UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 November 6, 2012 Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
INSPECTION DATE CHANGES FOR THE CLINTON POWER STATION
Dear Mr. Pacilio:
This letter confirms our plans to change the on-site inspection dates for the Components Design Bases Inspection (CDBI) and Problem Identification and Resolution (PI&R) inspection at your Clinton Power Station, which was conveyed to you in our Mid-Cycle Assessment Letter dated September 4, 2012. The reason for the changes is to accommodate a scheduling conflict associated with these inspections at the Clinton Power Station.
Per discussion with Kathy Anne Baker, Regulatory Assurance Manager, the new on-site inspection weeks for the CDBI will be the weeks of May 20, June 3, June 17, 2013.
In addition, the new on-site inspection weeks for the PI&R inspection will be the weeks of August 12 and August 26, 2013.
Sincerely,
/RA/
Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-461 License No. NPF-62 cc:
Distribution via ListServ'
Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
INSPECTION DATE CHANGES FOR THE CLINTON POWER STATION
Dear Mr. Pacilio:
This letter confirms our plans to change the on-site inspection dates for the Components Design Bases Inspection (CDBI) and Problem Identification and Resolution (PI&R) inspection at your Clinton Power Station, which was conveyed to you in our Mid-Cycle Assessment Letter dated September 4, 2012. The reason for the changes is to accommodate a scheduling conflict associated with these inspections at the Clinton Power Station.
Per discussion with Kathy Anne Baker, Regulatory Assurance Manager, the new on-site inspection weeks for the CDBI will be the weeks of May 20, June 3, June 17, 2013.
In addition, the new on-site inspection weeks for the PI&R inspection will be the weeks of August 12 and August 26, 2013.
Sincerely,
/RA/
Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-461 License No. NPF-62 cc:
Distribution via ListServ' DISTRIBUTION:
See next page DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress\\Ltr 110612 CLI 2013 CDBI Schedule Change.docx G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME AMStoneBJose:ls ROrlikowski AMStone DATE 11/06/12 11/06/12 11/06/12 OFFICIAL RECORD COPY
Letter to Mr. Michael Pacilio from Ms. Ann Marie Stone dated November 6, 2012.
SUBJECT:
INSPECTION DATE CHANGE FOR THE 2013 COMPONENT DESIGN BASES INSPECTION FOR THE CLINTON POWER STATION DISTRIBUTION:
Cayetano Santos RidsNrrDorlLpl3-2 Resource RidsNrrPMBraidwood Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck Allan Barker DRPIII DRSIII Christine Lipa Carole Ariano Linda Linn Patricia Buckley Tammy Tomczak