Notification of NRC Inspection and Request for Information
ML12326A679
Person / Time
Site: North Anna  
(NPF-004, NPF-007)
Issue date: 11/19/2012
From: Vias S
NRC/RGN-II/DRS/EB3
To: Heacock D
Virginia Electric & Power Co (VEPCO)
References
Download: ML12326A679 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 November 19, 2012 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company Dominion Nuclear Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

NORTH ANNA NUCLEAR POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Heacock:

On February 11, 2013, the Nuclear Regulatory Commission (NRC) will begin inspection activities for North Anna Nuclear Plant at the NRC Region II office in Atlanta, GA, in accordance with Temporary Instruction (TI) 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. This in-office inspection is scheduled to be performed from February 11-15, 2013 and will address the inspection requirements for Phase 1 of this TI.

In order to minimize the impact to your on-site resources, and to ensure a productive inspection, we have enclosed a list of documents needed for the preparation and implementation of this inspection. The documents that are requested for this inspection include all relevant documents that will allow the inspector(s) to adequately complete Phase 1 of this inspection.

We have discussed the schedule for this inspection activity with your staff and understand that our licensing contact for this inspection will be Mr. Jay Lieberstein of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Abhijit Sengupta at 404-997-4430 or Abhijit.Sengupta@nrc.gov.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide

D. Heacock 2

Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No.:

50-338, 50-339 License No.: NPF-4, NPF-7

Enclosure:

Temporary Instruction (TI 2515-182)

Inspection Document Request cc: (See page 3)

G SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRS RII:DRS RII:DRS SIGNATURE RA RA RA NAME ASENGUPTA CFLETCHER SVIAS DATE 11/ 15 /2012 11/ 19 /2012 11/ 19 /2012 11/ /2012 11/ /2012 11/ /2012 11/ /2012 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

D. Heacock 3

cc:

Mr. Gerald T. Bischof Site Vice President North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution Fred Mladen Director, Station Safety & Licensing Virginia Electric and Power Company Electronic Mail Distribution Michael Crist Plant Manager North Anna Power Station Virginia Electric & Power Company Electronic Mail Distribution Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

Electronic Mail Distribution Tom Huber Director, Nuclear Licensing & Operations Support Innsbrook Technical Center Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P.O. Box 1197 Richmond, VA 23209 Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219 Senior Resident Inspector North Anna Power Station U.S. Nuclear Regulatory Commission P.O. Box 490 Mineral, VA 23117 Donald R. Taylor Licensing Supervisor North Anna Power Station P. O. Box 402 Mineral, VA 23117-0402 Michael M. Cline Director Virginia Department of Emergency Services Management Electronic Mail Distribution Executive Vice President Old Dominion Electric Cooperative Electronic Mail Distribution County Administrator Louisa County P.O. Box 160 Louisa, VA 23093 Doug Smith President (Public Correspondence Only)

Lake Anna Civil Association Electronic Mail Distribution

Letter to David A. Heacock from Steven Vias dated November 19, 2012.

SUBJECT:

NORTH ANNA NUCLEAR POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION Distribution w/encl:

RIDSNRRDIRS PUBLIC RidsNrrPMNorthAnna Resource

Enclosure INSERVICE INSPECTION DOCUMENT REQUEST Inspection Dates:

February 11-15, 2013 Inspection Procedures:

TI 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks Inspector:

Abhijit Sengupta, Reactor Inspector Information Requested for the Preparation and Completion of the In-Office Inspection

1. The following documents listed below are requested (electronic copy CD ROM if possible or SharePoint) by January 11, 2013, to facilitate the preparation for the inspection.

A. Site point(s) of contact responsible for the implementation of the underground piping and tanks program; and B. Schedule for completion of the following NEI 09-14, Guideline For The Management of Underground Piping and Tank Integrity, Revision 1, attributes:

Buried Piping Procedures and Oversight Risk Ranking Inspection Plan Plan Implementation Asset Management Plan Underground Piping and Tanks Procedures and Oversight Prioritization Condition Assessment Plan Plan Implementation Asset Management Plan C. Copy of EPRI document Recommendations for an Effective Program to Control the Degradation of Buried Pipe.

D. Copy of Site Underground Piping and Tanks Program.

E. Self or third party assessments of the Underground Piping and Tanks Program (if any have been performed).

F. For any of the NEI 09-14, Revision 1, or subsequent revision attributes identified below which have been completed prior to the NRCs Phase 1 inspection, provide written records that demonstrate that the program attribute is complete.

2 Enclosure Buried Piping Procedures and Oversight Risk Ranking Inspection Plan Plan Implementation Asset Management Plan Underground Piping and Tanks Procedures and Oversight Prioritization Condition Assessment Plan Plan Implementation Asset Management Plan Inspector Contact Information Mailing Address Abhijit Sengupta US NRC-Region 2 Reactor Inspector Attn: Abhijit Sengupta 404.997.4430 245 Peachtree Center Avenue, Suite 1200 Abhijit.Sengupta@nrc.gov Atlanta, GA 30303