Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
ML12307A182
Person / Time
Site: Millstone, 05000426  Dominion icon.png
Issue date: 10/25/2012
From: Heacock D
Dominion, Dominion Nuclear Connecticut
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
12-165A, EA-12-051
Download: ML12307A182 (3)


Text

Dominion Nuclear Connecticut, Inc. .FDominio 5000 Dominion Boulevard, Glen Allen, VA 23060

.,'Web Address: www.dom.com 10 CFR 2.202 October 25, 2012 EA-12-051 Attention: Document Control Desk Serial No.: 12-165A U.S. Nuclear Regulatory Commission NL&OS/MAE: RO Washington, D.C. 20555-0001 Docket Nos.: 50-336/423 License Nos.: DPR-65 NPF-49 DOMINION NUCLEAR CONNECTICUT, INC.

MILLSTONE POWER STATION UNITS 2 AND 3 INITIAL STATUS REPORT IN RESPONSE TO MARCH 12, 2012 COMMISSION ORDER MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR RELIABLE SPENT FUEL POOL INSTRUMENTATION (ORDER NUMBER EA-12-051)

References:

1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12073A202)
2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012 (ML12221A339)

On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an order (Reference 1) to Dominion Nuclear Connecticut, Inc. (DNC). Reference 1 was immediately effective and directs DNC to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.

Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) was issued August 29, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms DNC has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in associated spent fuel storage pools as described in Attachment 2 of Reference 1.

Major activities completed during this reporting period:

" Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.

" Requests for Information (RFI) were issued to spent fuel pool instrumentation (SFPI) suppliers.

  • Responses to the RFIs have been reviewed and potential equipment has been identified.
  • Procurement specifications, requesting bids from SFPI suppliers that offer this equipment, are being prepared.

Planned activities for the next six months:

" Development and submittal of the overall integrated plan. 0)

  • Issuance of site-specific procurement specifications.

Serial No. 12-165A 60-Day Response to Order EA-12-051 Docket Nos. 50-336/423 Page 2 of 3

" Selection of equipment and a supplier(s).

  • Preparation, review, and approval of conforming specifications.
  • Issuance of purchase orders for SFPI.

" Initiation of the design change process.

Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:

  • None at this time.

Project milestones schedule through completion of installation and testing:

" A project milestones schedule will be provided with the overall integrated plan.

  • Implementation of the order will be completed for Millstone Unit 2 prior to startup from Refueling Outage (RFO) 23 (Fall 2015).
  • Implementation of the order will be completed for Millstone Unit 3 prior to startup from Refueling Outage (RFO) 16 (Fall 2014).

If you have any questions, please contact Ms. Margaret Earle at (804) 273-2768.

Sincerely, DavidA.9$cdk President and Chief Nuclear Officer Dominion Nuclear Connecticut, Inc.

Commitments made by this letter: No New Regulatory Commitments COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by David A. Heacock who is President and Chief Nuclear Officer of Dominion Nuclear Connecticut, Inc.

He has affirmed before me that he is duly authorized to execute and file the foregoing document in behalf of the Company, and that the statements in the document are true to the best of his knowledge and belief.

Acknowledged before me thiv?-'Qday of ., 2012.

My Commission ExpiresL . ,,4/..2O//..

S- - - - - - - - - ,J Notary Public VICKI L. HULL (SEAL) Notary Public Commonwealth of Virginia 140542 My Commission Expires May 31, 2014

Serial No. 12-165A 60-Day Response to Order EA-12-051 Docket Nos. 50-336/423 Page 3 of 3 cc: Director of Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 13H16M 11555 Rockville Pike Rockville, MD 20852-2738 U. S. Nuclear Regulatory Commission, Region I Regional Administrator 2100 Renaissance Blvd.

Suite 100 King of Prussia, PA 19406-2713 Ms. Lisa M. Regner U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 011 F1 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Blake A. Purnell U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 012 D20 11555 Rockville Pike Rockville, MD 20852-2738 Mr. Steven R. Jones U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 010 Al 11555 Rockville Pike Rockville, MD 20852-2738 Mr. James S. Kim NRC Project Manager Millstone Units 2 and 3 U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 08 C 2A 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station