Other: NG-12-0426, NextEra Energy Duane Arnold, LLCs Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-04, NG-12-0428, NextEra Energy Duane Arnold, Llcs, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), NG-13-0084, NextEra Energy Duane Arnold, Llcs, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12, NG-13-0086, NextEra Energy Duane Arnold, LLCs Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
|
MONTHYEARNG-12-0428, NextEra Energy Duane Arnold, Llcs, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2012-10-29029 October 2012 NextEra Energy Duane Arnold, Llcs, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other NG-12-0426, NextEra Energy Duane Arnold, LLCs Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-042012-10-29029 October 2012 NextEra Energy Duane Arnold, LLCs Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) Project stage: Other NG-13-0084, NextEra Energy Duane Arnold, Llcs, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-122013-02-28028 February 2013 NextEra Energy Duane Arnold, Llcs, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-0 Project stage: Other NG-13-0086, NextEra Energy Duane Arnold, LLCs Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)2013-02-28028 February 2013 NextEra Energy Duane Arnold, LLCs Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: Other ML13255A1982013-09-16016 September 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI NG-13-0389, Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-0512013-10-10010 October 2013 Response to Request for Additional Information Regarding Overall Integrated Plan in Response to Order EA-12-051 Project stage: Response to RAI ML13323B4432013-11-26026 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation Project stage: RAI ML14007A2152014-01-17017 January 2014 Correction Letter - Duane Arnold Energy Center Regarding Interim Staff Evaluation and Request for Additional Information for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) Project stage: RAI 2013-11-26
[Table View] |
Text
October 29,2012 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 NEXTera M
ENERGV~
DUANE
~
ARNOLD NG-12-0428 10 CFR 2.202 NextEra Energy Duane Arnold, LLC's Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
References:
- 1. NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (ML12054A682)
- 2. NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29,2012 (ML12221A339)
On March 12,2012, the Nuclear Regulatory Commission ("NRC" or "Commission")
issued an order (Reference 1) to NextEra Energy Duane Arnold, LLC (hereafter, NextEra Energy Duane Arnold). Reference 1 was immediately effective and directs NextEra Energy Duane Arnold to have a reliable indication of the water level in associated spent fuel storage pools. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 requires submission of an initial status report 60 days following issuance of the final interim staff guidance. The final interim staff guidance (Reference 2) is dated August 29, 2012. The purpose of this letter is to provide the initial status report pursuant to Section IV, Condition C.2, of Reference 1 within 60 days following issuance of Reference 2. This report confirms NextEra Energy Duane Arnold has received Reference 2 and is in the process of evaluating the guidance for the purpose of providing a reliable indication of the water level in associated spent fuel storage pools as described in Attachment 2 of Reference 1.
NextEra Energy Duane Arnold, LLC, 3277 DAEC Road, Palo, IA 52324
Document Control Desk NG-12-0428 Page 2 of 2 Major activities completed during this reporting period:
Resources are being identified and project plans initiated, including development of milestones, to assure compliance with Reference 1.
Planned activities for the next six months:
Development and submittal of the overall integrated plan.
Technical difficulties encountered that could affect the ability to provide the licensee's February 28, 2013, submittal:
None at this time.
Project milestones schedule through completion of installation and testing:
A project milestones schedule will be provided with the overall integrated plan.
Implementation of the order will be completed for the Duane Arnold Energy Center prior to startup from Refueling Outage (RFO) 25 (Fall 2016).
This letter makes no new commitments or changes to any existing commitments.
If you have any questions or require additional information, please contact Ken Putnam at 319-851-7238.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on October 29,2012 Ri~i~~
Vice President, Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC