Units 1 and 2 Project Manager Assignment
ML13095A098
Person / Time
Site: Saint Lucie, Turkey Point  NextEra Energy icon.png
Issue date: 04/09/2013
From: Jessie Quichocho
Plant Licensing Branch II
To: Nazar M
Florida Power & Light Co
Quichocho J NRR/DORL/LPL2-2
References
Download: ML13095A098 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 9, 2013 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT NUCLEAR GENERATING UNITS. 3 AND 4 ST. LUCIE PLANT, UNITS 1 AND 2 - PROJECT MANAGER ASSIGNMENTS

Dear Mr. Nazar:

This letter is to inform you that effective April 8, 2013, Mr. Tracy Orf is on a special assignment for approximately 6 months. In the interim Ms. Farideh E. Saba will be assigned as the U.S. Nuclear Regulatory Commission's Licensing Project Manager for Turkey Point, Units 3 and 4; Mr. Siva P. Lingam will be assigned as the Project Manager for St. Lucie, Units 1 and 2.

Ms. Saba may be reached at 301-415-1447 or bye-mail to Farideh.Saba@nrc.gov.

Mr. Lingam may be reached at 301-415-1564 or bye-mail to Siva.Lingam@nrc.gov.

Sincerely, e Ie F. Quichocho, Chief ant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335 and 50-389 cc: Distribution via Listserv

April 9, 2013 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

TURKEY POINT NUCLEAR GENERATING UNITS. 3 AND 4 ST. LUCIE PLANT, UNITS 1 AND 2 - PROJECT MANAGER ASSIGNMENTS

Dear Mr. Nazar:

This letter is to inform you that effective April 8, 2013, Mr. Tracy Orf is on a special assignment for approximately 6 months. In the interim Ms. Farideh E. Saba will be assigned as the U.S. Nuclear Regulatory Commission's Licensing Project Manager for Turkey Point, Units 3 and 4; Mr. Siva P. Lingam will be assigned as the Project Manager for St. Lucie, Units 1 and 2.

Ms. Saba may be reached at 301-415-1447 or bye-mail to Farideh.Saba@nrc.gov.

Mr. Lingam may be reached at 301-415-1564 or bye-mail to Siva.Lingam@nrc.gov.

Sincerely, IRA!

Jessie F. Quichocho, Chief Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-250, 50-251, 50-335 and 50-389 cc: Distribution via Listserv DISTRIBUTION:

PUBLIC LPL2-2 Reading RidsRgn2MailCenter RidsAcrsAcnw_MailCTR RidsNrrDorlLpl2-2 RidsNrrDorl Resource RidsNrrOd RidsNrrLABClayton RidsNrrPMTurkeyPoint RidsNrrPMSt. Lucie RidsOgcMailCenter S. Lingam, DORL C. Bladey, ADM/DAS/RDB L. Cox, DORL F. Saba, DORL ADAMS Accession No.: ML13095A098 OFFICE NRR/LPL2-2/PM NRR/LPL2-2/PM NRR/LPL2-2/LA NRR/LPL2-2/BC NAME FSaba SLingam BClayton JQuichocho DATE 4/5/13 4/8/13 4/8/13 4/9/13 OFFICIAL RECORD COpy