Dominion Nuclear Connecticut, Inc.

5000 Dominion Boulevard, Glen Allen, VA 23060 Web Address: www.dom.com January 23, 2013 Dominion U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 DOMINION NUCLEAR CONNECTICUT, INC.

MILLSTONE POWER STATION UNITS 2 AND 3 NOTIFICATION OF CHANGE FROM 1998 TO 2009 ANSI/ANS 3.5 NUCLEAR POWER PLANT SIMULATORS FOR USE IN OPERATOR TRAINING AND EXAMINATION Serial No.

MPS Lic/LES Docket Nos.

License Nos.12-761 RO 50-336 50-423 DPR-65 NPF-49 In letters dated June 30, 1997, and October 16, 1998, Northeast Nuclear Energy Company (NNECO) documented compliance with ANSI/ANS 3.5-1985, Nuclear Plant Simulators for Use in Operator Training and Examination, for the simulators at Millstone Power Station Units 2 and 3 (MPS2 and MPS3).

Subsequently, by letter dated November 3, 2000 (Serial No. B18256), NNECO advised the NRC that the use of this standard was changed to comply with the 1998 version for both MPS2 and MPS3. The purpose of this letter is to advise the NRC that Dominion Nuclear Connecticut, Inc.

(DNC) is revising its use of this standard to comply with the 2009 edition of ANSI/ANS 3.5 for both MPS2 and MPS3 simulators.

If you have any questions concerning this material, please contact Mr. William D.

Bartron at (860) 440-4301.

Sincerely,

~-

L. N. Hartz

.~ Li-Jd"-i-7'J-Vice President - Nuclear Support Services Commitment made in this letter: None

cc:

U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission Region I 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 J. S. Kim NRC Project Manager U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08-C2A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station Serial No.12-761 Docket Nos. 50-336/423 Page 2 of 2