ATTACHMENT 3 WALKDOWN CHECKLISTS Status: F]N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2COMPSWAC22B Equipment Class: (12) Air Compressors Equipment
Description:
22 SW AIR COMP B Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 5.00 ft, CAL-AB-205 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% Yes of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Yes This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage is consistent with drawing 61962 Sht. 2.
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
67
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [Y N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2COMPSWAC22B Equipment Class: (12) Air Compressors Equipment
Description:
22 SWAIR COMP B Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments A1 / -
Evaluated by: ,1/ ~ A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 68
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2COMPSWAC22B Equipment Class: (12) Air Compressors Fauinment Deqcrintion: 22 SW AIR COMP R 2COMPSWAC22B 8-6-12 258 69
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2COMPSWAC22B Equipment Class: (12) Air Compressors oiment Descriotion: 22 SW AIR COMP B 70
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2COMPSWAC22B Equipment Class: (12) Air Compressors ioment Descnotion: 22 SW AIR COMP B 71
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y- N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1581 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 CAC NORM INLET Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 27.00 ft, CAL-AB-310 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
72
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1581 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 CAC NORM INLET Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing in pipe's transverse direction may not have sufficient flexibility, need to look at piping ISO. Equivalent to 15" long 1/2" tube.
10/13/12 - Per Drawing 91575 the piping is supported approximately3.5 feet away from the valve. Hence the valve displacement is judged to be small enough not to affect the tubing and the tubing's flexibility is adequate.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 73
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1581 Equipment Class: (7) Fluid-(Operated Valves F:nhinmAnt "o.*rintinn" 71 CAr. h%(lPRMINI FT 74
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: MI N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1581 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 CAC NORM INLET 75
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV15880P Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
2A DG SRW SUPP VLV OP Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 45.00 ft, CAL-AB-422 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
76
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV15880P Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
2A DG SRW SUPP VLV OP Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes Masonry block walls, identified as A 19 and A24 on drawing A-259, are safety-relatedand thus seismically ratedper IE Bulletin 80-11.
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
Overheadlight, if not 2/1, may fall and strike operatortubing.
10/3/12 - Overhead lights were deemed not a credible seismic concern due to their lightweight and to typical construction practices. Also, they have been previously evaluated by CCNPPand found seismically acceptable.
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments
/1 / -
Evaluated by: // /Aý A. Karavoussianis Date: 11/09/2012
~zT C. Figliolini 11/09/2012 Photos 77
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV15880P Equipment Class: (7) Fluid-Operated Valves 2A DG SRW SUPP VLV OP 78
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1637 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
TB SRW HDR 21 ISOL Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 5.00 ft, CAL-AB-205 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies ifthe item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
79
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [-Y] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1637 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
TB SRW HDR 21 ISOL Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing between two valves (1637 and 1638) is supportedat center by a stanchion anchored to the ceiling. The valves are on a common pipe running to HXs that are supported on floor. Differential motion between floor and ceiling is judged to be small and will not affect tubing. Tubing is judged to have adequate flexibility.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments I,
Evaluated by: A. Karavoussianis Date: 11/09/2012
~zT C. Figliolini 11/09/2012 Photos 80
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1 637 Equipment Class: (7) Fluid-Operated Valves Enuinment Descrintion: TR RRW HDR 21 ISOL 81
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1637 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
TB SRW HDR 21 ISOL PW mwm-- ZJ00 82
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1637 Equipment Class: (7) Fluid-Operated Valves inment
Description:
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV1637 Equipment Class: (7) Fluid-Operated Valves 84
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 MSIV Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 27.00 ft, CAL-AB-309 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoraae
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
85
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 MSIV Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
Ductwork support is 1/2" from valve, ductwork is also laterally supportedon other side (nearby)therefore judged not to be a seismic concern.
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Hydraulic line insulationis in contact with hand rail. Line has adequate flexibility, therefore it is judged not to be a seismic concern.
Flex conduit is in contact with platform and the conduit's JB is supported on platform, therefore it is judged not to be a seismic concern.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 86
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-Operated Valves Iniinmont F)as-trintinn" 71 MRIV 87
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [--] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-( )perated Valves Fniiinmnt nmarrintinn" 21 MRIV 88
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-Operated Valves F:uioment Descrintion: 21 MSIV 89
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-Operated Valves Fnjuinment DAqrintinn" 21 MRIV 90
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4048 Equipment Class: (7) Fluid-Operated Valves 21 Equipment
Description:
21 MVSIV 2CV4048 8-9-12 038 2CV4048 8-9-12 039 91
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
S/G 21 MS WITH HS IN AUTO TURB Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 27.00 ft, CAL-AB-309 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
Tubing support approximately5' from valve Valve Y2" from steel pipe well supported in subject direction Floorcrack, dentedjacket on floorpiping 92
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
S/G 21 MS WITH HS IN AUTO TURB Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes There is a Y2" gap between the valve and nearby steel, the pipe is adequately supportedin the subject direction,judged not to be a seismic hazard.
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing is supported5' from valve and is judged to have adequate flexibility.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 93
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070 Equipment Class: (7) Fluid-Operated Valves Fnuinm~nt DPrrintion: R/r 21 MR WITH Hq IN AtITO THJRR 94
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: F] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070 Equipment Class: (7) Fluid-Operated Valves oment Descrintion: SIG 21 MS WITH HS IN AUTO TURR 95
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Mi-- N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070 Equipment Class: (7) Fluid-Operated Valves Enuinment DPcrrntion" R/r 21 MS WITH HS IN AIITC" TIIRR 96
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M-I N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070 Equipment Class: (7) Fluid-Operated Valves Fni iinmant rlaarrintinn' 5/(KZ 91 MR-WIT I-IWR IN Al ITr) TI IRR 97
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: MI N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070A Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
MS 2-CV-4070 BYPASS CV Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 27.00 ft, CAL-AB-309 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
98
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: F] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070A Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
MS 2-CV-4070 BYPASS CV Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Valve and piping are well supportednear to each other.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: /ý '4ýý ý' A. Karavoussianis Date: 11/09/2012
~I7 C. Figliolini 11/09/2012 Photos 99
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070A Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
MS 2-CV-4070 BYPASS CV 100
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M-I N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070A Equipment Class: (7) Fluid-Operated Valves Fauinment Descrintion: MS 2-CV-4070 BYPASS CV 101
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070A Equipment Class: (7) Fluid-Operated Valves EauiDment
Description:
MS 2-CV-4070 BYPASS CV 102
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [T N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070A Equipment Class: (7) Fluid-Operated Valves Fuinmpnt DAcdrintinn- MS 2-CV-4070 RYPASS CV 103
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070AOP Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
MS 2-CV-4070A VALVE OPERA Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 27.00 ft, CAL-AB-309 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
This is the operatorfor valve 2CV4070A.
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
104
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070AOP Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
MS 2-CV-4070A VALVE OPERA Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Valve and piping are well supportednear each other.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Comments Evaluated by: '9,AV~ %24A 4 A. Karavoussianis Date: 11/09/2012 7 C. Figliolini 11/09/2012 Photos 105
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV4070AOP Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
MS 2-CV-4070A VALVE OPERA Rule of Box 2CV4070AOP ROB 106
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV40700P Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 MS SUPP STM TO AFW TUR Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 27.00 ft, CAL-AB-309 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
This is the operatorfor valve 2CV4070.
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
Tubing support approximately5' from valve Valve Y2" from steel pipe well supportedin subject direction Floorcrack, dented jacket on floor piping 107
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV40700P Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 MS SUPP STM TO AFW TUR Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes There is a Y" gap between the valve and nearby steel, the pipe is adequately supportedin the subject direction, o.k.
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing is supported 5" from valve and is judged to have adequateflexibility.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: A. Karavoussianis Date: 11/09/2012
~zT C. Figliolini 11/09/2012 Photos 108
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV40700P Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
21 MS SUPP STM TO AFW TUR Rule of Box 2CV40700P ROB 109
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV5149OP Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
2 EMER SW DISCH TO BAY CV ACT Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): Intake, -7.00 ft, CAL-ISPR-INT2 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
110
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV51490P Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
2 EMER SW DISCH TO BAY CV ACT Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes The valve and operatorare approximately Y1/4" from platform steel. The platform steel is well braced, and the very large diameterpiping is anchored within approximately 30' from valve on each side. Therefore the differential motion between the platform and valve is judged not to exceed X". Judged to be seismic adequate.
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: /ý A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 111
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M-* N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV51490P Equipment Class: (7) Fluid-Ope rated Valves Equipment
Description:
2 EMER SW rlI5-CJ-I Tr) RAY M/~ AC.T 112
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV51490P Equipment Class: (7) Fluid-Operated Valves Fnhinmnnt Dflqnrintinn" 9 FMFR 5W rlI5RrH TO RAY rV ACT 113
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV51490P Equipment Class: (7) Fluid-Operated Valves FnhiinmAnt Ip)rcrintinn" 7 FMFR RW l)I.RrH TCO RAY (V ACT 114
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV5173 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
ECCS PP RM AIR CLR 22 WTR IN Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 5.00 ft, CAL-AB-201 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoraqe
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
115
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: T N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV5173 Equipment Class: (7) Fluid-Operated Valves Equipment
Description:
ECCS PP RM AIR CLR 22 WTR IN Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing supportedon wall near the valve's pipe supports, therefore small differential motion is expected and the tubing judged to have adequate flexibility.
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: /7" - A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 116
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV5173 Equipment Class: (7) Fluid-Operated Valves Initinmant fnac-rinfinn" ICr.C.. OP PU AID r(I P '9 XAWTP IN 117
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV5173 Equipment Class: (7) Fluid-C)perated Valves Equipment
Description:
ECCS PP PM AIR ('I P 99 VFJTP KIN 118
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: MI N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2CV5173 Equipment Class: (7) Fluid-Operated Valves ECCS PP RM AIR CLR 22 WTR IN 119
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r-* N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DAMP5426B Equipment Class: (10) Air Handlers Equipment
Description:
21 U RECIRC AIR DMPR Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 70.00 ft, CAL-AB-526 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
Damperis inline with 21SWGRHVAC.
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
120
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [-1 N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DAMP5426B Equipment Class: (10) Air Handlers Equipment
Description:
21 U RECIRC AIR DMPR Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes 8, Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
9, Do attached lines have adequate flexibility to avoid damage? Yes 10, Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions 11, Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Com~ments Comments Evaluated by: /ý "14ýýý- A. Karavoussianis Date: 11/09/2012
~z7 C. Figliolini 11/09/2012 Photos 121
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: MZ N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DAMP5426B Equipment Class: (10) Air Handlers ioment Descriotion: 21 U RECIRC AIR DMPR 122
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y K U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DISC189-2103A Equipment Class: (14) Distribution Panels Equipment
Description:
2A DG TO DISC SW 2NA103 Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 45.00 ft, CAL-AB-422 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% Yes of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Yes This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Walkdown anchorageas-built sketch is consistent with calculation CA01632.
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
123
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y j-W U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DISC189-2103A Equipment Class: (14) Distribution Panels Equipment
Description:
2A DG TO DISC SW 2NA103 Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could No adversely affect the safety functions of the equipment?
Cabinet is inaccessiblefor internalinspection.
Comments Evaluated by: A. Karavoussianis Date: 11/09/2012
~z7 C. Figliolini 11/09/2012 Photos 124
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: YFE U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DISC189-2103A Equipment Class: (14) Distribution Panels Eauioment Descnotion: 2A DG TO DISC SW 2N 125
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y W U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DISC189-2103A Equipment Class: (14) Distribution Panels F-n.inm.nt fnlPerintinn" A'nr. TO I')nI. 5RW 2NA1 O, A
126
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y L-N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DISC189-2103A Equipment Class: (14) Distribution Panels Fnijinmant rlaqrintinn- 9A rfl T* lr1.*I Rw 2 NAInf 2DISC189-2103A 8-13-12 208 2DISC189-2103A 8-13-12 207 127
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y W U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2DISC189-2103A Equipment Class: (14) Distribution Panels Equipment
Description:
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: I- N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2ENGEDG2B Equipment Class: (17) Engine-Generators Equipment
Description:
DIESEL GENERATOR 2B ENGINE Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 45.00 ft, CAL-AB-416 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% Yes of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes Minor grout crack but not close to bolts, judged not to be a seismic concern.
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Yes This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Anchorage is consistent with drawings 36988 (C-490).
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
129
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2ENGEDG2B Equipment Class: (17) Engine-Generators Equipment
Description:
DIESEL GENERATOR 2B ENGINE Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and No masonry block walls not likely to collapse onto the equipment?
There is tubing and a sight glass that are within the path of influence of overhead lights.
10/3/12 - Overheadlights were deemed not a credible seismic concern due to their lightweight and typical construction practices. Also, they have been previously evaluated by CCNPPand found seismically acceptable.
Unit 2G2B is mounted on vibration isolators,need to investigate the seismic adequacy of this unit's anchorage.CR-2012-010381 written to address this issue.
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Com~ments Evaluated by: A. Karavoussianis Date: 11/09/2012 130
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r-Y N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2ENGEDG2B Equipment Class: (17) Engine-Generators Equipment
Description:
DIESEL GENERATOR 2B ENGINE C. Figliolini 11/09/2012 Photos 131
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [V N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2ENGEDG2B Equipment Class: (17) Engine-Generators Fauinment Desrcrintionn DIESFL *.FNERATOR 2R FNr.INE 132
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2ENGEDG2B Equipment Class: (17) Engine-Generators inment Descrintion: DIESEL GENERATOR 2ENGEDG2B 8-13-12 050 133
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2ENGEDG2B Equipment Class: (17) Engine-Generators Equipment
Description:
DIESEL GENERATOR 2B ENGINE 2ENGEDG2B 8-13-12 051 134
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FAN0448A Equipment Class: (9) Fans Equipment
Description:
ECCS PP RM CLR 22 FAN A Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, -15.00 ft, CAL-AB-102 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
135
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FAN0448A Equipment Class: (9) Fans Equipment
Description:
ECCS PP RM CLR 22 FAN A Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Comments Evaluated by: A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 136
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FAN0448A Equipment Class: (9) Fans Dment DescriDtion: ECCS PP RM CLR 137
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: MY- N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FAN0448A Equipment Class: (9) Fans Equipment
Description:
ECCS PP RM CLR 22 FAN A 2FAN0448A 8-7-12 263 2FAN0448A 8-7-12 264 138
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FAN0448A Equipment Class: (9) Fans Fnuinmpnt Dpmrrintinn" FCCR PP PM rl P 99 FAN A ZI-AINU440A O-I'-IZ ZfU 139
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACEDGS2A Equipment Class: (9) Fans Equipment
Description:
2A DG RM SPLY FAN Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 45.00 ft, CAL-AB-422 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchoracqe
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
140
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACEDGS2A Equipment Class: (9) Fans Equipment
Description:
2A DG RM SPLY FAN Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by:
4~2~ A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 141
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACEDGS2A Equipment Class: (9) Fans jinmant )acrrintinn- A rlnr PM 5qPI V FAN 2FANHVACEDGS2A 8-13-12 213 142
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: T N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACEDGS2A Equipment Class: (9) Fans Enuinm~nt DPqnrtinn" 2A Dr RM .PLY FAN 143
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACPENETE21 Equipment Class: (9) Fans Equipment
Description:
21 PENET RM EXH FAN Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 5.00 ft, CAL-AB-204 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes Fan is on vibration isolator(springs). Isolatoris judged not to be a seismic concern.
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
144
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACPENETE21 Equipment Class: (9) Fans Equipment
Description:
21 PENET RM EXH FAN Interaction Effects
- 7. Are soft targets free from impact bynearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by:
,94~2&~ A. Karavoussianis Date: 11/09/2012
~zT C. Figliolini 11/09/2012 Photos 145
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M-I N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACPENETE21 Equipment Class: (9) Fans Inhinmant I'l*_nrinfinn" 91 PFNFT PM I::I- FAN 9FANW~JACPFMFTF91 P.~7.A 146
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACPENETE21 Equipment Class: (9) Fans
- nuimnmant IflAr.rnfirn. 91 DIMI=T ORA IYW 'AM 147
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: Y] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACSWGRS21 Equipment Class: (9) Fans Equipment
Description:
21 SWGR RM SPLY FAN Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 70.00 ft, CAL-AB-526 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% No of SWEL items requiring such verification)?
Fan is part of and mounted on 21SWGRHVAC.
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Not Applicable
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Not Applicable
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Not Applicable
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Not Applicable This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
148
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACSWGRS21 Equipment Class: (9) Fans Equipment
Description:
21 SWGR RM SPLY FAN Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Comments Evaluated by: A. Karavoussianis Date: 11/09/2012
~I7 C. Figliolini 11/09/2012 Photos 149
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACSWGRS21 Equipment Class: (9) Fans inmAnt nqrnrintinn" 91 qWrR PM RPI Y FAN 150
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: F N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACSWGRS21 Equipment Class: (9) Fans Fniiinmant l'marintinn. i 11 Wr. P RPI V FAN 151
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: MY N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FANHVACSWGRS21 Equipment Class: (9) Fans ipment
Description:
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT321 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Equipment
Description:
HPSI FLOW TO LOOP 22B Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 5.00 ft, CAL-AB-203 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% Yes of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Yes This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Walkdown as-built anchoragesketch is consistent with drawings 66300SH0002 and 91007 (J-106).
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
153
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: r] N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT321 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Equipment
Description:
HPSI FLOW TO LOOP 22B Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing is supported on the FT C6 stanchionand wall with adequate flexibility.
Not a seismic concern.
- 10. Based.on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Evaluated by: A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 154
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT321 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Enuinment Depcrintion: HPSI FLOW TO LOOP 22R 155
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT321 Equipment Class: (20) Instrumentation and Control Panels and Cabinets FnifinmAnt rtanrintinn" HPRI FI OW TO I OOP 'R 156
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: W N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Equipment
Description:
LPSI FLOW TO LOOP 22B Project: CCNPP 2 SWEL Location (Bldg, Elev, Room/Area): AUX, 5.00 ft, CAL-AB-203 Manufacturer/Model:
Instructions for Completing Checklist This checklist may be used to document the results of the Seismic Walkdown of an item of equipment on the SWEL. The space below each of the following questions may be used to record the results of judgments and findings. Additional space is provided at the end of this checklist for documenting other comments.
Anchorage
- 1. Is anchorage configuration verification required (i.e., is the item one of the 50% Yes of SWEL items requiring such verification)?
- 2. Is the anchorage free of bent, broken, missing or loose hardware? Yes
- 3. Is the anchorage free of corrosion that is more than mild surface oxidation? Yes
- 4. Is the anchorage free of visible cracks in the concrete near the anchors? Yes
- 5. Is the anchorage configuration consistent with plant documentation? (Note: Yes This question only applies if the item is one of the 50% for which an anchorage configuration verification is required.)
Walkdown as-built anchoragesketch is consistent with drawing 91007 (J-106).
- 6. Based on the above anchorage evaluations, is the anchorage free of Yes potentially adverse seismic conditions?
157
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Equipment
Description:
LPSI FLOW TO LOOP 22B Interaction Effects
- 7. Are soft targets free from impact by nearby equipment or structures? Yes
- 8. Are overhead equipment, distribution systems, ceiling tiles and lighting, and Yes masonry block walls not likely to collapse onto the equipment?
- 9. Do attached lines have adequate flexibility to avoid damage? Yes Tubing is supported on C6 stanchions and concrete wall, tubing has adequate flexibility. Not a seismic concern
- 10. Based on the above seismic interaction evaluations, is equipment free of Yes potentially adverse seismic interaction effects?
Other Adverse Conditions
- 11. Have you looked for and found no adverse seismic conditions that could Yes adversely affect the safety functions of the equipment?
Comments Switched from 2FT332, which was inaccessible.
Evaluated by: A. Karavoussianis Date: 11/09/2012 C. Figliolini 11/09/2012 Photos 158
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Fniiinmanf "larinfinn- I P1l A=1(1W TA I A'P DR 159
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets niflinmant l*amrrintinn" I PQI Pl f(W T(C I A"%P 99R 160
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: [ N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Enuinment Dcqrintion: LPSI FLOW TO LOOP 22R 161
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Equipment
Description:
LPSI FLOW TO LOOP 22B 2FT322 8-6-12 137 162
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets 1n=imnmjmnt fl)@nrniinn I P.QI P1 AM TA I A'ArP 'XJR 163
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets Fnifinmant r'arnrintinn" I P5I :I 3W T* I Ar"P 9R 164
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: M N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instrumentation and Control Panels and Cabinets ninmant fl'a_.trintinn-
- ni I PI F: W T( I 1OOP 99R 165
ATTACHMENT 3 WALKDOWN CHECKLISTS Status: F-7 N U Seismic Walkdown Checklist (SWC)
Equipment ID No.: 2FT322 Equipment Class: (20) Instirumentation and Control Panels and Cabinets Pi:r rmi nt ranf M -rintfinn" I DPQI I:1 MIW Tn I AArP "P 166