NRR E-mail Capture - Quad Cities Relief Request No. I5R-02 - Request for Additional Information
ML13123A086
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 05/02/2013
From: Blake Purnell
Plant Licensing Branch III
To: Nicely K
Exelon Corp
References
TAC ME9670, TAC ME9671
Download: ML13123A086 (2)


Text

NRR-PMDAPEm Resource From: Purnell, Blake Sent: Thursday, May 02, 2013 2:54 PM To: ken.nicely@exeloncorp.com Cc: Mozafari, Brenda; Bowen, Jeremy; Mitchel.Mathews@exeloncorp.com

Subject:

Quad Cities Relief Request No. I5R Request for Additional Information OFFICE OF NUCLEAR REACTOR REGULATION REQUEST FOR ADDITIONAL INFORMATION QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 EXELON GENERATION COMPANY, LLC RELIEF REQUEST NO. I5R-02 DOCKET NUMBERS 50-254 AND 50-265 TAC NOS. ME9670 AND ME9671 By letter to the U.S. Nuclear Regulatory Commission (NRC) dated September 28, 2012 (Agencywide Documents Access and management System (ADAMS) Accession No. ML12275A070), as supplemented by letter dated November 28, 2012 (ADAMS Accession No. ML12333A263), Exelon Generation Company, LLC (the licensee) submitted several proposed relief requests for the Quad Cities Nuclear Power Station, Units 1 and 2. The NRC staff determined that the following additional information is necessary to complete the review of relief request I5R-02. This request for additional information (RAI) is in addition to the RAI sent to you on April 24, 2013, and the associated RAI numbering is continued. To support the schedule for approval the response to this request is expected by June 3, 2013.

Based on the NRC staffs review of Relief Request I5R-02:

4. The description and disposition of the gap identified in Attachment 1 of relief request I5R-02 for supporting requirement DA-C12 does not address the requirements in the American Society of Mechanical Engineers (ASME)/American Nuclear Society (ANS) RA-Sa-2009, Addenda to ASME/ANS RA-S-2008: Standard for Level 1/Large Early Release Frequency Probabilistic Risk Assessment for Nuclear Power Plant Applications. Provide verification that a review was conducted that shows support system dependencies are properly captured as required by the standard. In addition, specify whether peer-review or self-assessment results indicate whether this supporting requirement is categorized as capability Category I or not-met. If categorized as not-met, provide the disposition that ascertains the supporting requirement is now capability Category I.

A copy of this email will be placed into ADAMS and made publicly available.

Sincerely, Blake Purnell, Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ph: 301-415-1380 1

Hearing Identifier: NRR_PMDA Email Number: 682 Mail Envelope Properties (Blake.Purnell@nrc.gov20130502145400)

Subject:

Quad Cities Relief Request No. I5R Request for Additional Information Sent Date: 5/2/2013 2:54:02 PM Received Date: 5/2/2013 2:54:00 PM From: Purnell, Blake Created By: Blake.Purnell@nrc.gov Recipients:

"Mozafari, Brenda" <Brenda.Mozafari@nrc.gov>

Tracking Status: None "Bowen, Jeremy" <Jeremy.Bowen@nrc.gov>

Tracking Status: None "Mitchel.Mathews@exeloncorp.com" <Mitchel.Mathews@exeloncorp.com>

Tracking Status: None "ken.nicely@exeloncorp.com" <ken.nicely@exeloncorp.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2291 5/2/2013 2:54:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: