Meeting Notice Public to Discuss NRC End-of-Cycle Assessment of Braidwood Station Unit 1 and 2 Performance for the 2012 Calendar Year
ML13143A352
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 05/23/2013
From: Eric Duncan
Region 3 Branch 3
To:
References
Download: ML13143A352 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 23, 2013 NOTICE OF SIGNIFICANT MEETING THIS MEETING IS OPEN TO PUBLIC ATTENDANCE Name of Licensee: Exelon Generation Company, LLC Name of Facility: Braidwood Station, Unit 1 and 2 Docket Nos.: 50-456; 50-457 Date and Time of Meeting: Thursday, August 8, 2013, 6:00 p.m. (CDT)

Location of Meeting: Braidwood City Hall 141 W. Main Street Braidwood, Illinois 60408 Purpose of Meeting: Discuss NRC end-of-cycle assessment of Braidwood Station Unit 1 and 2 performance for the 2012 calendar year. The NRCs Policy Statement, Enhancing Public Participation in NRC meetings, effective May 28, 2002, applies to this meeting. The policy statement may be found on the NRC website, www.nrc.gov, and contains information regarding visitors and security.

Meeting Category: This is a Category 1 Meeting. The public is invited to observe this meeting and will have one or more opportunities to communicate with the NRC after the business portion of the meeting, but before the meeting is adjourned.

NRC Attendees K. OBrien, Acting Deputy Director, DRP E. Duncan, Chief, DRP Branch 3 J. Benjamin, Senior Resident Inspector A. Garmoe, Resident Inspector Others as assigned

Notice of Significant Licensee Meeting Licensee Attendees D. Enright, Site Vice President M. Kanavos, Plant Manager Others as assigned Note: Attendance at this meeting by NRC personnel, other than those listed above, should be made known to Eric Duncan at (630) 829-9620 by Friday, August 2, 2013.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or transcript or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact.

Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

Because meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances, such as severe weather, confirm the meeting schedule with the meeting contact.

Meeting

Contact:

Eric Duncan, Chief Branch 3 (630) 829-9620 Eric.Duncan@nrc.gov Approved By: /RA By Jamie C. Benjamin Acting For/

Eric R. Duncan, Chief Branch 3 Division of Reactor Projects Notice of Significant Licensee Meeting Licensee Attendees

D. Enright, Site Vice President M. Kanavos, Plant Manager Others as assigned Note: Attendance at this meeting by NRC personnel, other than those listed above, should be made known to Eric Duncan at (630) 829-9620 by Friday, August 2, 2013.

The NRC provides reasonable accommodation to individuals with disabilities where appropriate. If you need a reasonable accommodation to participate in this meeting, or need this meeting notice or transcript or other information from the meeting in another format (e.g., Braille, large print), please notify the NRCs meeting contact.

Determinations on requests for reasonable accommodation will be made on a case-by-case basis.

Because meetings are sometimes canceled or rescheduled as a result of unforeseen circumstances, such as severe weather, confirm the meeting schedule with the meeting contact.

Meeting

Contact:

Eric Duncan, Chief Branch 3 (630) 829-9620 Eric.Duncan@nrc.gov Approved By: /RA By Jamie C. Benjamin Acting For/

Eric R. Duncan, Chief Branch 3 Division of Reactor Projects DOCUMENT NAME: G:\DRPIII\Branch TSS\ALL EOC\EOC CY 2013 (Issued 2013) Meeting Notices\Braidwood 2012 EOC Public Meeting Notice.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RNg:dtp EDuncan*JCB for DATE 05/23/13 05/23/13 OFFICIAL RECORD COPY Notice of Significant Licensee Meeting DISTRIBUTION:

Doug Huyck, Region III Coordinator, OEDO Allen Howe, Deputy Director, Division of Inspection and Regional Support, NRR RidsNrrDorlLpl3-2 Resource RidsNrrPMBraidwood Resource PMNS Resource Steven Reynolds, Director, Division of Reactor Projects, RIII Gary Shear, Director, Division of Reactor Safety, RIII Kenneth OBrien, Deputy Director, Division of Reactor Projects, RIII Patrick Louden, Deputy Director, Division of Reactor Safety, RIII DRP Branch Chief SRI, Braidwood DRS Branch Chiefs:

Robert Daley Billy Dickson Donald Funk David Hills Hironori Peterson AnnMarie Stone Allan Barker, Regional State Liaison Officer, RIII Viktoria Mitlyng, RIII Public Affairs Prema Chandrathil, RIII Public Affairs Tammy Tomczak, ORA Patricia Buckley, ORA Marjorie Zerth, DRP