Lr Hearing - Draft Telecon Notes for Conference Call on January 7, 2013
ML13010A218
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 01/10/2013
From:
Office of Nuclear Reactor Regulation
To:
Division of License Renewal
References
Download: ML13010A218 (3)


Text

IPRenewal NPEmails From: Daily, John Sent: Thursday, January 10, 2013 10:19 AM To: Waters, Roger M.

Cc: IPRenewal NPEmails

Subject:

Draft Telecon notes for conference call on January 7, 2013

Roger, Please review the following draft summary of telecon for our conference call of January 7, 2013, on RAI 15a, and provide comments back by Monday COB, if thats possible.

Thanks.

John Daily Senior Project Manager, Division of License Renewal Office of Nuclear Reactor Regulation USNRC John.Daily@NRC.Gov (301) 415-3873 REQUEST FOR ADDITIONAL INFORMATION CONFERENCE CALL INDIAN POINT ENERGY CENTER, UNITS 2 AND 3 LICENSE RENEWAL APPLICATION REACTOR VESSEL INTERNALS PROGRAM AND MRP-227-A RAI 15a January 7, 2013 The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of Entergy Nuclear Operations, Inc.

(Entergy or the applicant) held a telephone conference call on January 7, 2013, to discuss staff aging management questions related to the applicants Reactor Vessel Internals Aging Management Program, in the Indian Point Energy Center (IPEC), Units 2 and 3, license renewal application (LRA). The telephone conference call was useful in clarifying the requests for additional information (RAIs) on the issue.

RAI-15a Fatigue-induced Cracking for RVI Components - Followup The staff noted that the applicants revised response to RAI 12 indicates that it intends to use the Reactor Vessel Internals (RVI) Program to manage the cracking-fatigue aging effect for RVI components that have a time-limited aging analysis (TLAA) which determines a cumulative usage factor (CUF).

The staff had questions regarding the following:

  • Most of the applicants RVI components that have an associated fatigue TLAA are not Primary inspection category components under the RVI Program, thus they may be subject to no inspection other than a VT-3 visual examination under the ASME Section XI, Inservice Inspection Program, since Expansion category component inspections are only triggered in the event of degradation of the linked Primary inspection category component(s).
  • The applicant did not justify the adequacy of the periodicity of RVI Program inspections performed on RVI components that have a fatigue TLAA.
  • Components that are not in the Primary, Expansion, or Existing Programs categories of MRP-227-A fall into its No Additional Measures category, for which all aging mechanisms are below the screening criteria, therefore no examination techniques, periodicity, coverage, or acceptance criteria are specified for these components in MRP-227-A.

The staff and Entergy discussed these issues and agreed to clarify the RAI in that it is not intended to re-visit components having a TLAA for CUF and that are classified as Primary, Expansion, or Existing componentsfor those components the staff agreed that the inspection techniques as recommended in MRP-227-A are sufficient. The applicant would still, 1

however, need to justify the inspection periodicity for the components, since a default 10-year reinspection frequency may not be adequate for a CUF (inclusive of environmental effects) that is greater than 1.0 at some point in the period of extended operation.

In addition, the staff and Entergy agreed that the reply window for this RAI would be 90 days from date of issue. The staff indicated its intent to issue this RAI in conjunction with RAI 11a.

The applicant agreed that it would take the staff's questions into account as it prepares its response to RAI 15a. Both the staff and the applicant agreed that the discussion was useful in clarifying the RAI.

LIST OF PARTICIPANTS January 7, 2013 PARTICIPANT AFFILIATION John Daily Nuclear Regulatory Commission (NRC)

Jeff Poehler NRC Ching Ng NRC On Yee NRC Roger Waters Entergy Nelson Azevedo Entergy Ted Ivy Entergy Alan Cox Entergy Bob Dolansky Entergy Charles Caputo Entergy John Curry Entergy Randy Lott Westinghouse David Roarty Westinghouse Sallie Carrera Westinghouse 2

Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 4020 Mail Envelope Properties (0046140293E11F408991442DB4FE25CA9F43576E41)

Subject:

Draft Telecon notes for conference call on January 7, 2013 Sent Date: 1/10/2013 10:18:54 AM Received Date: 1/10/2013 10:18:58 AM From: Daily, John Created By: John.Daily@nrc.gov Recipients:

"IPRenewal NPEmails" <IPRenewal.NPEmails@nrc.gov>

Tracking Status: None "Waters, Roger M." <rwater1@entergy.com>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 3896 1/10/2013 10:18:58 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: