February 2023 FW: TVA Intentions on EA-22-129 ML23062A5952023-02-27027 February 2023 Staff follow-up Questions to Tva'S 12/19/2022 Response of the Staff'S Rsi Regarding 08/04/2022 SQN Exemption Request ML23052A0792023-02-21021 February 2023 NRR E-mail Capture - Acceptance Review for Browns Ferry and Sequoyah License Amendment Request to Adopt TSTF-541 ML23046A3552023-02-15015 February 2023 Annual Water Withdrawal Report 2022 2024-09-24
[Table view] |
Text
NRR-PMDAPEm Resource From: Lingam, Siva Sent: Tuesday, July 23, 2013 3:33 PM To: Mackaman, Clyde Douglas (cdmackaman@tva.gov)
Cc: Broaddus, Doug; McMurtray, Anthony; Hon, Andrew; Uribe, Juan
Subject:
SQN 1 & 2 and WBN RAIs on TVA's Letter Dated January 18, 2013 (ADAMS Accession No. ML13025A262) - HESCO Flood Barriers and Earthen Embankments Attachments: RAIs for Sequoyah and Watts Bar CAL Supplemental Info on HESCO Barriers ....docx Attached please find our Mechanical and Civil Engineering Branch official RAIs on the subject letter. Please provide the responses by August 31, 2013.
Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager (NRR/DORL/LPL2-2)
Sequoyah Nuclear Plant St. Lucie Plant Location: O8-D5; Mail Stop: O8-G9a Telephone: 301-415-1564; Fax: 301-415-1222 E-mail address: siva.lingam@nrc.gov 1
Hearing Identifier: NRR_PMDA Email Number: 773 Mail Envelope Properties (Siva.Lingam@nrc.gov20130723153200)
Subject:
SQN 1 & 2 and WBN RAIs on TVA's Letter Dated January 18, 2013 (ADAMS Accession No. ML13025A262) - HESCO Flood Barriers and Earthen Embankments Sent Date: 7/23/2013 3:32:32 PM Received Date: 7/23/2013 3:32:00 PM From: Lingam, Siva Created By: Siva.Lingam@nrc.gov Recipients:
"Broaddus, Doug" <Doug.Broaddus@nrc.gov>
Tracking Status: None "McMurtray, Anthony" <Anthony.McMurtray@nrc.gov>
Tracking Status: None "Hon, Andrew" <Andrew.Hon@nrc.gov>
Tracking Status: None "Uribe, Juan" <Juan.Uribe@nrc.gov>
Tracking Status: None "Mackaman, Clyde Douglas (cdmackaman@tva.gov)" <cdmackaman@tva.gov>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 454 7/23/2013 3:32:00 PM RAIs for Sequoyah and Watts Bar CAL Supplemental Info on HESCO Barriers ....docx 21873 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
REQUESTS FOR ADDITIONAL INFORMATION (RAIs)
TENNESSEE VALLEY AUTHORITY (TVA)
SEQUOYAH NUCLEAR PLANT (SQN), UNITS 1 AND 2 AND WATTS BAR NUCLEAR PLANT (WBN), UNIT 1 RELATED TO THE REVIEW OF POTENTIAL BREACHES OF HESCO FLOOD BARRIERS &
EARTHEN EMBANKMENTS AFFECTING THE UPDATED HYDRO ANALYSIS RESULTS (DOCKET NOS. 50-327, 50-328 and 50-390)
Reference:
Letter from Joseph W. Shea of TVA to NRC, Potential for breaches of HESCO Modular Flood Barriers and Earthen Embankments Affecting the Updated Hydrologic Analysis Results for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Unit 1 dated January 18, 2013 (ADAMS Accession Number ML13025A262).
Mechanical and Civil Engineering Branch (EMCB)-RAI-1 With regards to the Computational Fluid Dynamics (CFD) Model for the Fort Loudoun and Tellico reservoirs, the Reference notes that the CFD model was developed to determine the likely movement that an uncontrolled barge would have during a Probable Maximum Flood (PMF) event. However, the Reference concludes, in the CFD model analysis section, that it is possible that the HESCO barriers could be approached by a simulated barge trajectory, but that the results should be considered indeterminate based on particle tracking results.
Please provide additional information regarding the particle seed location and the use of other post-processing results that lead you to reach this conclusion. Regarding the seed location, the response should describe if alternate seed locations were considered in the reservoir.
Regarding other visualization/post-processing methods, please state if inverse particle tracking methods were considered for use. For example, inverse particle tracking techniques could be used to determine where the particles (i.e., barge surrogates) would need to originate (i.e.,
moored and released) in order to have them approach the HESCO barriers during the PMF event.
EMCB-RAI-2 The Reference notes that no bathymetry data was available for the Fort Loudoun/Tellico channel, between the two reservoirs when developing the model, and therefore the channel bottom was estimated to be 10 meters (m) below the pool level. Due to the high importance of this location in relation to the case model studies performed as part of the analysis, please provide additional technical information that documents the basis for selecting 10m as a bathymetry estimate between the channels. The response should clarify if a sensitivity study was performed as means of verifying the estimate and provide reasonable assurance that the bathymetry assigned to the model is conservative and appropriate for use.
EMCB-RAI-3 The Reference notes that the barges were modeled using a sphere whose wetted area equals that of a 195 foot(ft) barge with a width of 35ft and draft of 6ft. Furthermore, the Reference notes that the density of the sphere matches the laden weight of a barge weighing 1000 tons.
The simulations use 1000-ton large objects to represent the barges. The 195ft by 35ft dimensions are typical for a single barge. However, commercial barges are frequently transported in groups and this has been acknowledged by TVA. Please clarify if the barges, once stationed at the docks, are also tied together. If a group of barges were not considered for the model, please provide additional information that documents why this approach was acceptable.
EMCB-RAI-4 In Figure 19 of the Reference, it is not clear what the caption or the image is trying to convey.
The caption states that 17% of the modeled sphere beaches. If this is assumed, then 83% of the modeled sphere would then continue in the flow path. However, a typical barge that is flowing uncontrolled would flow as a unit. Please clarify the perceived discrepancy in this analysis.