MONTHYEARIR 05000250/20240052024-08-23023 August 2024 Updated Inspection Plan for Turkey Point Units 3 & 4 - Report 05000250/2024005 and 05000251/2024005 ML24234A0062024-08-22022 August 2024 Project Manager Assignment L-2024-106, Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-022024-08-12012 August 2024 Fifth and Sixth 10-Year Inservice Testing Interval Relief Request No. VR-02 L-2024-122, Core Operating Limits Report2024-08-12012 August 2024 Core Operating Limits Report ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-089, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-07-25025 July 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP- 17 451-P. Revision 1. Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal ML24173A1902024-06-28028 June 2024 Withdrawal of an Amendment Request ML24159A2652024-06-26026 June 2024 Correction of Safety Evaluation for Issuance of Amendment Nos. 298 & 291 Regarding Revising the Fire Protection Program in Support of Reactor Coolant Pump Seal Replacement Project L-2024-100, Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project2024-06-19019 June 2024 Withdrawal of License Amendment Request 274, Reactor Protection System, Engineered Safety Features Actuation System, and Nuclear Instrumentation System Replacement Project L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter IR 05000250/20244012024-06-0505 June 2024 – Security Baseline Inspection Report 05000250-2024401, 05000251-2024401 and 07200062-2024401 L-2024-076, Reply to Notice of Violation; NOV 05000250, 05000251/2024010-052024-05-29029 May 2024 Reply to Notice of Violation; NOV 05000250, 05000251/2024010-05 L-2024-082, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000250/20240012024-05-10010 May 2024 Integrated Inspection Report 05000250/2024001 and 05000251/2024001 ML24135A0942024-05-0909 May 2024 Periodic Update to the Updated Final Safety Analysis Report L-2024-060, 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report2024-05-0909 May 2024 10 CFR 50.59(d)(2) Evaluation and 10 CFR 50.71(e)(2) Technical Specification Bases Summaries Report ML24127A1862024-05-0909 May 2024 Request for Withholding Information from Public Disclosure ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes IR 05000250/20240102024-05-0101 May 2024 Design Basis Assurance Inspection Programs Inspection Report 05000250/2024010 and 05000251/2024010 and Notice of Violation L-2024-073, Cycle 34 Core Operating Limits Report2024-05-0101 May 2024 Cycle 34 Core Operating Limits Report L-2024-072, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report L-2024-048, Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision2024-04-30030 April 2024 Divider Plate Assemblies Bounding Analysis Evaluation for Subsequent License Renewal Commitment Revision L-2024-069, Radiological Emergency Plan Revision 762024-04-22022 April 2024 Radiological Emergency Plan Revision 76 L-2024-066, Sixth 10-Year Inservice Testing Interval Relief Request No. PR-022024-04-17017 April 2024 Sixth 10-Year Inservice Testing Interval Relief Request No. PR-02 ML24087A2002024-04-0505 April 2024 Letter to Miami-Dade County Office of Historic Preservation Re Section 106 on Turkey Point Units 3 & 4 EIS ML24087A2012024-04-0505 April 2024 Letter to Talbert Cypress, Miccosukee Tribe of Indians of Florida; Re., Section 106 Letters for Turkey Point ML24087A1982024-04-0505 April 2024 Notice of Availability of the Final Environmental Impact Statement for the Turkey Point Nuclear Generating Unit Numbers 3 and 4 Subsequent License Renewal Application ML24096A2142024-04-0505 April 2024 Ltr. to David Hill, Principal Chief, the Muscogee (Creek) Nation, Re., Section 106 Letters for Turkey Point ML24087A1992024-04-0505 April 2024 Achp Section 106 Letter Re Notice of Availability of the Final Environmental Impact Statement for Turkey Point Units 3 & 4 Subsequent License Renewal Application ML24096A2162024-04-0505 April 2024 Ltr. to Marcellus Osceola, Chairman, Seminole Tribe of Florida, Re., Section 106 Letters for Turkey Point ML24096A2152024-04-0505 April 2024 Ltr. to Lewis Johnson, Principal Chief, Seminole Nation of Oklahoma, Re., Section 106 Letters for Turkey Point ML24096A2182024-04-0505 April 2024 Ltr. to Stephanie Bryan, Tribal Chair, Poarch Band of Creek Indians, Re., Section 106 Letters for Turkey Point ML24072A2832024-04-0101 April 2024 Ltr to Dianne Strand-Notice of Avail.-Final Site-Specific Supp. 5a, 2nd Renewal to the GEIS for License Renewal L-2024-040, Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections2024-03-28028 March 2024 Notification of Deviation from Pressurized Water Owners Group (PWROG) Report WCAP-17451-P, Revision 1, Reactor Internals Guide Tube Wear - Westinghouse Domestic Fleet Operational Projections L-2024-047, Proposed Use of a Subsequent ASME Code Edition and Addenda2024-03-28028 March 2024 Proposed Use of a Subsequent ASME Code Edition and Addenda L-2024-013, Submittal of Periodic Reports2024-03-28028 March 2024 Submittal of Periodic Reports ML24073A1712024-03-26026 March 2024 Correction of Amendment Nos. 297 and 290 Regarding Conversion to Improved Standard Technical Specifications ML24072A2382024-03-20020 March 2024 Review of the Fall 2023 Steam Generator Tube Inspections During Refueling Outage No. 33 L-2024-044, Revised Steam Generator Tube Inspection Reports2024-03-19019 March 2024 Revised Steam Generator Tube Inspection Reports L-2024-011, and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2024-03-13013 March 2024 and Point Beach, Units 1 and 2 - 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications IR 05000250/20244202024-03-11011 March 2024 – Security Baseline Inspection Report 05000250/2024420 and 05000251/2024420 - Final ML24064A1642024-03-11011 March 2024 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 ML24058A1182024-03-0101 March 2024 Request for Withholding Information from Public Disclosure for Turkey Point Nuclear Generating Unit Nos. 3 and 4 L-2024-014, Turkey Points, Units 3 and 4 - 2023 Annual Radioactive Effluent Release Report2024-02-29029 February 2024 Turkey Points, Units 3 and 4 - 2023 Annual Radioactive Effluent Release Report IR 05000250/20230062024-02-28028 February 2024 Annual Assessment Letter for Turkey Point Units 3 & 4 - Report 05000250/2023006 and 05000251/2023006 2024-08-05
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 November 1, 2012 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420
SUBJECT:
CONFIRMATION OF REQUESTED INITIAL OPERATOR LICENSE EXAMINATIONS FOR TURKEY POINT NUCLEAR PLANT
Dear Mr. Nazar:
In a letter dated August 10, 2012, your staff responded to Regulatory Issue Summary 2012-07 and requested we schedule initial license operator examinations for the Turkey Point Nuclear Plant. Based on your letter and following discussions with your staff, we have scheduled the requested examinations as follows:
2013 2014 Plant / Station Date Applicants Date Applicants Turkey Point 3/4 15 * *
- Could not support requested date. Scheduled for Jan 2015.
On-site validation of the examinations is typically scheduled to occur approximately three weeks before each examination. If you have a need to change the dates of your scheduled exam(s) from that (those) listed above, please inform us in writing of your request and the reason for the change. Due to the large number of examinations scheduled to be administered at Region II sites, requests to change examination dates will be considered on a case-by-case basis. We will confirm any change in examination schedule with a follow-up letter.
We understand that your staff will develop the proposed examinations. For examinations that have greater than nine applicants, each examination is scheduled for a minimum of two weeks.
If the number of applicants is reduced to less than ten (10) for any examination, please inform us as this will impact the examination schedule.
A supplementary letter will be sent to each stations training department director approximately 120 days prior to the initial examination. The letter will provide the director with the chief examiner=s name, an outline of examination security expectations, a list of the materials required by the NRC to conduct the examination, and it will reconfirm the examination dates. If you have any questions concerning this information, please contact Mr. Malcolm Widmann, Chief, Operations Branch I, at 404-997-4550 or Mr. Mark Franke, Chief, Operations Branch II at 404-997-4436.
M. Nazar 2 In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRC=s public Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
Terrence Reis, Director Division of Reactor Safety Docket Nos.: 50-250, 50-251 License Nos.: DPR-31, DPR-41 cc: (See page 3)
_________________________ G SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRS RII:DRS RII:DRS RII:DRS SIGNATURE RA RA RA RA NAME SCHAAF WIDMANN FRANKE CHRISTENSEN DATE 10/25/2012 11/1/2012 `11/1/2012 11/1/2012 11/ /2012 11/ /2012 11/ /2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO M. Nazar 3 cc: Mitch S. Ross Alison Brown Vice President and General Counsel Nuclear Licensing Nuclear Florida Power & Light Company Florida Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Larry Nicholson Cynthia Becker Director (Acting) Chief Licensing Florida Bureau of Radiation Control Florida Power & Light Company Department of Health Electronic Mail Distribution Electronic Mail Distribution Michael Kiley Senior Resident Inspector Site Vice President Turkey Point Nuclear Generating Station Turkey Point Nuclear Plant U.S. Nuclear Regulatory Commission Florida Power and Light Company 9762 SW 344th St.
Electronic Mail Distribution Florida City, FL 33035 Niel Batista Attorney General Emergency Management Coordinator Department of Legal Affairs Department of Emergency Management The Capitol PL-01 and Homeland Security Tallahassee, FL 32399-1050 Electronic Mail Distribution County Manager of Miami-Dade County Paul Freeman 111 NW 1st Street, 29th Floor Vice President Miami, FL 33128 Organizational Effectiveness Florida Power & Light Company George Gretsas Electronic Mail Distribution City Manager City of Homestead Peter Wells Electronic Mail Distribution Vice President Outage Support CFAM Florida Power and Light Company Florida Power & Light Company ATTN: Mr. Brian Stamp Electronic Mail Distribution Training Manager Turkey Point Nuclear Plant Robert J. Tomonto 9760 SW 344th Street Licensing Manager Homestead, FL 33035 Turkey Point Nuclear Plant Florida Power & Light Company Electronic Mail Distribution Eric McCartney Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company Electronic Mail Distribution
Letter to Mano Nazar from Terrence Reis dated November 1, 2012
SUBJECT:
CONFIRMATION OF REQUESTED INITIAL OPERATOR LICENSE EXAMINATIONS FOR TURKEY POINT NUCLEAR PLANT Distribution:
ORA, RII T. Reis H. Christensen M. Widmann M. Franke K. Schaaf J. Vincent J. Kirby D. Rich J. McHale RIDSNRRDIRSIRIB Resource Document Control Desk - Licensing RIDSNRRDIRS PUBLIC RidsNrrPMTurkeyPoint Resource