Official Exhibit - NYS000094-00-BD01 - Empire Generating Co., LLC, Project Timeline as of May 19, 2010 (2010 Empire Project Timeline)
ML12334A515
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 12/14/2011
From:
Empire Generating Co
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
RAS 21536, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01
Download: ML12334A515 (4)


Text

United States Nuclear Regulatory Commission Official Hearing Exhibit NYS000094 Entergy Nuclear Operations, Inc. Submitted: December 14, 2011 In the Matter of:

(Indian Point Nuclear Generating Units 2 and 3) c.\.~P.R REGlJ~" ASLBP #: 07-858-03-LR-BD01 P~~"

Docket #: 05000247 l 05000286 Exhibit #: NYS000094-00-BD01 Identified: 10/15/2012 I-

~ -'

~

0'!:

r;;

Admitted: 10/15/2012 Withdrawn:

~4: O~ Rejected: Stricken:

" ** ** ... ... Other:

75 Riverside Avenue P.O. Box 350 Rensselaer, NY 12144 Empire Generating Project Timeline As of May 19, 2010 November 2009:

  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • Complete enclosure of the turbine building
  • Continue piping, electrical power and control wiring
  • Initial system checkouts and turnovers for plant support systems December 2009:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • Complete gray water tie at Albany County Sewer District (ACSD) plant
  • Start commissioning of water treatment systems
  • Continue critical pipe and process pipe installation
  • Begin back feed of power to portions of the power block
  • Continue electrical and power wiring
  • Continue HRSG stack erection
  • Complete tie in of the gas line from the Tennessee Gas main line January 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee OAGI0001299_00001
  • Citizens Committee held
  • Direct newsletter mailed to targeted communities and stakeholders
  • Copy of newsletter posted on Website
  • Completion of majority of critical pipe and process piping
  • Continue electrical power and control wiring
  • Electrical control wiring checkout
  • Check out and commissioning of the gas supply systems
  • Hydro Test HRSGs
  • Complete commissioning of the water treatment equipment February 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • Begin complete control and instrument checks and calibrations
  • Commission primary HRSG and Gas Turbine support systems
  • Perform control loop checks on all major systems
  • Start preparing boiler piping for steam blows March 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee April 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • Citizens Committee held
  • Direct newsletter mailed to targeted communities and stakeholders
  • Copy of newsletter posted on Website
  • Continue sub system checkout and commissioning May 2010:

OAGI0001299_00002

  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • Continue sub system checkout and commissioning
  • Tune water treatment systems to make boiler quality make up water
  • First fire on Combustion Turbine (CT) # 11
  • Continue ancillary equipment check out and commissioning
  • Synchronize CTG # 11 to power grid
  • Perform initial control testing June 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • First fire CT # 12 and repeat checkout process and generator synchronization before the end of the month
  • Complete HRSG #11 and #12 and combined steam blows
  • Restore steam piping systems after steam blows July 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee
  • Citizens Committee held
  • Direct newsletter mailed to targeted communities and stakeholders
  • Copy of newsletter posted on Website
  • Restore steam piping systems after steam blows
  • Perform controls and emissions tuning on the Combustion Turbine Generator (CTG) 11 and 12
  • Install emission control catalyst in HRSG 11 and 12 AU2ust 2010:
  • Rensselaer office hours held
  • Complaint log distributed to Citizens Committee OAGI0001299_00003
  • Load testing on CTG 11 and 12
  • Tune ammonia control and injection systems
  • U nit run for steam quality
  • Initial roll up and synchronization of the steam turbine
  • Duct burner firing testing and tuning
  • Perform Continuous Emissions Monitoring System (CEMS) testing and certification
  • On line emission tuning September 2010:
  • Plant in Commercial Operation OAGI0001299_00004