UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 28, 2013 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
DRESDEN CONFIRMATION OF INITIAL LICENSE EXAMINATION
Dear Mr. Pacilio:
In a telephone conversation on May 3, 2013, between Mr. R. K. Walton, NRC Chief Examiner and Mr. J. Nelson, Lead Exam Developer - Dresden Station, arrangements were made for the administration of licensing examinations at the Dresden Nuclear Power Station during the week(s) of October 21 and October 23, 2013.
In addition, the U. S. Nuclear Regulatory Commission (NRC) will make an examination validation visit to your facility the week of August 26, 2013, for a pre-onsite validation visit with the intent to develop the operating test. The NRC will also visit the site the week of September 30, 2013, for an onsite validation of the operating test and written examination.
As agreed during the telephone conversation, the staff of the NRC will prepare the examinations based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors." Your staff will be given the opportunity to review the examinations during the week of August 19, 2013.
To meet the above schedule, it will be necessary for your staff to furnish the reference materials identified in Attachment 3 to ES-201 by June 10, 2013. We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Any delay in receiving the required reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations and operating tests, it will be necessary for your staff to provide adequate space and accommodations in accordance with ES-402, and to make the simulation facility available on the dates noted above. In accordance with ES-302, your staff should retain the original simulator performance data (e.g., system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations and operating tests are being administered.
M. Pacilio To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The public reporting burden for this collection is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC=s Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. Mr. J. Nelson has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Walton at (630) 829-9836, or I can be reached at (630) 829-9707.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237, 50-249 License Nos. DPR-19 and DPR-25 cc w/encl:
Distribution via ListServTM Training Mgr.
Paul DiGiovanna Paul.digiovanna@exeloncorp.com
M. Pacilio To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver requests (if any) (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary. Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The public reporting burden for this collection is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC=s Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. Mr. J. Nelson has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRC's examination procedures and guidelines, please contact Mr. Walton at (630) 829-9836, or I can be reached at (630) 829-9707.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-237, 50-249 License Nos. DPR-19 and DPR-25 cc w/encl:
Distribution via ListServTM Training Mgr.
Paul DiGiovanna Paul.digiovanna@exeloncorp.com DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress\\Ltr 52813 Dresden Confirmation of Initial License Examination.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII:DRS RIII:DRS RIII RIII NAME RKWalton:ls HPeterson DATE 5/28/13 5/28/13 OFFICIAL RECORD COPY
Letter to Mr. Michael J. Pacilio from Mr. Hironori Peterson dated May 28, 2013.
SUBJECT:
DRESDEN CONFIRMATION OF INITIAL LICENSE EXAMINATION DISTRIBUTION:
Doug Huyck RidsNrrDorlLpl3-2 Resource RidsNrrPMDresden Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak James McHale Paul DiGiovanna