Summary of Public Meeting to Discuss NRC Activities, Nuclear Power Issues, and 2012 End-Of-Cycle Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2
ML13170A186
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 06/18/2013
From: Christine Lipa
NRC/RGN-III/DRP/B1
To:
References
Download: ML13170A186 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 18, 2013 LICENSEE: Exelon Generation Company, LLC FACILITY: Quad Cities Nuclear Power Station

SUBJECT:

SUMMARY

OF THE JUNE 11, 2013, PUBLIC MEETING/OPEN HOUSE TO DISCUSS NRC ACTIVITIES, NUCLEAR POWER ISSUES, AND 2012 END-OF-CYCLE PERFORMANCE ASSESSMENT OF QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 On June 11, 2013, an open house public meeting was held at Cordova Civic Center in Cordova, IL, between the U.S. Nuclear Regulatory Commission (NRC) and Quad Cities Nuclear Power Station management and staff. The purpose of the open house meeting was to provide an opportunity for the public to discuss NRC activities, nuclear power issues, and Quad Cities Nuclear Power Station performance for the period of January 1, 2012, through December 31, 2012. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML13136A344 and ML13137A366 respectively. A list of the Open House attendees is enclosed.

The public meeting discussed an overview of the NRCs Mission and Performance Goals, the Reactor Oversight Process (ROP), and national ROP results. The NRC discussed other agency regulatory activities such as nuclear security and nuclear waste.

The NRC also provided discussions related to the NRCs assessment of the Quad Cities Nuclear Power Station performance, which was documented in the March 4, 2012, End-of-Cycle Assessment Letter (reference ADAMS Accession Number ML13060A117). As part of this open house, staff members from both Exelon and the Illinois Emergency Management Agency (IEMA)

were available to address questions and concerns. Slides used to describe the NRC's ROP process and Quad Cities Nuclear Power Station 2012 performance can be found in ADAMS under ML13165A198. Throughout the open house, members of the public were given the opportunity to ask questions of Exelon officials and NRC officials.

/RA by C. Phillips for/____

Christine Lipa, Chief Branch 1 Division of Reactor Projects Docket No. 50-254, 50-265 License No. DPR-29, DPR-30

Enclosure:

As Stated As stated cc w/encl: Distribution via ListServTM

PUBLIC MEETING ATTENDEES June 11, 2013 Nuclear Regulatory Commission C. Lipa J. McGhee B. Cushman T. Ray Illinois Emergency Management Agency C. Mathews C. Settles Scott County Emergency Management Agency R. Bergen Exelon Employees C. Alguire W. Beck S. Darin J. Haas T. Hanley S. Howel T. Petersen J. Wooldridge MidAmerican Energy Company Employees B. Cambell S. Ryan Members of the Public J. Hayes representing Illinois State Representative, Mike Smiddy, 71st District C. Filbert J. Myer Enclosure

were available to address questions and concerns. Slides used to describe the NRC's ROP process and Quad Cities Nuclear Power Station 2012 performance can be found in ADAMS under ML13165A198. Throughout the open house, members of the public were given the opportunity to ask questions of Exelon officials and NRC officials.

/RA by C. Phillips for/____

Christine Lipa, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-254, 50-265 License Nos. DPR-29, DPR-30

Enclosure:

As Stated cc w/encl: Distribution via ListServTM DISTRIBUTION:

See next page DOCUMENT NAME: Quad Cities EOC Mtg Summary CY 2012 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E RIII N RIII RIII NAME CPhillips for CLipa:rj CPhillips for RElliott DATE 06/18/13 06/18/13 OFFICIAL RECORD COPY

Letter to Exelon Generation Company from C. Lipa dated June 18, 2013

SUBJECT:

SUMMARY

OF THE JUNE 11, 2013, PUBLIC MEETING/OPEN HOUSE TO DISCUSS NRC ACTIVITIES, NUCLEAR POWER ISSUES, AND 2012 END-OF-CYCLE PERFORMANCE ASSESSMENT OF QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 DISTRIBUTION:

Vivian Campbell RidsNrrDorlLpl3-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPassessment.Resource@nrc.gov