United States Nuclear Regulatory Commission Official Hearing Exhibit NYS000094 Entergy Nuclear Operations, Inc. Submitted: December 14, 2011 In the Matter of:
(Indian Point Nuclear Generating Units 2 and 3) c.\.~P.R REGlJ~" ASLBP #: 07-858-03-LR-BD01 P~~"
Docket #: 05000247 l 05000286 Exhibit #: NYS000094-00-BD01 Identified: 10/15/2012 I-
~ -'
~
0'!:
r;;
Admitted: 10/15/2012 Withdrawn:
~4: O~ Rejected: Stricken:
" ** ** ... ... Other:
75 Riverside Avenue P.O. Box 350 Rensselaer, NY 12144 Empire Generating Project Timeline As of May 19, 2010 November 2009:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- Complete enclosure of the turbine building
- Continue piping, electrical power and control wiring
- Start Heat Recovery Steam Generator (HRSG) stack erection
- Initial system checkouts and turnovers for plant support systems December 2009:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- Complete gray water tie at Albany County Sewer District (ACSD) plant
- Start commissioning of water treatment systems
- Continue critical pipe and process pipe installation
- Begin back feed of power to portions of the power block
- Continue electrical and power wiring
- Continue HRSG stack erection
- Complete tie in of the gas line from the Tennessee Gas main line January 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee OAGI0001299_00001
- Citizens Committee held
- Direct newsletter mailed to targeted communities and stakeholders
- Copy of newsletter posted on Website
- Completion of majority of critical pipe and process piping
- Continue electrical power and control wiring
- Electrical control wiring checkout
- Check out and commissioning of the gas supply systems
- Hydro Test HRSGs
- Complete commissioning of the water treatment equipment February 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- Begin complete control and instrument checks and calibrations
- Commission primary HRSG and Gas Turbine support systems
- Perform control loop checks on all major systems
- Start preparing boiler piping for steam blows March 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee April 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- Citizens Committee held
- Direct newsletter mailed to targeted communities and stakeholders
- Copy of newsletter posted on Website
- Continue sub system checkout and commissioning May 2010:
OAGI0001299_00002
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- Continue sub system checkout and commissioning
- Tune water treatment systems to make boiler quality make up water
- First fire on Combustion Turbine (CT) # 11
- Continue ancillary equipment check out and commissioning
- Synchronize CTG # 11 to power grid
- Perform initial control testing June 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- First fire CT # 12 and repeat checkout process and generator synchronization before the end of the month
- Complete HRSG #11 and #12 and combined steam blows
- Restore steam piping systems after steam blows July 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee
- Citizens Committee held
- Direct newsletter mailed to targeted communities and stakeholders
- Copy of newsletter posted on Website
- Restore steam piping systems after steam blows
- Perform controls and emissions tuning on the Combustion Turbine Generator (CTG) 11 and 12
- Install emission control catalyst in HRSG 11 and 12 AU2ust 2010:
- Rensselaer office hours held
- Complaint log distributed to Citizens Committee OAGI0001299_00003
- Load testing on CTG 11 and 12
- Tune ammonia control and injection systems
- U nit run for steam quality
- Initial roll up and synchronization of the steam turbine
- Duct burner firing testing and tuning
- Perform Continuous Emissions Monitoring System (CEMS) testing and certification
- On line emission tuning September 2010:
- Plant in Commercial Operation OAGI0001299_00004