Letter Sequence RAI |
---|
TAC:MF0596, DC Electrical Rewrite - Update to TSTF-360, DC Electrical Rewrite (Approved, Closed) |
|
MONTHYEAR1CAN011304, License Amendment Request - Adoption of Technical Specification Task Force (TSTF)-500, Revision 2 DC Electrical Rewrite - Update to TSTF-360.2013-01-28028 January 2013 License Amendment Request - Adoption of Technical Specification Task Force (TSTF)-500, Revision 2 DC Electrical Rewrite - Update to TSTF-360. Project stage: Request ML13078A4262013-03-19019 March 2013 Acceptance Review Email, License Amendment Request, Adoption of Technical Specifications Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 Project stage: Acceptance Review ML13197A0142013-07-15015 July 2013 Request for Additional Information Email, License Amendment Request, Adoption of Technical Specifications Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 Project stage: RAI 1CAN081302, Response to Request for Additional Information, Adoption of Technical Specification Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360.2013-08-28028 August 2013 Response to Request for Additional Information, Adoption of Technical Specification Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360. Project stage: Response to RAI ML14254A1332014-11-24024 November 2014 Issuance of Amendment No. 250, Adoption of Technical Specifications Task Force (TSTF)-500, Revision 2, DC Electrical Rewrite - Update to TSTF-360 Project stage: Approval 2013-07-15
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24227A0072024-08-13013 August 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 2 - Proposed Alternative for Implementation of Extended Reactor Vessel In-Service Inspection Interval (ANO2-ISI-24-02) - EPID L-2024-LLR-0048 ML24218A0652024-08-0202 August 2024 NRR E-mail Capture - LIC-109 Acceptance Review - Arkansas Nuclear One, Unit 1 - License Amendment Request - Request for Review and Approval Changes to SAR and to a Confirmatory Order - Pzr Htr Emergency Power Supply - EPID L-2024-LLA-0092 ML24180A0022024-06-26026 June 2024 NRR E-mail Capture - LIC-109 Acceptance - ANO 1 and 2 - Proposed Alternatives for Examinations of SG Pressure Retaining Welds and Full Penetrations Nozzles - EPID L-2024-LLR-0038 ML24149A3672024-05-28028 May 2024 August 2024 Emergency Preparedness Exercise Inspection - Request for Information ML24117A0262024-04-26026 April 2024 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Revise Typographical Errors in Technical Specifications ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23269A0232023-09-22022 September 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - TSTF-505 Audit Questions ML23240A3412023-08-28028 August 2023 NRR E-mail Capture - ANO-2, Grand Gulf, and River Bend - Acceptance Review of LAR Revising TSs to Adopt TSTF-205, Revision of Channel Calibration, Channel Functional Test, and Related Definitions ML23194A1752023-07-13013 July 2023 NRR E-mail Capture - ANO-1 - Acceptance Review of Alternative Request ANO1-ISI-037 ML23187A0432023-07-0303 July 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Agenda ML23166A0132023-06-14014 June 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 1 - TSTF-505 Audit Questions ML23130A2752023-05-10010 May 2023 NRR E-mail Capture - ANO Unit 2- Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML23118A0692023-04-28028 April 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Modify ANO-1 TS 3.3.1, Reactor Protection System Instrumentation (L-2023-LLA-0048) ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23072A3672023-03-0909 March 2023 NRR E-mail Capture - Entergy Fleet - Acceptance Review of Quality Assurance Program Manual Reduction in Commitment ML23039A0872023-02-0808 February 2023 NRR E-mail Capture - Arkansas Nuclear One, Unit 2 - Acceptance Review of Relief Request ANO2-RR-23-001, Half-Nozzle Repair of RVCH Penetration 46 (L-2023-LLR-0000) ML23026A1322023-01-26026 January 2023 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to Adopt TSTF-505 Revision 2 ML22354A0122022-12-19019 December 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Acceptance Review of Request for Alternative ANO-CISI-002 Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (L-2022-LLR-0080) ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22341A1202022-12-0707 December 2022 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action LAR to to Remove Technical Specification Condition Allowing Two Reactor Coolant Pump Operation (L-2022-LLA-0161) ML22273A0982022-09-30030 September 2022 NRR E-mail Capture - ANO Units 1 and 2 - Acceptance of Requested Licensing Action Emergency Plan Staffing Requirements ML22265A2012022-09-22022 September 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-036 ML22188A1782022-07-0707 July 2022 NRR E-mail Capture - ANO-1 - Acceptance Review of Relief Request ANO1-ISI-035 ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22081A3902022-03-22022 March 2022 NRR E-mail Capture - ANO-2 - Acceptance Review of Relief Requests ANO2-ISI-023, -024, -025, -026, -027, and -028 (Epids: L-2022-LLR-022, -023, -024, -025, -026, and -027) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML22020A0742022-01-13013 January 2022 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21314A1212021-11-0909 November 2021 Verbal Authorization of Relief Request ANO2-RR-21-002 ML21312A4792021-11-0505 November 2021 Email: NRC Staff Preliminary Questions Regarding X Energy LLC Xe-100 Topical Report: Risk-Informed Performance-Based Licensing Basis Development ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21308A5602021-11-0404 November 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, Grand Gulf, River Bend, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML21292A0112021-10-18018 October 2021 NRR E-mail Capture - ANO, 1 and 2, Grand Gulf, River Bend, Waterford, 3 - Acceptance Review of LAR to Adopt TSTF-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML21287A1692021-10-13013 October 2021 Record of 10-13-21 Verbal Authorization of ANO2-R&R-012 (L-2021-LLR-0082) ML21298A1562021-10-11011 October 2021 NRR E-mail Capture - ANO-2 Final RAI Relief Request ANO2-R&R-012 Concerning Rv Closure Head Penetration 46 ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21238A3742021-08-23023 August 2021 RFI Email - Cyber PI&R Inspection (ANO) ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21202A1662021-07-20020 July 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action Alternative ANO2-PT-003 ML21201A0062021-07-19019 July 2021 NRR E-mail Capture - Arkansas Nuclear One, Units 1 and 2, and Waterford, Unit 3 - Acceptance Review of LAR to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 ML21179A0042021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 1 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21179A0052021-06-25025 June 2021 NRR E-mail Capture - ANO Unit 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 ML21174A0342021-06-22022 June 2021 NRR E-mail Capture - Entergy Fleet (ANO, Ggulf, Rbend, & Waterford) - Acceptance Review for Relief Request to Use a Provision of a Later Edition of the ASME Code, Section XI for Periodic System Pressure Tests Exemptions ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program 2024-08-02
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24143A0632024-05-22022 May 2024 Notification of Inspection (NRC Inspection Report 05000368/2024003) and Request for Information ML24107A0282024-04-17017 April 2024 Notification of Comprehensive Engineering Team Inspection (05000313/2024011 and 05000368/2024011) and Request for Information ML24088A0082024-03-27027 March 2024 NRR E-mail Capture - ANO-2 -- TSTF-505 Post-Audit Final RAI (L-2023-LLA-0052) ML23130A2972023-05-17017 May 2023 Notification of Inspection (NRC Inspection Report 05000313/2023003) and Request for Information ML23104A1052023-03-10010 March 2023 NRR E-mail Capture - ANO-2 Final RAI Alternative Request for Life-of-Repair of RVCH Pen. 46 ML23019A0672023-01-19019 January 2023 Inservice Inspection Request for Information ML22349A0112022-12-14014 December 2022 NRR E-mail Capture - Final RAI Relief Request ANO1-ISI-035 ML22213A1662022-08-0101 August 2022 Information Request, Security IR 2022401 ML22208A0542022-07-26026 July 2022 Request for Information ML22174A1362022-06-23023 June 2022 NRR E-mail Capture - ANO-2 Final RAI Relief Requests ANO2-ISI-023 Through -028 (EPIDs L-2022-LLR-0022 Through -0027) ML22159A3242022-06-0909 June 2022 Notification of NRC Triennial Heat Exchanger/Sink Performance Inspection (05000313/2022003 and 05000368/2022003) and Request for Information ML22151A3262022-05-31031 May 2022 August 2022 Emergency Preparedness Exercise Inspection - Request for Information ML22124A2452022-05-0404 May 2022 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI 2 License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22122A2952022-05-0404 May 2022 Notification of Inspection NRC Inspection Report 05000368/2022003 and Request for Information ML22108A1642022-04-18018 April 2022 NRR E-mail Capture - ANO-1: Final RAI License Amendment Request Concerning TS Changes Due to Revised Dose Calculations (L-2021-LLA-0181) ML22034A5482022-02-0303 February 2022 NRR E-mail Capture - Final RAI License Amendment Requests to Implement Provisions of 10 CFR 50.69 (L-2021-LLA-0105/-0106) ML22020A0822022-01-19019 January 2022 NRR E-mail Capture - ANO-1 and 2 - Final RAI 2 License Amendment Requests to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21312A0382021-11-0505 November 2021 NRR E-mail Capture - ANO-2 RAI Relief Request ANO2-RR-21-002 ML21286A7132021-10-15015 October 2021 ANO2022010 Tfp RFI Stg, Arkansas Nuclear One, Units 1 and 2 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000313/2022010 and 05000368/2022010) and Request for Information ML21273A0672021-09-29029 September 2021 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request to Adopt a Safety Function Determination Program ML21236A3222021-09-19019 September 2021 Request for Information ML21252A0052021-08-20020 August 2021 NRR E-mail Capture - ANO-1 and 2 Final RAI License Amendment Request to Allow the ECP to Remain Operable on a One-Time Basis for Up to 65 Days to Perform Piping Upgrade (L-2021-LLA-0015) ML21217A3302021-08-0505 August 2021 (ANO) Problem Identification and Resolution (PIR) Request for Information Combined ML21204A0842021-07-28028 July 2021 ANO Phase 4 2021013 RFI Gap ML21197A0372021-07-16016 July 2021 NRR E-mail Capture - ANO-1 and 2 - Final RAI Final Response to GL 2004-02 0CAN042105, Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description2021-04-30030 April 2021 Supplement to Response to Request for Additional Information Reduction of Commitment to the Entergy Operation'S Quality Assurance Program Manual Description ML21116A1092021-04-26026 April 2021 NRR E-mail Capture - ANO-1 and ANO-2: Final Supplemental RAI Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of ECP Supply Piping ML21105A0122021-04-0909 April 2021 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Adopt a Safety Function Determination Program ML21071A2172021-03-10010 March 2021 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Proposed Change to Quality Assurance Program Manual ML21026A2682021-01-26026 January 2021 Request for Information ML21022A0842021-01-22022 January 2021 Request for Additional Information - Proposed Alternative to ASME Section XI Requirements for Repair/Replacement of Emergency Cooling Pond Supply Piping - Arkansas Nuclear One,Units 1 and 2 -Entergy Operations, Inc. NON-PROPRIETARY Redacted ML21019A5142021-01-14014 January 2021 March 2021 Emergency Preparedness Exercise Inspection - Request for Information ML20324A6412020-11-19019 November 2020 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-034 ML20316A0102020-11-0202 November 2020 NRR E-mail Capture - ANO-1 and ANO-2 - Final RAI Concerning Relief Request EN-20-RR-01 ML20262H0752020-09-17017 September 2020 NRR E-mail Capture - ANO-2 Final RAI 2 License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20260H4762020-09-0909 September 2020 NRR E-mail Capture - ANO-1 Final RAI License Amendment Request to Revise Lov Relay Allowable Values ML20154K7622020-06-0101 June 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request Concerning Proposed Technical Specification Additions, Deletions, and Relocations ML20119A0982020-04-28028 April 2020 Notification of Inspection (NRC Inspection Report 05000368/2020003 and Request for Information ML20106E8522020-04-13013 April 2020 Information Request, NRC Inspection Report 05000313/2020410 and 05000368/2020410 ML20065H7992020-03-0606 March 2020 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Revise Loss of Voltage Relay Allowable Values ML20055E9092020-02-24024 February 2020 NRR E-mail Capture - ANO-2 Final RAI License Amendment Request to Revise Control Element Assembly Drop Time ML20036D3092020-02-0505 February 2020 NRR E-mail Capture - ANO-2 - Final RAI Alternative Request VRR-ANO2-2019-1 ML20013C7472020-01-10010 January 2020 NRR E-mail Capture - ANO-1 and 2 -- Final RAI #2 LAR to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19316A0242019-11-0707 November 2019 NRR E-mail Capture - ANO-1 - - Final RAI Concerning Relief Request ANO1-ISI-033 (L-2019-LLR-0100) ML19280A0402019-10-0707 October 2019 NRR E-mail Capture - ANO-1 and 2 - Final RAI #1 License Amendment Request to Incorporate Tornado Missile Risk Evaluator (TMRE) Into Licensing Basis ML19339F5902019-09-23023 September 2019 Request for Information: Arkansas Nuclear One, IR 05000313/2019-004 Occupational Radiation Safety Inspection ML19281E0032019-08-0505 August 2019 ANO 2019 PIR Request for Information ML19203A0122019-07-16016 July 2019 Request for Information - Inservice Inspection Activities (NRC Inspection Report 05000313/2019004) ML19106A4322019-04-16016 April 2019 NRR E-mail Capture - ANO-2 Final RAI Re LAR to Add TS Actions to Address Inoperability of the Containment Building Sump ML19058A8332019-02-27027 February 2019 NRR E-mail Capture - ANO-1 - Final RAI Relief Request ANO1-ISI-032 2024-05-22
[Table view] |
Text
Burkhardt, Janet From: Kalyanam, Kaly Sent: Monday, July 15, 2013 12:59 PM To: BICE, DAVID B (ANO) (DBICE@entergy.com)
Cc: Burkhardt, Janet; CLARK, ROBERT W (RCLARK@entergy.com)
Subject:
RAI regarding the LAR for adoption of TSTF-500, Revision. 2, DC Electrical Rewrite -
Update to TSTF-360 (SUNSI Information at the end)
DATE: July 15, 2013
SUBJECT:
ARKANSAS NUCLEAR ONE, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST FOR ADOPTION OF TECHNICAL SPECIFICATIONS TASK FORCE (TSTF) TRAVELER TSTF-500, REVISION. 2, DC ELECTRICAL REWRITE - UPDATE TO TSTF - 360 (TAC NO. MF0596)
By letter dated January 28, 2013 (Agencywide Documents Access and Management System Accession Number ML13029A767), Entergy Operations, Inc. (Entergy, the licensee) submitted a license amendment request (LAR) for Arkansas Nuclear One, Unit 1 (ANO-1) to adopt NRC-approved Technical Specifications Task Force (TSTF)-500, Revision 2, direct current (DC) Electrical Rewrite - Update to TSTF - 360. The proposed amendment would revise Technical Specification (TS) 3.8.4, DC sources - Operating, TS 3.8.5, DC Sources - Shutdown, and TS 3.8.6, Battery Parameters, add a new program, Battery Monitoring and Maintenance Program to TS Section 5.5, and relocate Surveillance Requirements (SRs) in Table 3.8.6-1 to the new program.
The NRC Staff has reviewed the information provided by the licensee and in order to complete the review, EEEB has attached a request for additional information regarding the adoption of TSTF-500, Revision 2 that should be transmitted to the licensee for a formal written response. Please provide your response to the RAI within 45 from the receipt of this request.
Thanks Kaly N. Kalyanam REQUEST FOR ADDITIONAL INFORMATION ARKANSAS NUCLEAR ONE, UNIT 1 LAR FOR ADOPTION OF TECHNICAL SPECIFICATIONS TASK FORCE (TSTF) TRAVELER TSTF-500, REVISION. 2, DC ELECTRICAL REWRITE - UPDATE TO TSTF - 360 1
DOCKET NO. 50-313 The NRC staff has determined that the following additional information is needed to complete its review of the license amendment request (LAR) dated January 28, 2013:
- 1. In Attachment 1, Section 1 of the LAR, the licensee proposed relocating the requirements of Technical Specification (TS) Table 3.8.6-1, Battery Surveillance Requirements, to the proposed TS 5.5.6, Battery Monitoring and Maintenance Program.
Confirm that the Table 3.8.6-1 Categories A, B, and C values (electrolyte level, float voltage, specific gravity) that will be relocated to TS 5.5.6, will continue to be controlled at their current levels in the TS Battery Monitoring and Maintenance Program and that actions to restore deficient values will be implemented in accordance with the licensees corrective action program.
- 2. In Attachment 1, Section 2.1 of the LAR, the licensee proposed adopting TSTF-500 TS 3.8.5, Condition A, which applies when a required battery charger on one subsystem is inoperable and the required redundant subsystem battery and charger are operable. Condition A is included only when the plant-specific implementation of TS 3.8.5 may require both subsystems of the direct current (DC) electrical power system to be operable. Arkansas Nuclear One, Unit 1 ANO-1 TS LCO 3.8.5 requires the DC electrical power subsystem to be operable to support the DC electrical power distribution subsystem(s) required by Limiting Condition for Operation (LCO) 3.8.10 in Modes 5 and 6.
a) Clarify whether ANO-1 TS requires one or both DC electrical power subsystem(s) to be operable in Modes 5 and 6. If TS 3.8.5 requires one DC electrical power subsystem to be operable, justify the adoption of the second part of Condition A, which states the required redundant subsystem battery and charger are operable.
b) The licensee proposed adopting TSTF-500 TS 3.8.5 Required Action (RA) A.1, which requires restoring the battery terminal voltage to greater than or equal to the minimum established float voltage within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. Explain how the licensee would ensure that the battery was returned to its fully charged state from any discharge that might have occurred due to the charger inoperability.
- 3. In Attachment 1, Page 6 of the LAR, the licensee stated that the maintenance of the ANO-2 DC distribution system, given the program modifications committed to via adoption of TSTF-500, meets the intent of the Regulatory Guidance (RG) 1.129, Revision 2, Maintenance, Testing, and Replacement of Vented Lead-Acid Storage Batteries for Nuclear Power Plant.
2
Clarify whether the above statement refers to ANO-1 instead of ANO-2 and whether ANO-1 is committed to RG 1.129, Revision 2.
- 4. In Attachment 1, Section 2.2 of the LAR, the licensee stated that ANO-1 will revise the ANO-1 Safety Analysis Report (SAR) to include how a 2 percent design margin for the batteries corresponds to a 2 amperes (amps) float current value indicating that the battery is 98 percent charged.
a) Provide the bases for the 2-amp float current at which ANO-1 batteries are capable of performing its design function.
b) Explain how maintaining a 2 percent design and 98 percent charge will ensure that the ANO-1 safety-related batteries are fully charged (i.e., capable of performing their design function).
- 5. In Attachment 1, Section 2.2 of the LAR, the licensee proposed to adopt into the Battery Monitoring and Maintenance Program, the battery connection resistance limit of 50 micro ohms which ensures that the minimum DC voltage is maintained for all required loads.
a) Clarify whether 50 micro ohms is the overall connection resistance limit or the resistance limit for each inter-cell connection, each inter-rack connection, each inter-tier connection, and each terminal connection.
b) Provide a summary table that includes current baseline resistance values or the battery manufacturers recommended resistance limits for each type of battery connections.
c) Provide the basis for the proposed connection resistance value.
- 6. In Attachment 4 of the LAR, the licensee proposed an alternative criterion for new TS Surveillance Requirement (SR) 3.8.4.2 which states, Verify each battery charger can recharge the battery to the fully charged state within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> while supplying the largest combined demands of the various continuous steady state loads, after a battery discharge to the bounding design basis event discharge state. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is bracketed in TSTF-500.
Explain the basis for 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
- 7. In Attachment 4 of the LAR, the licensee proposed new SR 3.8.4.3 as in TSTF-500. SR 3.8.4.3 in TSTF-500 includes a note that states, This Surveillance shall not be performed in Mode 1, 2, 3, or 4.
However, credit may be taken for unplanned events that satisfy this SR.
Explain why this note was not adopted in ANO-1 SR 3.8.6.6.
3
- 8. In Attachment 4 of the LAR, the licensee proposed TS 3.8.5, Condition A, RA A.1, which requires the restoration of the battery terminal voltage to greater than or equal to the minimum established float voltage within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> when one of the required battery charger on one subsystem is inoperable and the required redundant subsystem battery and charger are operable.
a) Explain how the licensee will ensure that the battery is returned to its fully charged state from any discharge that might have occurred due to the charger inoperability b) Per TSTF-500, Page 9, the new TS 3.8.5, Condition A is included only when the plant-specific implementation of TS 3.8.5 may require both trains of the DC electrical power system to be operable. Clarify whether ANO-1 TS 3.8.5 requires both DC subsystems to be operable.
c) The mark-up version of TS 3.8.5, Condition A states, the required redundant subsystem battery and charger while the clean version of TS 3.8.5, Condition A in Attachment 5 states, the redundant subsystem battery and charger. Explain this apparent discrepancy.
- 9. In Attachment 4 of the LAR, the licensee proposed 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Completion Time (CT) for TS 3.8.6, Condition B, Required Action (RA) B.2. This 12-hour CT is bracketed in TSTF-500.
Explain how the 12-hour CT is applicable to ANO-1.
- 10. In Attachment 4 of the LAR, the licensee proposed adding new Condition D to TS 3.8.6 which would apply to a battery found with a pilot cell electrolyte temperature less than the minimum established design limit. The RA associated with new Condition D would require the licensee to restore the pilot cell electrolyte temperature to greater than or equal to minimum established design limits within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
a) Discuss how the battery room temperature is periodically monitored at ANO-1 and provide the minimum frequency at which the temperature of the battery room is monitored.
b) Explain how the licensee would restore battery room temperature if it was outside the temperature limits.
c) Provide the method of selection of pilot cells at ANO-1.
- 11. In Attachment 4 of the LAR, the licensee proposed a battery cell float voltage limit of greater than or equal to 2.07 V which is reflected in TS 3.8.6 RA A.3, SR 3.8.6.2, and SR 3.8.6.5. This 2.07-V is bracketed in TSTF-500.
a) Explain how this cell float voltage limit is applicable to ANO-1.
b) Current TS Table 3.8.6-1, Battery Cell Surveillance Requirements, Category C float voltage allowable limits for each connected cell is > 2.07 V. Explain the change from > 2.07 V to 2.07 V.
- 12. In Attachment 4 of the LAR, the licensee proposed relocating SR 3.8.4.3 to SR 3.8.6.6 as in TSTF-500. SR 3.8.6.6 in TSTF-500 includes a note that states, This Surveillance shall not be performed in Mode 1, 2, 3, or 4. However, credit may be taken for unplanned events that satisfy this SR.
Explain why this note was not adopted in ANO-1 SR 3.8.6.6.
SUNSI Information:
4
Plant: Arkansas Nuclear One, Unit 1 Docket No.: 50/313 From: N. Kalyanam To: D. Bice
Subject:
RAI regarding the LAR for adoption of TSTF-500, Revision. 2, DC Electrical Rewrite - Update to TSTF-360 TAC No. 0596 SUNSI Review Done: Yes. Not Publicly Available, Normal Release, Non-sensitive, 5