Other: ML13060A357, ML14251A231, ML14323A680, ML15057A228, ML15089A123, PLA-6980, Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licence with Regard to Reliable Spent Fuel Pool Level Instrumentation (EA-12-051), PLA-7073, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051), PLA-7137, Second Six-Month Status Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, PLA-7138, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) PLA-7138, PLA-7222, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (NRC Order EA-12-051), PLA-7296, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Level Instrumentation (NRC Order EA-12-051)
|
MONTHYEARPLA-6980, Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licence with Regard to Reliable Spent Fuel Pool Level Instrumentation (EA-12-051)2013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licence with Regard to Reliable Spent Fuel Pool Level Instrumentation (EA-12-051) Project stage: Other ML13060A3572013-02-28028 February 2013 Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (NRC Order EA-12-049) Project stage: Other ML13163A0032013-06-17017 June 2013 Public LTR - Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (EA-12-051) Project stage: RAI PLA-7026, Response to Request for Additional Information on Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation2013-07-0303 July 2013 Response to Request for Additional Information on Overall Integrated Plan in Response to Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: Response to RAI PLA-7073, First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051)2013-08-26026 August 2013 First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) Project stage: Other ML13295A6062013-11-0606 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI PLA-7138, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) PLA-71382014-02-27027 February 2014 Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (NRC Order EA-12-051) PLA-7138 Project stage: Other PLA-7137, Second Six-Month Status Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-02-28028 February 2014 Second Six-Month Status Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML14251A2312014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard Requirements for Mitigation Strategies for Beyond-Design-Basis External Events(Nrc Order EA-12-049) PLA-7204 Project stage: Other PLA-7222, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (NRC Order EA-12-051)2014-08-27027 August 2014 Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. (NRC Order EA-12-051) Project stage: Other ML14323A6802014-11-24024 November 2014 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other ML15057A2282015-02-25025 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (NRC Order EA-12-049) PLA-7295 Project stage: Other PLA-7296, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Level Instrumentation (NRC Order EA-12-051)2015-02-25025 February 2015 Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Level Instrumentation (NRC Order EA-12-051) Project stage: Other ML15089A1232015-04-13013 April 2015 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 (TAC Nos. MF0888, MF0889, MF0890, and MF0891 Project stage: Other 2014-11-24
[Table View] |
Text
Timothy S. Rausch Senior Vice President & Chief Nuclear Officer FEB 2 8 l013 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-001 PPL Susquehanna, LLC 769 Salem Boulevard Berwick, PA 18603 Tel. 570.542.3345 Fax 570.542.1504 tsrausch @pplweb.com SUSQUEHANNA STEAM ELECTRIC STATION OVERALL INTEGRATED PLAN IN RESPONSE I
I TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQIDREMENTS FOR MITIGATION STRATEGIES FOR BEYOND DESIGN BASIS EXTERNAL EVENTS (NRC ORDER EA-12-049)
PLA-6981 Docket Nos. 50-387 50-388
References:
- 1) NRC Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events dated March 12, 2012.
- 2) NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External events," Revision 0, dated August 29, 2012.
- 3) NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,"
Revision 0, dated August, 2012.
- 4) PLA-6923: PPL Susquehanna, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation strategies for Beyond-Design-Basis External events (Order Number EA-12-049), dated October 29, 2012.
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued an order (Reference 1) to PPL Susquehanna, LLC (PPL). Reference 1 was immediately effective and directs Susquehanna Steam Electric Station to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an Overall Integrated Plan by February 28, 2013.
The NRC Interim Staff Guidance (ISG) (Reference 2) was issued August 29, 2012 which Document Control Desk PLA-6981 endorses industry guidance document NEI 12-06, Revision 0 (Reference 3) with clarifications and exceptions identified in Reference 2. Reference 3 provides direction regarding the content of this Overall Integrated Plan.
Reference 4 provided PPL' s initial status report regarding mitigation strategies, as required by Reference 1.
The purpose of this letter is to provide the Overall Integrated Plan pursuant to Section IV, Condition C.l, of Reference 1. This letter confirms PPL has received Reference 2 and has an Overall Integrated Plan developed in accordance with the guidance for defining and deploying strategies that will enhance the ability to cope with conditions resulting from beyond-design-basis external events.
The information in Enclosure 1 provides the PPL Overall Integrated Plan for mitigation strategies pursuant to Reference 3. The Integrated Plan is based on conceptual design information. Final design details and associated procedure guidance, as well as any revisions to the information contained in Enclosure 1, will be provided in the 6-month Integrated Plan updates required by Reference 1.
Susquehanna's Hardened Containment Vent System Order EA-12-050 response will need to be revised if the NRC decides to impose any additional requirements like those described in SECY-12-0157, Options 2, 3, or 4, on Susquehanna,. The design information, milestones, and schedule dates for the compliance with Order EA-12-050 will need to be revised. Compliance with the existing Hardened Containment Vent System Order EA-12-050 deadlines will likely not be possible. Delays in implementing the Hardened Containment Vent System will also affect implementation of the Mitigation Strategies Order EA-12-049 actions. The SECY-12-0157 Options are titled: 1) Option 1:
Reliable Hardened Vents (Status Quo or Base Case); 2) Option 2: Severe Accident Capable Venting System Order (without Filter); 3) Option 3: Filtered Severe Accident Venting System Order; and, 4) Option 4: Severe Accident Confinement Strategies.
If you have any questions regarding this submittal, please contact Mr. John L. Tripoli, Manager, Nuclear Regulatory Mfairs, at (570) 542-3100.
This letter does not contain any new or revised regulatory commitments. The information contained in this submittal is based on conceptual level design information.
The final design process will determine actual details such as - connection points, pipe routing, specific components, and electrical and pneumatic sizing and routing.
PPL requests that Enclosure 1 to this letter be withheld from public disclosure. The information represents Security-Related information as defined by 10 CFR 2.390.
Document Control Desk PLA-6981 I declare under penalty of perjury that the foregoing is true and correct.
Executed on __
%]=*
'~--': 2/)=,L-___, 2013.
Enclosure:
- 1) Overall Integrated Plan for Mitigation Strategies for Beyond Design Bases External Events -Withhold From Public Disclosure in Accordance with 10 CFR 2.390 Copy: Mr. P. W. Finney, NRC Sr. Resident Inspector Mr. J. A. Whited, NRC Project Manager Mr. L. J. Winker, PA DEP/BRP Region I Administrator, NRC to PLA-6981 Overall Integrated Plan for Mitigation Strategies for Beyond Design Bases External Events