RS-13-183, (EGC) Response to NRC Regulatory Issue Summary 2013-06, Preparation and Scheduling of Operator Licensing Examinations

From kanterella
(Redirected from ML13190A049)
Jump to navigation Jump to search
(EGC) Response to NRC Regulatory Issue Summary 2013-06, Preparation and Scheduling of Operator Licensing Examinations
ML13190A049
Person / Time
Site: Dresden, Peach Bottom, Oyster Creek, Byron, Braidwood, Limerick, Clinton, Quad Cities, LaSalle, Crane
Issue date: 07/08/2013
From: Gullott D
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RS-13-183
Download: ML13190A049 (12)


Text

RS-13-183 July 8, 2013 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-1 1 and NPF-1 8 NRC Docket Nos. 50-373 and 50-374 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353 Oyster Creek Nuclear Generating Station Renewed Facility Operating License No. DPR-1 6 NRC Docket No. 50-219 Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265 Three Mile Island Nuclear Station, Unit 1 Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289 Ik-1 RS-13-183 July 8,2013 2000 Office U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 Byron Station, Units 1 and 2 Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. STN 50-454 and STN 50-455 Clinton Power Station, Unit 1 Facility Operating License No. NPF-62 NRC Docket No. 50-461 Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249 LaSalle County Station, Units 1 and 2 Facility Operating License Nos. NPF-11 and NPF-18 NRC Docket Nos. 50-373 and 50-374 Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353 Oyster Creek Nuclear Generating Station Renewed Facility Operating License No. DPR-16 NRC Docket No. 50-219 Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265 Three Mile Island Nuclear Station, Unit 1 Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289

July 8, 2013 U. S. Nuclear Regulatory Commission Page 2

Subject:

Exelon Generation Company, LLC (EGC) Response to NRC Regulatory Issue Summary 2013-06, "Preparation and Scheduling of Operator Licensing Examinations"

Reference:

NRC Regulatory Issue Summary 2013-06, "Preparation and Scheduling of Operator Licensing Examinations," dated June 7, 2013 The referenced Regulatory Issue Summary (RIS) requested that facility licensees provide a proposed schedule of operator licensing examinations and an estimate of the number of candidates requiring initial operator license examinations for calendar years 2015 through 2018, and the number of candidates requiring Generic Fundamentals Examinations for calendar years 2015 and 2016. Attachments 1 through 10 provide responses to RIS 2013-06 for the EGC plants identified above. The requested information for each facility is provided on a separate NRC Form 536.

For the Limerick Generating Station (LGS) and the Peach Bottom Atomic Power Station (PBAPS), the Limited Senior Reactor Operator (LSRO) initial license examination can be a dual-site examination. Rather than repeat the same information on both attachments, the examination scheduling information is provided on Attachment 6 for LGS. Attachment 8 for PBAPS references Attachment 6 where appropriate. There are no candidates currently expected to take the dual-site LSRO initial license examination for calendar years 2015 through 2018, as indicated on Attachment 6.

There are no regulatory commitments contained within this letter. Should you have any questions concerning this letter, please contact Richard W. McIntosh at (630) 657-2816.

Respectfully, David M. Gullott Manager - Licensing Exelon Generation Company, LLC - Completed NRC Form 536 for Braidwood Station - Completed NRC Form 536 for Byron Station - Completed NRC Form 536 for Clinton Power Station - Completed NRC Form 536 for Dresden Nuclear Power Station - Completed NRC Form 536 for LaSalle County Station - Completed NRC Form 536 for Limerick Generating Station - Completed NRC Form 536 for Oyster Creek Nuclear Generating Station - Completed NRC Form 536 for Peach Bottom Atomic Power Station - Completed NRC Form 536 for Quad Cities Nuclear Power Station 0 - Completed NRC Form 536 for Three Mile Island Nuclear Station cc:

Regional Administrator - NRC Region I Regional Administrator - NRC Region III July 8,2013 U. S. Nuclear Regulatory Commission Page 2

Subject:

Exelon Generation Company, LLC (EGC) Response to NRC Regulatory Issue Summary 2013-06, "Preparation and Scheduling of Operator Licensing Examinations"

Reference:

NRC Regulatory Issue Summary 2013-06, "Preparation and Scheduling of Operator licensing Examinations," dated June 7,2013 The referenced Regulatory Issue Summary (RIS) requested that facility licensees provide a proposed schedule of operator licensing examinations and an estimate of the number of candidates requiring initial operator license examinations for calendar years 2015 through 2018, and the number of candidates requiring Generic Fundamentals Examinations for calendar years 2015 and 2016. Attachments 1 through 10 provide responses to RIS 2013-06 for the EGC plants identified above. The requested information for each facility is provided on a separate NRC Form 536.

For the Limerick Generating Station (LGS) and the Peach Bottom Atomic Power Station (PBAPS), the Limited Senior Reactor Operator (LSRO) initial license examination can be a dual-site examination. Rather than repeat the same information on both attachments, the examination scheduling information is provided on Attachment 6 for LGS. Attachment 8 for PBAPS references Attachment 6 where appropriate. There are no candidates currently expected to take the dual-site LSRO initial license examination for calendar years 2015 through 2018, as indicated on Attachment 6.

There are no regulatory commitments contained within this letter. Should you have any questions concerning this letter, please contact Richard W. Mcintosh at (630) 657-2816.

Respectfully, 7:?/~

David M. Gullott Manager - Licensing Exelon Generation Company, LLC - Completed NRC Form 536 for Braidwood Station - Completed NRC Form 536 for Byron Station - Completed NRC Form 536 for Clinton Power Station - Completed NRC Form 536 for Dresden Nuclear Power Station - Completed NRC Form 536 for LaSalle County Station - Completed NRC Form 536 for Limerick Generating Station - Completed NRC Form 536 for Oyster Creek Nuclear Generating Station - Completed NRC Form 536 for Peach Bottom Atomic Power Station - Completed NRC Form 536 for Quad Cities Nuclear Power Station 0 - Completed NRC Form 536 for Three Mile Island Nuclear Station cc:

Regional Administrator - NRC Region I Regional Administrator - NRC Region III

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 09/30/2014 (09-2011)

Estimated burden per response to comply with this voluntary information collection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator OPERATOR LICENSING examinations.

Send comments regarding burden estimate to the Information Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-EXAMINATION DATA mail to lnfocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Braidwood Station, Units 1 and 2 III Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

1 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER Cy 2015 Cy 2016 Cy 2017 Cy 2018 NUMBER OF REACTOR 0

9 0

9 OPERATORS NUMBER OF SENIOR REACTOR 0

11 0

8 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE N/A 08/29/2016 N/A 05/14/2018 ALTERNATE DATE N/A 09/12/2016 N/A 05/29/2018 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

20 0

0 0

0 0

0 CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company. LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 09/30/2014 (09-2011)

Estimated burden per response to comply with this voluntary information collection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator OPERA TOR LICENSING examinations. Send comments regarding burden estimate to the Information Services Branch (T-5 F53). U.S. Nuclear Regulatory Commission. Washington, DC 20555-0001, or by inlernet e-EXAMINATION DATA mail to Infocoliects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs. NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Braidwood Station, Units 1 and 2 III Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

1 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 0

9 0

9 OPERATORS NUMBER OF SENIOR REACTOR 0

11 0

8 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE N/A 08/29/2016 N/A 05/14/2018 ALTERNATE DATE N/A 09/12/2016 N/A 05/29/2018 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

20 0

0 0

0 0

0 CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 0913012014 (09-2011)

Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator OPERATOR LICENSING examinations.

Send comments regarding burden estimate to the Information Services Branch (f-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-EXAMINATION DATA mail to lnfocdlects.Rescurce@rrc.gov, and to the Desk Officer, Office of Information and Regulatory Altars, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY N

REGION Byron Station, Units I and 2 Facility Operating License Nos. NPF-37 and NPF-66 III NRC Docket Nos. STN 50-454 and STN 50-455 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY 2016 CY 2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

1 1

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2015 CY 2016 CY 2017 CY 2018 NUMBER OF REACTOR 0

5 8

7 OPERATORS NUMBER OF SENIOR REACTOR 0

7 7

8 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

1 1

1 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS-LIMITED PROPOSED DATES PRIMARY DATE N/A 03/28/16 - 04/01/16 08/14/17 - 08/18/17 12/03/18 - 12/07/18 ALTERNATE DATE N/A 04/04/16 - 04/08/16 08/21/17 - 08/25/17 12/10/18 - 14/18 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE Cy 2015 Cy 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 16 CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150"()131 EXPIRES: 0913012014 (09-2011 )

Estimated burden per response to compty with this voluntary irfonmation collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This irfonmation collection is used to plan budgets and resoulCes for operator OPERA TOR LICENSING examirations Sem comments regarding burden esllmate to the Infonmation ServK:es Branch (T-5 F53), US Nuclear RegulatOl)' Ccrnmission, Washington, DC 20555-oml, or by iriemet e-EXAMINATION DATA mail to InfocoilectsResource@lTc.gov, and to the Desk Officer, Office of Infonmation and Regulatory Affairs, NEOB-I0202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an irfonmation collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person IS not required to respond to, the infonmationcollection.

FACtLlTY Nh:Ch:t:<>ION Byron Station, Units I and 2 Facility Operating License Nos. NPF-37 and NPF-66 ill NRC Docket Nos. STN 50-454 and STN 50-455 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

1 1

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY 20 17 CY2018 NUMBER OF REACTOR 0

5 8

7 OPERATORS NUMBER OF SENIOR REACTOR 0

7 7

8 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

1 1

1 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS* LIMITED PROPOSED DATES PRIMARY DATE N/A 03/28/16 - 04/01116 08/14/17 - 08/18/17 12/03/18 - 12/07/18 ALTERNATE DATE N/A 04/04/16 - 04/08/16 08/21117 - 08/25/17 12/10/18 - 14/18 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 16 CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 OPERATO R LICENSING (Y 5 P53), U.S.

a1,

, DC U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 per response to comp^

M p

hatc This imonnatton c0110co n is USK$

xamnabs. Send cmvwru teganfinf; bwd XAMINATION DATA R

gm',

to the Desk Ofter, Ofte of kftvam and R

teas, NECO-10202, (3150-0131), Oft of ManWment and BudgK W DC 20503.

If a means used to hpose an s not daplay a amsnq vdd OW cattrd mffnber, the NRC may not con&xt or spwsor, and a pww is not mwm to mW to 111 respondtIffamadw FACILITY 0

Clinton Power Station, Unit I Facility Operating License No.

F-62 NRC Docket No. 50-461 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY 2016 CY 2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS 0

0 0

0 0

Cy 2015 4

CY 2016 0

CY 2017 6

CY 2018 0

NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED 6

4 0

0 0

6 2

0 0

0 03/1612015 03/23/2015 02/21/2017 02/27/2017 N/A N/A N/A N/A C FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 201 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF CANDIDATES NRC FORM 536 (09-2011) 0 0

0 12 0

0 Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 1..1. S. NUCLEAR REGUlATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 0913012014 (Q9.2011 I Estimaled hurdeIl per fOS!lOI1S8 10 comply 'MIll IhiI ~

Womtalion coIIectiilo fCQIIISI: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This Information coIIedIon is used 10 plan bodgIlIs and resoun:ea br operaU OPERATOR LICENSING 1lXllIllinaIion. Send _nil! regarding hurdeIl eslima!e to !he IoformIIIoo SllMces Bmnch (T-; f53~ u.s. Nuclear ~

~

Washlngm. DC 2()5$.0001, or by iolsmet 8-EXAMINATION DATA mail 10 II1iocoIIecIs.R~gov. and 10 !he Desk OOcer, 0II!ce of Information and R~

Affairs, NE0Il-1tl202, (3150..(1131). 0II!ce of Management and Budget. WesI!ingIon, DC 20503.

If a means used 10 impose an iofomlalioo roIIedion does not display a CUIllII1!Iy vaid OMS control number. tile IIRC may not conduct Of sponsor, and a person is not I1lqUimd 10 respond 10. tile lniormallm CtJiIedIon.

FACILITY NRC REGION Clinton Power Station, Unit I Facility Operating License No. NPF-62 ill NRC Docket No. 50-461 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY20l8 ESTIMATED NUMBER OF LICENSEE-PREPARED 1

0 1

0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 4

0 6

0 OPERATORS NUMBER OF SENIOR REACTOR 6

0 6

0 OPERATORS -INSTANT NUMBER OF SENIOR REACTOR 4

0 2

0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 03/16/2015 N/A 02/2112017 N/A ALTERNATE DATE 03123/2015 N/A 02/27/2011 N/A C. PROPOSED GENERIC FUNDAMENTALS EXAM INA nON (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTiMATED NUMBER OF 0

0 0

12 0

0 0

0 CANDIDATES NRC FORM 536 (1J9.201 j I

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION (09.2011)

OPERATOR LICENSING EXAMINATION DATA FACILITY Dresden Nuclear Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-19 and DPR-25 NRC Docket Nos. 50-237 and 50-249 APPROVED BY OMB: NO. 3150-0131 EXPIRES: 0413012014 Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden estimate to the Information Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internal a-mat to Infocafects.Resource&rc.gov, and to the Desk Officer, Mice of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, W ashirtgton, DC 20503.

d a means used to impose an information collection does not display a currently valid OM8 control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

C I GION 111 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2015 CY2016 CY 2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS 0

0 0

0 0

CY 2018 4

3 0

0 10/01/2018 10/15/2018 PROPOSED NUMBER NUMBER OF REACTOR OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE ALTERNATE DATE Cy 2015 03/02/2015 03/23/2015 CY 2016 08/08/2016 08/22/2016 6

5 0

4 7

0 CY 2017 0

0 0

0 N/A N/A C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE Cy 2015 JUNE SEPTEMBER CY 2016 JUNE SEPTEMBER PROPOSED NUMBER MARCH DECEMBER DECEMBER MARCH ESTIMATED NUMBER OF CANDIDATES 7

0 0

12 0

0 0

0 NRC FORM 536 (092011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-6131 EXPIRES: 0913012014 (09*2011)

ESlimaied burden per response 10 comply with this volunlaly infllnnation ctilection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

ThIs infonnetion collection is used to plan budgets and resourte5 for operetor OPERA TOR LICENSING examinations. Send oommenls reganfing burden estimate 10 the InfonnaUon Sarvices Branch (T*5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet II-EXAMINATION DATA mal 10 Infocoilects.Rasoun:e@nrc.gov, and to the Desk Officer, 0fIite of Infonnation and Regulalcry Affairs. NEOB*10202, (3150-0131), Oftlce of Management and 8udge~ Washington, DC 20503.

If a mesne used to impose an infO!lTlation coRection does not display a cunentiy vatid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond 10. the infonnation coKection.

FACILITY NRCREGIUN Dresden Nuclear Power Station. Units 2 and 3 III Renewed Facility Operating License Nos. DPR~19 and DPR~25 NRC Docket Nos. 50-237 and 50~249 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 1

1 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 6

4 0

4 OPERATORS NUMBER OF SENIOR REACTOR 5

7 0

3 OPERATORS* INSTANT NUMBER OF SENIOR REACTOR 1

I 0

0 OPERATORS* UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERA TORS -LIMITED PROPOSED DATES PRIMARY DATE 03/02/2015 08/08/2016 N/A 10/0112018 ALTERNATE DATE 03/23/2015 08/22/2016 N/A LO/15/2018 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

12 0

0 0

0 0

7 CANDIDATES NRC FORM 536 (09*2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-01131 EXPIRES: 09/30/2014 (09-2011)

Estimated burden per response to comply with this voluntary information co llection request: I hour.

This information collection is used to (tarn budgets and resources for operator OPERATOR LICENSING examinations, Send comments regardurg burden estimate to the Information Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-EXAMINATION DATA mad to lnfocolects.Resorvice@rvc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NE08.10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid OM8 control number, the NRC may not conduct or sponsor and a person is not required to respond to, the information collection.

FACILITY NRC REGION LaSalle County Station, Units 1 and 2 III Facility Operating License Nos. NPF-1 I and NPF-18 NRC Docket Nos. STN 50-373 and STN 50-374 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY 2016 CY 2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

1 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER Cy 2015 CY 2016 Cy 2017 Cy 2018 NUMBER OF REACTOR 0

7 0

7 OPERATORS NUMBER OF SENIOR REACTOR 0

5 0

5 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

1 0

1 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE N/A 10/10/2016 N/A 10/15/2018 ALTERNATE DATE N/A 10/17/2016 N/A 10/22/2018 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE Cy 2015 Cy 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

12 0

0 0

0 0

0 CANDIDATES t4RC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULA TORY COMMISSION APPROVED BY OMS: NO. 3150-0131 EXPIRES: 09/30/2014 (09-2011)

Estimated burden per response III comply with this voluntary information collection reqtJest: 1 hour<

This information collection is used III plan budgets and resources for operaillr OPERA TOR LICENSING examinations< Send comments regarding burden estimate to !he Information Services Branch (T*5 F53), U.s< Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-EXAMINATION DATA mail 10 Infocoliecls<Resource@nrC<9OV, and III the Desk Officer, Office of Information and Regulalory Affairs, NEOB*10202, (3150-0131), Office of Management and Budget, Washington DC 20503.

If a means used III impose an information col!ecoon does not display a currenlly vatio OMS controt number. the NRC may not conduct or sponsor and a person is not required III respond to, !he information coIIecticn<

FACILITY NRC REGION LaSalle County Station, Units I and 2 III Facility Operating License Nos. NPF-II and NPF-18 NRC Docket Nos. STN 50-373 and STN 50-374 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

I 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 0

7 0

7 OPERATORS NUMBER OF SENIOR REACTOR 0

5 0

5 OPERATORS -INSTANT NUMBER OF SENIOR REACTOR 0

I 0

I OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE N/A 10/10/2016 N/A 10115/2018 ALTERNATE DATE N/A 10/17/2016 N/A 10/2212018 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

12 0

0 0

0 0

0 CANDIDATES NRC FORM 536 (09*2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 535 U. S. NUCLEAR REGULATORY COMMISSION (09.2011)

OPERATOR LICENSING EXAMINATION DATA FACILITY Limerick Generating Station, Units I and 2 Facility Operating License Nos. NPF-39 and NPF-85 NRC Docket Nos. 50-352 and 50-353 APPROVED BY OMB: NO.3150-0131 EXPIRES: 0913012014 Estimated burden per response to comply with this voluntary nkxmatmn collection request I how.

This infomation collection Is used to plan budgets and resources for operator exansnatio s. Send comments regarding burden estimate to the Information Services Branch (T-5 F53). U.S. Nuclear Regulatory Comrrission, Washington, DC 20555-0001, or by Internet a-mal to infocatiects.Resou gov, and to the Desk Officer, Office of Information and Regulatory Affairs. NEO&10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently valid Oka central number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

INRC REG-ION 1

A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2015 CY 2016 CY 2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

EXAMINATIONS E. INITIAL OPERATOR LICENSE EXAMINATIONS 0

0 1

0 Cy 2017 0

0 0

0 N/A N/A PROPOSED NUMBER NUMBER OF REACTOR OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE ALTERNATE DATE Cy 2015 12/07/2015 12/14/2015 Cy 2016 12/05/2016 12112/2016 Cy 2018 12/03/2018 12/10/2018 6

5 1

0 6

4 3

0 5

5 3

0 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE PROPOSED NUMBER MARCH SEPTEMBER DECEMBER MARCH CY 2016 JUNE SEPTEMBER DECEMBER CY 2015 JUNE ESTIMATED NUMBER OF CANDIDATES 0

0 0

0 13 0

0 0

NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVEO BY OMB: NO. 3150.(1131 EXPtRES: 09/3012014 (09-2011)

Estimated burden per response 10 comply v.ith !his voluntary information collection request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This infonnation collection Is used to plan budgets and resources for operalor OPERA TOR LICENSING examinations. Send comments regarding burden estimate 10 the tnfonnalioo Services Branch (ToS FS31. U.S. Nuclear Regulatory Commission. Washinglon. DC 20555-0001. or by inlarnst.

EXAMINATION DATA mall 10 lnfocollects.Resoun:e@nlt.gov. and to the DII1k Officer. Office of Iofonnation and Regulalory Affairs. NEOB-l0202. (31S0-0131). Office of Management and Budget. Washington.

DC 20503.

If a means used to impose an infonnatiao collection does not display a CUII1!I1Uy vatid OMB contrnl number. the NRC may not conduct or sponsor. and a person is not required to respond to. the information collection.

FACILITY NRC REGION Limerick Generating Station, Units 1 and 2 Facility Operating License Nos. NPF-39 and NPF-85 1

NRC Docket Nos. 50-352 and 50-353 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED I

I 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 6

6 0

5 OPERATORS NUMBER OF SENIOR REACTOR 5

4 0

5 OPERATORS -INSTANT NUMBER OF SENIOR REACTOR 1

3 0

3 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 12/07/2015 12/05/2016 N/A 12/03/2018 ALTERNATE DATE 12/14/2015 12/12/2016 N/A 12110/2018 C. PROPOSED GENERIC fUNDAMENTALS EXAMINATION (GfE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATEO NUMBER OF 0

13 0

0 0

0 0

0 CANOIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION (09.2011)

OPERATOR LICENSING EXAMINATION DATA FACILITY Oyster Creek Nuclear Generating Station Renewed Facility Operating License No. DPR-16 NRC Docket No. 50-219 APPROVED BY OMB: NO.3150.0131 EXPIRES: 0913012014 Eslbnatad burden per response to amply wth HA vauroffy i rfon axon co ection request: 1 tour.

This '

n cokcft is used to plan budgets and resources for operator ex atlaa. Send connants ragnfing burden es*nWe to Be Infomradon Services Branch (T-5 F53), U.S. Nuclear ROWARICKY Canmesion, W

, DC 20555.0001, or by Wernst e-maY is run.gov, and to the task Cfer, Office of ftmWon and Regulatory Affairs, NEOB.10202, (3150-0131), Ofke of maneward and Budget, W n,

DC 20503.

If a mews used to knposs an '

s not

{day a cunendy vaN OMB control martar, the NRC may not conduct or sponsor, and a person is not req*ed to respond in, the Marsdion collection.

Region I A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY 2016 CY2017 CY 2018 NUMBER OF REACTOR OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE ALTERNATE DATE C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE 0

0 0

0 0

0 0

6 0

0 0

4 2

0 0

5/16/2016 5/12/2016 0

0 0

0 0

0 0

0 CY 2016 CY 2015 JUNE JUNE PROPOSED NUMBER MARCH SEPTEMBER DECEMBER MARCH SEPTEMBER DECEMBER ESTIMATED NUMBER OF CANDIDATES 12 NRC FORM 536 (49-20111 Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROveO BY OMS: NO. 3150-0131 EXPIRES: 09/3012014 (09-2011)

Esl!maIed buIden per R!5pOIlSfI 10 comply with !his voIunIa!y infamalim coIedlon request; 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information coIIacIion is used 10 plan budgets ami reswces for operator OPERA TOR LICENSING examina1lons. Send cotm1IInls ragartfing bW1len esIImaIa 10 lila Inlonnalim SeMces Bnmcb (T -5 F53), u.s. Nudear ReguIajory Commissim, WasIIIngIon, DC 20555-0001, at by InIemet eo EXAMINATION DATA mall 10 1nfaroIads.Resnun:e@nrc.gov, ami 10 !he Desk O!IIcer, Office t:A InIormaIIon ami ReguIa\\oIy Mairs, NE0f3.10202, (3150-0131), Office 01 Managemanl and Budge~ WasI1/ng1cn, DC 20503.

If a IllIIIlI1I used to impose an inIormation coIIacIion does nol display a cunenUy vaId OMS COIItroI runbar, lIIe NRC may nol conduct Of SjlIlnSCr, ami 8 IIIIrson is not requin!d 10 respond 10, the information collection.

FACILITY jNRCREGION Oyster Creek Nuclear Generating Station Region I Renewed Facility Operating License No. DPR-16 NRC Docket No. 50-219 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LlCENSEE*PREPARED 0

I 0

0 EXAMINATIONS ESTIMATED NUMBER OF NRC*PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 0

6 0

0 OPERATORS NUMBER Of SENIOR REACTOR 0

4 0

0 OPERATORS* INSTANT NUMBER OF SENIOR REACTOR 0

2 0

0 OPERATORS*UPGRADE NUMBER Of SENIOR REACTOR 0

0 0

0 OPERATORS* LIMITED PROPOSED DATES PRIMARY DATE 5116/2016 ALTERNATE DATE 5/12/2016 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 12 CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION (08.2011)

APPROVED BY OMB: NO, 3150-0131 EXPIRES: 0913012014 Estimated burden per response to candy with ft voluntary Information co on request I hour.

This Infonnat$on cotiection is used to plan budgets and resources for operator examinations. Send comments regarding burden estimale to the Information Servkm Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555 01, or by Internet e-mail to Infocotiects.ResoU

.gov, and to the Dec OScar, ONce of k0ortnation r

ReVilalary Affairs, NEOS-t0202. (31500131),

of Mamagement and Budget, W DC 20503.

If a meatus used to Impose an tntonnatlon collection does not display a currently vato OMB cor*d number, the NRC may not conduct or sponsor, and a person Is not required to respond to, the Infarmatlan collection.

N t

N A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY 2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EMINATIONS OPERATOR LICENSING EXAMINATION DATA FACILITY Peach Bottom Atomic Power Station, Units 2 and 3 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278 1

0 0

0 0

0 0

CV 2016 0

0 0

  • see LGS N/A N/A PROPOSED NUMBER NUMBER OF REACTOR OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE ALTERNATE DATE Cy 2015
  • see LGS 03/23/2015 03/30/2015 Cy 2017
  • see LGS 03/20/2017 03/27/2013 6

7 6

7 CY2018 0

0 0

0 0

13 0

0 0

0 NRC FORM 5W (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMS: NO. 31110..0131 EXPIRES: 0913012014 (09-2011)

Estimated burden per response to comply will this voluntary InIonnallon ooIect!on request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

ThIs InIonnallon coIecl!on Is used to plan budgets and teSOUlCllS for opel'lllOr OPERA TOR LICENSING examlnatfons. Send comments regarding burden eslimlllll to Ih8 IntJrmallon Services Branch (T-5 F53), U.S. Nuclear Regulatory Commfssfon, Washington. DC 20555-0001. or bV Internet e-EXAMINATION DATA mail to Infocollects.Resource@nlc.gov, and 10 Ih8 Desk 0fIItw. O/IIce 01 information and Regulatory Affaits, NEOB-t!l202. (315(1.0131). 0IIIce of Management and Budget. WashfngIon, DC 20503.

If a means used to Impose an information coIecIIon does not display II currently vald OMII contIOI number, !he NRC may not conduct Qr sponsor, and II person Is not required to respond to, !he inIIInnalon coIecIIon.

FACILITY NKI.;KI::UluN Peach Bottom Atomic Power Station, Units 2 and 3 I

Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-277 and 50-278 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED I

0 1

0 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 6

0 6

0 OPERATORS NUMBER OF SENIOR REACTOR 7

0 7

0 OPERATORS -INSTANT NUMBER OF SENIOR REACTOR 3

0 3

0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR

  • see LOS
  • see LOS
  • see LOS
  • see LOS OPERA TORS -LIMITED PROPOSED DATES PRIMARY DATE 03/23/2015 N/A 03/20/2017 N/A ALTERNATE DATE 03/3012015 N/A 03/27/2013 N/A C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0

0 13 0

0 0

0 0

CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3160 -01131 EXPIRES: 09/30/2014 (09-2011)

Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator OPERATOR LICENSING examinations.

Send comments regarding burden estimate to the Information Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-EXAMINATION DATA mad to Infocoltects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20501 If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 III NRC Docket Nos. 50-254 and 50-265 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY 2015 CY 2016 CY 2017 CY 2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

1 0

1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER Cy 2015 Cy 2016 Cy 2017 Cy 2018 NUMBER OF REACTOR 0

3 0

3 OPERATORS NUMBER OF SENIOR REACTOR 0

8 0

8 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE N/A 8/1/16 N/A 8/6/18 ALTERNATE DATE N/A 9/6/16 N/A 9/4/18 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE Cy 2015 Cy 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 11 0

0 0

0 0

0 0

CANDIDATES NRC FORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 Page 1 of 1 NRC FORM 536 U. S. NUCLEAR REGULA TORY COMMISSION APPROVED BY OMB: NO. 3150*0131 EXPIRES: 09/30/2014 (09-2011)

Eslimated burden per response to comply with this voluntary information coUection recuesl: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This information collection is used to plan budgets and resources for operator OPERATOR LICENSING examinations. Send comments regarding burden estimate to the Information Services Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washinglon, DC 20555-0001, or by inlemet e-EXAMINATION DATA mall to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503.

If a means used to impose an information collection does not display a currently vand OMS control number. the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Quad Cities Nuclear Power Station, Units I and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 III NRC Docket Nos. 50-254 and 50-265 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED 0

I 0

I EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2015 CY2016 CY2017 CY2018 NUMBER OF REACTOR 0

3 0

3 OPERATORS NUMBER OF SENIOR REACTOR 0

8 0

8 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE N/A 8/1/16 N/A 8/6/18 ALTERNATE DATE N/A 9/6/16 N/A 9/4/18 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 2015 CY 2016 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF II 0

0 CANDIDATES 0

0 0

0 0

NRC.. ORM 536 (09-2011)

Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 0 Page 1 of 1 APPROVED BY OMB: NO. 3160-0131 EXPIRES: 0913012014 Estimated burden per response to comply with this voluntary kcfomuation coffin request 1 how.

This nformation collection Is used to plan budgets and resources for operator examinations. Send comments regards burden estimate to the Informaft Servlces &anch (T-5 F53), U.S, Mbar Regulatory Commission,

, DC 205550001, or by Internet e-mall to Infocoltecia.Res gov, and to the Desk Other, Ofd of Information and Regulatory Affas. NE08-10202, (3150-0131), tie of Management and 8udg, Washington, DC 20503.

H a means used to loose an kukumatbn collection does not display a currently vafid ON control number, the N RC may not conduct or sponsor, and a person Is not requi red to respond to, the informatn collection.

FACILITY Three Mile Island Nuclear Station, Unit I Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289 A. PROPOSED EXAMINATION PREPA RATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY 2017 CY2018 ESTIMATED NUMBER OF LICENSEE-PREPARED EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY 2015 Cy 2016 CY 2017 CY 2018 NRC FORM 536 U. S. NUCLEAR REGULATORY COMMISSION (09.2011)

OPERATOR LICENSING EXAMINATION DATA 1

0 1

0 0

0 0

0 4

9 0

0 0

0 NUMBER OF REACTOR OPERATORS NUMBER OF SENIOR REACTOR OPERATORS - INSTANT NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR OPERATORS - LIMITED PROPOSED DATES 0

0 5

10 1

0 0

0 0

PRIMARY DATE ALTERNATE DATE 10/12/2015 11/09/2015 05/22/2017 06/12/2017 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE Cy 2015 JUNE SEPTEMBER DECEMBER CY 2014 CH JUNE SEPTEMBER DECEMBER MARCH ESTIMATED NUMBER OF CANDIDATES NRC FORM 536 (09-2011 15 14 Exelon Generation Company, LLC Response to Regulatory Issue Summary 2013-06 0 Page 1 of 1 NRC FORM 636 U. S. NUCLEAR REGULA TORY COMMISSION APPROVED BY OMS: NO. 3160..0131 EXPIRES: 0913012014 (09-2011)

Estlmated buIden per response to comply with this voluntary infonnation oollaction request 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />.

This infonnation coUection Is used til plan budgsls and r_ lor operaIDr OPERA TOR LICENSING

.xamlnetions. Send oomm.nls regarding burden estimaIe to the Infonnation Services Branch (T-5 F53), U.S, Nuclear ReguIa\\IlIy Commission, WashlngIon, DC 20555-0001, or by intamet Il-EXAMINATION DATA mall to InfoooIeeIs.RestlUlC8@lnrc.gov. and to the Desk OHicer. 0HIce ot Information and ReglUtory AffaInI, NEQB.10202, (31so.o131), 0HIce at Management and Budget, Wastmgton, DC 20503.

H a means used to Impose an Inlormatioo colection does not display a COOIlnUy valid OMB conIrol number, the NRC may not conduct or SfXXlSOI', and a per.lOn Is not required to respond to, tile Information coIedion.

FACILITY

"""..... t:UlUN Three Mile Island Nuclear Station, Unit 1 I

Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289 A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY2015 CY2016 CY2017 Cy2018 ESTIMATED NUMBER OF LICENSEE-PREPARED I

0 I

0 EXAMINATIONS ESTIMATED NUMBER OF NRC*PREPARED 0

0 0

0 EXAMINATIONS B. INITIAL OPERA TOR LICENSE EXAMINATIONS PROPOSED NUMBER CY2015 CY2016 CY20t7 CV2018 NUMBER OF REACTOR 4

0 5

0 OPERATORS NUMBER OF SENIOR REACTOR 9

0 10 0

OPERATORS

  • INSTANT NUMBER OF SENIOR REACTOR I

0 I

0 OPERATORS-UPGRADE NUMBER OF SENIOR REACTOR 0

0 0

0 OPERATORS* LIMITED PROPOSED DATES PRIMARY DATE 10/12/2015 OS/2212017 ALTERNATE DATE 1110912015 06/12/2017 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GfE) SCHEDULE CY 2014 CY 2015 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 14 15 CANDIDATES NRC FORM 536 (00-lOll}