Supplement to Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regards to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)
ML13126A208
Person / Time
Site: Surry, Turkey Point  NextEra Energy icon.png
Issue date: 04/30/2013
From: Grecheck E
Virginia Electric & Power Co (VEPCO)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
12-163C, EA-12-049
Download: ML13126A208 (5)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 10 CFR 2.202 EA-12-049 April 30, 2013 Attention: Document Control Desk Serial No.: 12-163C U.S. Nuclear Regulatory Commission NL&OS/MAE: RO Washington, D.C. 20555-0001 Docket Nos.: 50-280/281 License Nos.: DPR-32/37 VIRGINIA ELECTRIC AND POWER COMPANY SURRY POWER STATION UNITS 1 AND 2 SUPPLEMENT TO OVERALL INTEGRATED PLAN IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS (ORDER NUMBER EA-12-049)

On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (the Order) to Virginia Electric and Power Company (Dominion). Dominion responded to the Order by letters dated March 26, 2012, October 25, 2012, and February 28, 2013 (Serial Nos.12-163, 12-163A and 12-163B, respectively).

The purpose of this letter is to supplement the Overall Integrated Plan that was provided in Dominion's February 28, 2013 letter. The additional information is provided in the attachment to this letter.

If you have any questions, please contact Ms. Margaret Earle at (804) 273-2768.

Sincerely, Eugene S. Grecheck Ii m

! VICKI L. HULL Vice President Nuclear Engineering and Development i Notary Public Virginia Electric and Power Company q Commonwealth of Virginia 140542 My Commission Expires May 31. 2014 COMMONWEALTH OF VIRGINIA ) ml L__ v - v v v . . . - . - V

)

COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Eugene S. Grecheck who is Vice President Nuclear Engineering and Development of Virginia Electric and Power Company. He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me this .I "*day of, . rll ,2013.

5 3 Ig i/LLY. AILVIL My Commission Expires: - -

Notary Public (SEAL) 1kt :s_

Serial No. 12-163C Docket Nos. 50-280/281 Order EA-12-049 Page 2 of 2 Attachment Commitments made by this letter: No New Regulatory Commitments cc: Director of Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 U, S. Nuclear Regulatory Commission, Region II Regional Administrator Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 Ms. K. R. Cotton NRC Project Manager Surry U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas NRC Project Manager North Anna U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 G-9A 11555 Rockville Pike Rockville, MD 20852-2738 Ms. J. A. Kratchman U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 09 D2 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Surry Power Station

Serial No. 12-163C Docket Nos. 50-280/281 Order EA-12-049 Attachment Supplement To Overall Integrated Plan Requirements for Mitigation Strategies For Beyond-Design-Basis External Events Surry Power Station Units 1 and 2 Virginia Electric and Power Company (Dominion)

Serial No. 12-163C Docket Nos. 50-280/281 Order EA-12-049 Page 1 of 2 Supplement To Overall Integrated Plan Requirements for Mitigation Strategies For Beyond-Design-Basis External Events By letter dated February 28, 2013, Serial No. 12-163B, Dominion provided an Overall Integrated Plan (OIP) to address Beyond-Design-Basis (BDB) events at Surry Units 1 and 2 as required by Order Number EA-12-049, dated March 12, 2012. It was stated that the OIP was based on conceptual design information and that final design information and revisions would be provided via updates. Various open items were inserted into the OIP to identify information that would be provided or confirmed at a later date. This attachment provides the basis for closure of Open Item Nos. 2 and 3.

Open Item No. 2 - Preliminaryanalyses have been performed to determine the Class 1E battery life based on implementation of load stripping actions.

The final battery life duration will be provided when the analyses are completed.

The completed analyses of the Class 1E station emergency battery life determined an increase in extended battery life from the original 14 hours1.62037e-4 days <br />0.00389 hours <br />2.314815e-5 weeks <br />5.327e-6 months <br /> to 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> for both Surry Units 1 and 2. This provides additional time to setup and engage Phase 2 BDB equipment as part of the long-term coping strategy.

This response closes Open Item No. 2 for Surry. .

Open Item No. 3 - Preliminaryanalyses have been performed to determine the time to steam generator overfill without operator action to reduce AFW flow, time to steam generatordryout without AFW flow, and time to depletion of the useable volume of the ECST. The final durations will be provided when the analyses are completed.

The analysis for secondary side inventories and heat removal has been finalized. Slight changes were observed from the preliminary values reported in the OIP. These changes, applicable to both Surry Units 1 and 2, are as follows:

1) The time to steam generator (SG) overfill without operator action decreased from 2.3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> to 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />. As indicated in the February 28, 2013 OIP submittal, the loss of all AC power directs operations personnel to locally throttle AFW flow from the turbine driven auxiliary feedwater (TDAFW) pump to all three SGs to prevent overfilling of the SGs.

Operators could access the area in less than 20 minutes and begin to control AFW flow within the following 10 minutes in order to maintain SG levels. Therefore, the throttling of AFW flow to prevent SG overfill can be accomplished within the decreased time constraint of 1.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />.

Serial No. 12-163C Docket Nos. 50-280/281 Order EA-12-049 Page 2 of 2

2) The time for SG dryout increased from 50 minutes to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This provides additional time, if needed, to perform a manual start of the TDAFW pump as part of the Phase 1 core cooling strategy.
3) The time to depletion of the water supply from the emergency condensate storage tank (ECST) increased from 4.4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to 5.0 hours0 days <br />0 hours <br />0 weeks <br />0 months <br />. This increase provides additional time to realign the suction supply from the emergency condensate makeup tank (ECMT) to the TDAFW pump as part of the long-term core cooling strategy. The cumulative time for depletion of both the ECST and the ECMT also changed from 13.1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to 14.2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. This increase provides additional time to setup and engage Phase 2 BDB equipment as part of the long-term core cooling strategy.

This response closes Open Item No. 3 for Surry.