1 IPRenewal NPEmails From:
Green, Kimberly Sent:
Wednesday, July 17, 2013 10:09 AM To:
Waters, Roger M.
Cc:
IPRenewal NPEmails; Poehler, Jeffrey
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan
- Roger, Below are the conference call details for the call on Friday at 1:00 pm:
Phone Number: 888-957-9841 Pass Code: 59872 (followed by the #)
There are currently 4 lines available for Entergy; however, if more are needed, just call the above number and use the pass code.
If you have any questions or need to adjust the time, please let me know.
- Thanks, Kim From: Waters, Roger M. [1]
Sent: Wednesday, July 17, 2013 8:15 AM To: Green, Kimberly
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan Thanks.
Roger From: Green, Kimberly [2]
Sent: Wednesday, July 17, 2013 7:42 AM To: Waters, Roger M.
Cc: Poehler, Jeffrey; IPRenewal NPEmails
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan
- Roger, We are available for a phone call on Friday at 1:00 pm. Ill will arrange for a bridge line and send you the information shortly.
Kim From: Waters, Roger M. [3]
Sent: Tuesday, July 16, 2013 3:10 PM To: Green, Kimberly
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan
- Kim,
2 We would like the call to be at 1 pm on Friday - is that still good for you?
During the call we will walk through each RAI to ensure that we have a clear understanding.
Roger From: Green, Kimberly [4]
Sent: Monday, July 15, 2013 10:58 AM To: Waters, Roger M.
Cc: IPRenewal NPEmails; Poehler, Jeffrey
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan
- Roger, Jeff Poehler is available Wednesday before noon, Thursday and Friday all day. Please let me know which of these days and times are convenient for Entergy.
- Thanks, Kim From: Waters, Roger M. [5]
Sent: Monday, July 15, 2013 10:50 AM To: Green, Kimberly
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan
- Kim, We will need a conference call to discuss, at a minimum, draft RAI 11-b. We are also reviewing the 3 other RAIs to determine whether we need clarification on those.
Roger From: Green, Kimberly [6]
Sent: Wednesday, July 10, 2013 3:53 PM To: Waters, Roger M.
Cc: IPRenewal NPEmails; Poehler, Jeffrey
Subject:
Draft RAI on Reactor Vessel Internals Inspection Plan
- Roger, Attached is a draft request for additional information (RAI) regarding the Indian Point Reactor Vessel Internals Inspection Plan and responses to previous RAIs.
Please review the draft RAIs and let me know if Entergy requires a phone call. The purpose of the phone call would be to obtain clarification on the staffs requests.
- Thanks, Kim (301) 415-1627 kimberly.green@nrc.gov
Hearing Identifier:
IndianPointUnits2and3NonPublic_EX Email Number:
4310 Mail Envelope Properties (F5A4366DF596BF458646C9D433EA37D701090B0416A8)
Subject:
RE: Draft RAI on Reactor Vessel Internals Inspection Plan Sent Date:
7/17/2013 10:09:20 AM Received Date:
7/17/2013 10:09:21 AM From:
Green, Kimberly Created By:
Kimberly.Green@nrc.gov Recipients:
"IPRenewal NPEmails" <IPRenewal.NPEmails@nrc.gov>
Tracking Status: None "Poehler, Jeffrey" <Jeffrey.Poehler@nrc.gov>
Tracking Status: None "Waters, Roger M." <rwater1@entergy.com>
Tracking Status: None Post Office:
HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 2954 7/17/2013 10:09:21 AM Options Priority:
Standard Return Notification:
No Reply Requested:
No Sensitivity:
Normal Expiration Date:
Recipients Received: