Davis-BesseNPEm Resource From: CuadradoDeJesus, Samuel Sent: Wednesday, January 16, 2013 3:14 PM To: custerc@firstenergycorp.com; dorts@firstenergycorp.com Cc: Davis-BesseHearingFile Resource

Subject:

Draft Teleconference Summary 10 23 2012 Attachments: 10 23 2012 DB NRC Telecon Summary.docx Importance: High Cliff and Steve, Attached is the draft summary of our 10/23/2012 teleconference. Please let me know if you have any comment.

Regards, Samuel Cuadrado de Jesús Project Manager Projects Branch 1 Division of License Renewal U.S. Nuclear Regulatory Commission Phone: 301-415-2946 Samuel.CuadradoDeJesus@nrc.gov 1

Hearing Identifier: Davis_BesseLicenseRenewal_Saf_NonPublic Email Number: 4017 Mail Envelope Properties (377CB97DD54F0F4FAAC7E9FD88BCA6D0B9F26CEBC7)

Subject:

Draft Teleconference Summary 10 23 2012 Sent Date: 1/16/2013 3:14:25 PM Received Date: 1/16/2013 3:14:27 PM From: CuadradoDeJesus, Samuel Created By: Samuel.CuadradoDeJesus@nrc.gov Recipients:

"Davis-BesseHearingFile Resource" <Davis-BesseHearingFile.Resource@nrc.gov>

Tracking Status: None "custerc@firstenergycorp.com" <custerc@firstenergycorp.com>

Tracking Status: None "dorts@firstenergycorp.com" <dorts@firstenergycorp.com>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 400 1/16/2013 3:14:27 PM 10 23 2012 DB NRC Telecon Summary.docx 29711 Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON OCTOBER 23, 2012 BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE DAVIS-BESSE NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION (TAC. NO. ME4640)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC or the applicant) held a telephone conference call on October 23, 2012, to discuss and clarify the applicants responses to the staffs requests for additional information (RAIs) concerning the Davis-Besse license renewal application. provides a listing of the participants and Enclosure 2 contains a description of the staff concerns discussed with the applicant. A brief description on the status of the items is also included.

The applicant had an opportunity to comment on this summary.

Samuel Cuadrado de Jesús, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Number:50-346

Enclosures:

1. List of Participants
2. List of Requests for Additional Information cc w/encls: See next page

DOCUMENT NAME: Insert document name and full path.

OFFICE LA:DLR PM:RPB1:DLR BC:RPB1:DLR NAME S Cuadrado de D Morey Jesús DATE / / / / / /

SUMMARY

OF TELEPHONE CONFERENCE CALL DAVIS-BESSE LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS October 23, 2012 PARTICIPANTS AFFILIATIONS Samuel Cuadrado de Jesús U.S. Nuclear Regulatory Commission (NRC)

Chris Sydnor NRC Allen Hiser NRC Steven Dort FirstEnergy Nuclear Operating Company (FENOC)

Larry Hinkle FENOC Dennis Blakely FENOC Mark Rinckel AREVA ENCLOSURE 1

SUMMARY

OF TELEPHONE CONFERENCE CALL DAVIS-BESSE LICENSE RENEWAL APPLICATION October 23, 2012 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC or the applicant) held a telephone conference call on October 23, 2012, to discuss and clarify the following response to requests for additional information (RAIs) concerning the Davis-Besse license renewal application (LRA).

Response to RAI 4.2.4-1: Pressure-Temperature (P-T) Limits Discussion: The purpose of the call was to discuss the applicants response to the staff request for additional information (RAI) 4.2.4-1 submitted by FENOC letter dated August 24, 2012.

The staff stated that it could not find information in the applicants response that addressed how future P-T limit curves would be developed for the period of extended operation taking into account the neutron embrittlement effects on the extended beltline region and the localized stresses of the inlet and outlet nozzles. The staff also stated that this information needs to be provided in LRA Sections 4.2.4 and A.2.2.4 (USAR Supplement).

The applicant stated that the Davis-Besse P-T limit curves are currently limited to 32 effective full power years, and that additional analysis is required to extend the curves in the future.

The applicant also stated that in order to provide clarification and address the staffs concern it will submit a supplemental response to RAI 4.2.4-1 and as part of the supplemental response it will incorporate the clarification into LRA Sections 4.2.4 and A.2.2.4, both titled Pressure-Temperature Limits. The staff agreed with the applicant determination of providing a supplemental response to RAI 4.2.4-1.

Action: The applicant will provide a supplemental response to RAI 4.2.4-1

SUBJECT:

Summary of Telephone Conference Call conducted on October 23, 2012 ENCLOSURE 2