MONTHYEARML23303A0662023-11-0606 November 2023 October 2023 Environmental Scoping Meetings Re Perry Nuclear Power Plant License Renewal Application Meeting Summary Memo ML23129A6062023-05-0404 May 2023 Special Inspection Team Charters to Evaluate the Circumstances Surrounding the Ground Settling at the Davis-Besse Nuclear Power Station ML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML21096A2282021-03-30030 March 2021 FEMA Disapproval of Davis-Besse Exercise Exemption ML20163A6272020-06-15015 June 2020 Summary of Public Telecon with Energy Harbor on License Renewal for Perry Nuclear Plant ML19182A3562019-07-23023 July 2019 Quarterly Report on the Status of Public Petitions Under Title 10 of the Code of Federal Regulations, Section 2.206 - April 1 to June 30, 2019 ML19162A0102019-06-0707 June 2019 Memorandum to File Environmental Assessment and Finding of No Significant Impact for Firstenergy Nuclear Operating Company'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) and 72.30(C) for Davis Besse ISFSI ML18254A3982018-10-0101 October 2018 Fleet Nuclear Power Plant Adoption of Technical Specifications Task Force Traveler TSTF-546, Revision 0, Revise APRM Channel Adjustment Surveillance Requirement (EPID No. 05000440/L-2018-LLA-0167) ML17004A2952017-01-0505 January 2017 Safety Evaluation Report- Application for Amendment Perry Nuclear Power Plant ML16180A1352016-06-22022 June 2016 Summary of Open House Public Meeting to Discuss NRC Activities, Nuclear Power Issues, and 2015 End-of-Cycle Performance Assessment of Perry Nuclear Power Plant ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML15205A1692015-08-0707 August 2015 ACRS Review of the Davis Besse Nuclear Plant LRA - Transmittal of the Sser ML15182A1912015-07-16016 July 2015 Annual Financial Test for a Parent Company Guarantee Given by Firstenergy Solutions Corporation and Firstenergy Corporation ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis ML14296A6892014-11-10010 November 2014 Summary of September 18, 2014, Meeting with Firstenergy Nuclear Operating Company to Discuss Alternative Source Term Implementation as a Result of Fuel Change IR 05000334/20004122014-07-0808 July 2014 NRC Staff'S Spot-Check Review of First Energy Nuclear Operating Company'S Ownership Interest in Beaver Valley, Units 1 and 2, Perry, and Davis-Besse, Docket No. 05000334, 05000412, 05000440, and 05000346, on June 10, 2014-Finding of No Pote ML14189A1212014-07-0808 July 2014 NRC Staff'S Spot-Check Review of Ohio Edison'S Ownership Interest in Beaver Valley, Unit 2 and Perry, Finding of No Potential Issues ML14099A4642014-05-0606 May 2014 Summary of Public Meetings to Discuss Draft Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Generating Station, Unit 1 ML13280A9062013-10-21021 October 2013 Forthcoming Meeting with Firstenergy Nuclear Operating Company (FENOC) to Discuss Voluntary Risk Informed Fire Protection Amendment for Davis-Besse ML13282A6462013-10-0909 October 2013 Notice of Cancelled Forthcoming Meeting with Firstenergy Nuclear Operating Company (FENOC) to Discuss Proposed Dose Calculations for Fuel ML13142A5122013-07-0202 July 2013 Summary of Telephone Conference Call Held on May 21, 2013, Between NRC and Firstenergy Nuclear Operating Company, Concerning RAI Pertaining to the Davis-Besse Nuclear Power Station, LRA ML13171A2922013-06-13013 June 2013 LTR-13-0540 - Bill Hawkins and Vinod Arora Email San Onofre Nuclear Generating Station (SONGS) Lessons Learn for Davis-Besse ML13154A4442013-06-0404 June 2013 Rai'S Following Ifib Analysis of Fenoc'S 2013 Decommissioning Funding Status Report for Davis-Besse and Perry ML13004A4032013-01-0404 January 2013 Memo - Request for a Deviation from the Reactor Oversight Process Action Matrix for Perry Nuclear Power Plant ML12199A2072012-07-17017 July 2012 Public Meeting Notice to Discuss the 2011 End-of-Cycle Performance Assessment ML12158A4002012-06-0808 June 2012 6/26/2012 Forthcoming Meeting Firstenergy Nuclear Operating Company (FENOC) ML12123A7032012-05-17017 May 2012 Safety Evaluation by the Office of Nuclear Reactor Regulation Annual Financial Test for a Parent Company Guarantee Firstenergy Nuclear Operating Company Beaver Valley Power Station, Unit 1; Docket No. DPR-66 and Perry Nuclear Power Plant ML12111A1712012-04-23023 April 2012 Notice of Forthcoming Meeting with First Energy Nuclear Operating Co. (FENOC) to Discuss a Proposed LAR to Modify Technical Specifications 3.8.1 to Remove Mode Restrictions Associated with Division 3 Surveillance Testing for Perry, Unit 1 ML1206901652012-03-0909 March 2012 Memo - Summary of Public Meeting with Industry Regarding Pwrog'S Boric Acid Corrosion Test Program ML12018A1652012-01-27027 January 2012 Summary of Telephone Conference Call Held on November 9, 2011, Between the NRC and Firstenergy Nuclear Operating Company, Concerning RAI Pertaining to the Davis-Besse, LRA ML14028A5462012-01-25025 January 2012 NRC Telecon Regarding Davis-Besse License Renewal Severe Accident Mitigation Alternatives Analysis Questions ML11363A1712012-01-23023 January 2012 Summary of Telephone Conference Call Held on December 12, 2011 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Request for Additional Information ML11355A0952011-12-29029 December 2011 Summary of Telephone Conference Call Held on December 8, 2011, Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning RAIs Pertaining to the Davis-Besse Nuclear Power Station, LRA ML11348A0212011-12-21021 December 2011 Summary of Telephone Conference Call Held on November 1, 2011 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis Besse Nuclear Pow ML11341A1182011-12-14014 December 2011 Summary of Telephone Conference Call Held on June 15, 2011 Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis-Besse Nuclear Power ML11339A0862011-12-13013 December 2011 Summary of Telephone Conference Call Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning RAIs Pertaining to the Davis-Besse Nuclear Power Station LRA ML11327A0082011-12-0202 December 2011 Summary of Telephone Conference Call Held on September 29, 2011, Between the NRC and Firstenergy Nuclear Operating Company, Concerning RAI Pertaining to the Davis-Besse, LRA ML11327A0792011-12-0202 December 2011 Summary of Telephone Conference Call Held on Between the U.S. Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning Requests for Additional Information Pertaining to the Davis Besse Nuclear Power Station ML11327A0872011-12-0202 December 2011 Summary of Telephone Conference Call Held on July 27, 2011, Between the NRC and Firstenergy Nuclear Operating Company Concerning RAI Pertaining to the Davis-Besse, LRA ML11279A2182011-10-0606 October 2011 Memo - Task Interface Agreement - Evaluation of Compliance with Code for Examination of Flange Stud Holes on the Replacement Vessel Head at the Davis-Besse Nuclear Power Station (TIA 2011-015) ML11242A0032011-09-12012 September 2011 Summary of Conference Call Held on August 4, 2011, Between the NRC and FENOC Concerning Requests for Additional Information Pertaining to the Davis-Besse License Renewal Application ML1122701392011-08-15015 August 2011 Request for Additional Information Response Clarification from Davis-Besse Nuclear Power Station in Support of License Renewal Application Review ML11173A2002011-08-0101 August 2011 Summary of Public Scoping Meetingsconducted Related to the Review of the Davis-Besse Nuclear Power Station, Unit 1, LRA ML11193A2032011-07-26026 July 2011 Final Response to TIA 2011-001, Davis-Besse Nuclear Power Station Safety-Related Batteries Electrical Separation Design and Licensing Bases ML11174A2322011-06-21021 June 2011 for the Record-06-21-2011: NRC Ensures Public Safety Through Rigorous Oversight of Nuclear Power Plant Safety Standards ML1108202762011-06-0303 June 2011 Summary of Site Audit Related to the Review of the License Renewal Application for Davis-Besse Nuclear Power Station, Unit 1 ML11174A2472011-05-31031 May 2011 for the Record-05-31-2011: NRC Chairman Gregory B. Jaczko'S Statement on Nrc'S Commitment to Safety ML1110806902011-04-20020 April 2011 Notice of Meeting with First Energy Nuclear Operating Company (FENOC) to Discuss a Proposed LAR to Delete Technical Specification 5.5.8g, Steam Generator (SG) Program Auxiliary Feedwater Header Inspections ML1028702612010-10-22022 October 2010 11/04/10 Notice of Meeting to Discuss the License Renewal Process and Environmental Scoping for Davis-Besse Nuclear Power Station License Renewal Application Review 2023-05-04
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML23193A7842023-07-13013 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000346/2023402 ML23131A2732023-05-15015 May 2023 Notification of NRC Supplemental Inspection 95001 and Request for Information ML23033A0322023-02-0101 February 2023 NRR E-mail Capture - Request for Additional Information for Davis-Besse's 2022 Steam Generator Inspection Report (L-2022-LRO-0115) ML22357A0302022-12-23023 December 2022 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000346/2023010 ML22266A1102022-09-23023 September 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding July 21, 2022, Request for Withholding Information from Public Disclosure ML22234A1482022-08-22022 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22214A7042022-08-0202 August 2022 Reissue - Davis-Besse Nuclear Power Station, Unit 1 Notification of Nrc Fire Protection Team Inspection Request for Information: Inspection Report 05000346/2022011 ML22187A0992022-07-0606 July 2022 Notification of NRC Supplemental Inspection (95001) and Request for Information ML22182A4442022-07-0202 July 2022 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection Report 05000440/2022010 ML22164A8572022-06-13013 June 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Emergency Plan ML22136A2122022-05-16016 May 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 ML22130A5662022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22118A6862022-04-28028 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML22112A1092022-04-22022 April 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Revise the Design Basis for the Shield Building ML22089A2452022-03-30030 March 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12 ML22055A0872022-02-23023 February 2022 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Relief Request RP-3 IR 05000346/20210912021-12-17017 December 2021 NRC Inspection Report (05000346/2021091) Preliminary Greater than Green Finding ML21321A3792021-11-16016 November 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Alternative to Extend the Steam Generator Weld Inspection Interval ML21301A0992021-10-28028 October 2021 Draft Request for Additional Information: Proposed Alternate for Examination of Steam Generator Welds - Energy Harbor Nuclear Corp., Davis-Besse Nuclear Power Station, Unit No. 1 ML21203A3252021-07-28028 July 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000346/2021011 ML21168A0662021-06-17017 June 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000440/2021010 ML21155A1952021-06-0404 June 2021 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Davis Besse Nuclear Power Station ML21110A6852021-04-19019 April 2021 NRR E-mail Capture - Final RAI - Perry - Request to Review the Emergency Plan ML21050A1032021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-3, Rev. 0 and VR-5, Rev. 0 ML21050A1072021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-7, Rev. 0 ML21050A1112021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-4, Rev. 0 and VR-6, Rev. 0 ML21049A2702021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request SR-2, Rev. 0 (EPID: L-2021-LLR-0005) (2nd Round RAI) ML21041A5452021-02-10010 February 2021 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding Steam Generator Tube Inspection Reports ML21032A3422021-02-0101 February 2021 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Alternative Request SR-2, Rev. 0 ML21020A0392021-01-20020 January 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000440/2021010 ML21007A3732021-01-0707 January 2021 NRR E-mail Capture - (External_Sender) (External) Request for Additional Information Regarding License Amendment Request to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff, ML21004A1442020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding License Amendment Request to Incorporate the Applicable Standard Technical Specification 5.2.2, Unit Staff ML20325A2782020-11-20020 November 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Part 73 Force-on-Force Exemption ML20300A5592020-10-27027 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML20289A1012020-10-0505 October 2020 NRR E-mail Capture - Final 2nd Round RAI - Perry Request for Relief - Proposed Alternative Request IR-056, Rev. 3 ML20191A0192020-07-0101 July 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Extension to License Expiration Date by Recapturing Low-Power Testing Time ML20154K7642020-06-0202 June 2020 NRR E-mail Capture - Davis-Besse Nuclear Power Station, Unit No. 1 - Request for Additional Information Regarding License Amendment Request to Adopt TSTF-425 ML20133K0632020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20133J9792020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20127H8692020-05-0606 May 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request IR-054, Rev. 2 ML20127H8672020-05-0606 May 2020 NRR E-mail Capture - Beaver Valley, Davis-Besse, and Perry - Request for Additional Information Regarding Request for Exemptions from Part 73 Security Requalification Requirements ML20021A3162020-01-21021 January 2020 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request to Revise Containment Leakage Rate Testing ML19192A2222019-07-18018 July 2019 Request for Additional Information Regarding Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML19179A1382019-06-28028 June 2019 NRR E-mail Capture - Davis-Besse - Request for Additional Information Regarding the Decommissioning Quality Assurance Program ML19164A1532019-06-13013 June 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request for Post-Shutdown Emergency Plan ML19162A3922019-06-11011 June 2019 NRR E-mail Capture - Davis-Besse Nuclear Power Station - Request for Additional Information Regarding License Amendment Request for Permanently Defueled Technical Specifications ML19143A0732019-05-29029 May 2019 FENOC Fleet - Beaver Valley, Units 1 and 2; Davis-Besse, Unit 1, Perry, Unit 1 - Supplemental Information Needed for Acceptance of Requested Licensing Action; Application for Order Consenting to License Transfer and Conforming Amendments 2023-08-15
[Table view] |
Text
June 4, 2013 MEMORANDUM TO: Jeremy Bowen, Chief Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Christopher M. Regan, Chief /RA/
Financial Analysis and International Projects Branch Division of Inspection and Regional Support Office of Nuclear Reactor Regulation
SUBJECT:
FIRSTENERGY NUCLEAR OPERATING COMPANY - 2013 DECOMMISSIONING FUNDING STATUS REPORTS - REQUEST FOR ADDITIONAL INFORMATION Enclosed is the subject Request for Additional Information (RAI) for FirstEnergy Nuclear Operating Company (FENOC) for Davis-Besse Nuclear Power Station and Perry Nuclear Power Plant, 2013 Decommissioning Funding Status (DFS) reports, from the Financial Analysis and International Projects Branch (IFIB). IFIB staff requests that the RAI be issued to the licensee with a response to be provided 30 days from issuance.
Enclosure:
As stated CONTACT: Richard H. Turtil, NRR/DIRS 301-415-2308
ML13154A444 OFFICE: NRR/DIRS/IFIB NRR/DIRS/IFIB: BC NAME: RTurtil CRegan DATE: 6/3/2013 6/4/2013 REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION 2013 DECOMMISSIONING FUNDING STATUS REPORT FOR FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC)
DAVIS-BESSE NUCLEAR POWER STATION AND PERRY NUCLEAR POWER PLANT The requests for additional information (RAIs) provided are in response to FENOCS 2013 Decommissioning Funding Status (DFS) report. On March 25, 2013, FENOC submitted to the Nuclear Regulatory Commission (NRC) the 2013 Decommissioning Funding Status (DFS) report for Davis-Besse Nuclear Power Station and Perry Nuclear Power Plant (see ML13084A374) as required under 10 CFR 50.75(f)(1). The NRC staff has reviewed the information provided in the submittal and determined that the following additional information is required in order to complete its review. FENOC should provide a response within 30 days from the date of this letter.
RAI #1 for Davis-Besse Nuclear Power Station and Perry Nuclear Power Plant: Reporting Requirements Indicate what portion of the accumulated fund balances are for radiological decommissioning activities only. Specify if any of the $478,270,692 for Davis-Besse Nuclear Power Station and
$462,378,077 for Perry Nuclear Power Plant, is for non-radiological decommissioning costs such as spent fuel management or other non-radiological decommissioning activities.
On March 25, 2013, FENOC provided the amount accumulated in the decommissioning trust fund at the end of the calendar year preceding the date of the report for items included in 10 CFR 50.75 (b) and (c). Confirm that the dollar amounts identified above are exclusively for radiological decommissioning.
Per 10 CFR 50.75(f)(1), licensees must identify the amount accumulated to the end of the calendar year preceding the date of the report. This actual amount is dedicated for NRC decommissioning activities as defined in 10 CFR 50.2.
RAI #2 for Davis-Besse Nuclear Power Station: Site Specific Cost Estimate Submit a preliminary site specific decommissioning cost estimate, or identify the NRC ADAMS ML document reference number for such an estimate if previously submitted, which includes an up-to-date assessment of the major factors that could affect the cost to decommission the Davis-Besse Nuclear Power Station.
Per 10 CFR 50.75(f)(3), each power reactor licensee shall at or about 5 years prior to the projected end of operations submit a preliminary decommissioning cost estimate which includes an up-to-date assessment of the major factors that could affect the cost to decommission. As presently scheduled, termination of operations for the Davis-Besse Nuclear Power Station is currently set for April 2017.
RAI #2 for Perry Nuclear Power Plant: Use of Parent Company Guarantee (Current Parent Company Guarantee)
Provide details that address the corporate and financial tests and requirements pertaining to the current $95 million Parent Guarantee cited by FENOC, as well as the dollar amount of the portion of the current $95 million Parent Guarantee that is being applied to the Perry Nuclear Power Plant decommissioning funding requirement In its March 25, 2013, submittal, FENOC recognized that a shortfall exists for its Perry Nuclear Power Plant, when the existing trust balances and assumed earnings are compared with the NRC formula amount. FENOC reported that when the Perry Nuclear Power Plant portion of an existing $95 million Parent Guarantee is included in the calculation, the remaining shortfall is
$12,319,654. To resolve the shortfall, FENOC indicated that it will obtain a Parent Guarantee in accordance with 10 CFR 50.75(b)(2) and (b)(3) within 90 days of the date of its March 25, 2013, submittal.
Per 10 CFR 50.75(d)(2)(ii) and 50.75(e)(1)(iii)(B), financial assurance may be provided by parent company guarantee. Such use must be based on financial test criteria, including that contained in appendix A to 10 CFR part 30.
RAI #3 for Perry Nuclear Power Plant: Use of Parent Company Guarantee (Proposed 2nd Parent Company Guarantee to Address Shortfall)
Provide details that address the corporate and financial tests and requirements pertaining to the proposed 2nd Parent Guarantee referred to by FENOC that will be used to resolve the current Perry Nuclear Power Plant shortfall, as well as the dollar amount of that Parent Guarantee that will be used to resolve the current Perry Nuclear Power Plant shortfall.
In its March 25, 2013, submittal, FENOC recognized that a shortfall exists for the Perry Nuclear Power Plant, when the existing trust balances and assumed earnings are compared with the NRC formula amount. FENOC reported that when the Perry Nuclear Power Plant portion of an existing $95 million Parent Guarantee is included in the calculation, the remaining shortfall is
$12,319,654. To resolve the shortfall, FENOC indicated that it will obtain a Parent Guarantee in accordance with 10 CFR 50.75(b)(2) and (b)(3) within 90 days of the date of its March 25, 2013, submittal.
Per 10 CFR 50.75(d)(2)(ii) and 50.75(e)(1)(iii)(B), financial assurance may be provided by parent company guarantee. Such use must be based on financial test criteria, including that contained in appendix A to 10 CFR part 30.