MONTHYEARML24262A2382024-09-18018 September 2024 Annual Report for the Ohio State University Research Reactor ML24156A1752024-05-23023 May 2024 Administrative Change at the Ohio State University Research Reactor (OSURR) IR 05000150/20242012024-05-0303 May 2024 Ohio State University - U.S. Nuclear Regulatory Commission Safety Inspection Report 05000150/2024201 ML24087A2062024-04-0808 April 2024 Ohio State University - Change of Facility Backup Project Manager ML24012A0282024-01-0808 January 2024 Administrative Change at the Ohio State University Research Reactor (OSURR) ML24002A7372024-01-0303 January 2024 Ohio State University - Change of Facility Project Manager ML23258A0892023-09-11011 September 2023 Ohio State University, Annual Report for Fy 2022/2023 IR 05000150/20232012023-03-16016 March 2023 Ohio State University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000150/2023201 IR 05000150/20232022023-03-13013 March 2023 Ohio State University - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000150/2023202 (Public) ML22257A1052022-09-0909 September 2022 Annual Report for the Ohio State University Research Reactor ML22070B0942022-04-12012 April 2022 Ohio State University U.S. Nuclear Regulatory Commission Safety Inspection Report ML22060A1042022-02-24024 February 2022 Report Regarding Loss of Building Exhaust Fan on February 14, 2022, While Operating the Ohio State University Research Reactor ML21267A3982021-09-13013 September 2021 Annual Report for the Ohio State University Research Reactor ML21215A0802021-08-11011 August 2021 Examination Confirmation Letter No. 50-150/OL-21-01, Ohio State University IR 05000150/20202012021-03-30030 March 2021 Ohio State University Routine Inspection Report 05000150/2020201 ML20295A4242020-11-16016 November 2020 Notification of Mailing Address Change Regarding Submittal of Fingerprint Cards ML20262H0622020-09-0909 September 2020 Annual Report for the Ohio State University Research Reactor, License R-75, Docket 50-150 ML19317D7992019-11-0606 November 2019 Replacement Pages for Modified Technical Specification 3.5 of Renewed Facility Operating License No. R-75 of the Ohio State University Research Reactor ML19298A1102019-10-22022 October 2019 Ohio State University - Revision to the Request for Modification of Technical Specifications 3.5 and 5.1.2 of Renewed Facility Operating License No. 75 ML19266A0282019-09-16016 September 2019 Annual Report for the Ohio State University Research Reactor ML19253A0512019-09-0606 September 2019 Additional Information to Support the Request for Modification of Technical Specifications 3.5 and 5.1.2 of Renewed Facility Operating License No. R-75 of the Ohio State University Research Reactor ML19105A1372019-04-10010 April 2019 Response to NRC Request for Additional Information (RAI) Letter to the Ohio State University Research Reactor (OSURR, License R-75) Dated January 16, 2019 ML19063A4992019-02-27027 February 2019 Response to NRC RAI Letter Dated 16-January-2019 Regarding License Amendment Request to Modify Technical Specifications 3.5 and 5.1.2 for License R-75 of the Ohio State University Research Reactor ML18360A3592019-01-16016 January 2019 the Ohio State University - Request for Additional Information License Amendment Request to Modify Technical Specifications 3.5 and 5.1.2 of Renewed Facility Operating License No. R-75 of the Ohio State University Research IR 05000150/20182012019-01-0909 January 2019 Ohio State University - U.S. Nuclear Regulatory Commission Safety Inspection Report 05000150/2018201 ML18324A5852018-11-14014 November 2018 Relevant Sections of the Ohio State University Research Reactor (OSURR, License R-75, Docket 50-150) Safety Analysis Report (SAR) to Support a Technical Specifications Amendment Request ML18303A1892018-10-31031 October 2018 the Ohio State University - Acceptance of Requested Licensing Action License Amendment Request to Modify Technical Specifications 3.5 and 5.1.2 of Renewed Facility Operating License No. R75 ML18291A9132018-10-16016 October 2018 Additional Information to Support a Technical Specifications Amendment Request for the Ohio State University Research Reactor (OSURR, License R-75, Docket 50-150) ML18270A1662018-10-0303 October 2018 the Ohio State University Nuclear Reactor Laboratory, Non-Acceptance of Amendment Request with Opportunity to Supplement, for the Renewed Facility License No. R-75 (CAC No. A11010/05000150) ML18267A0602018-09-18018 September 2018 the Ohio State University, Submittal of Annual Report for Fy 2017/2018 ML18242A0752018-08-27027 August 2018 Request for an Amendment to the Ohio State University Research Reactor IR 05000150/20172012018-02-13013 February 2018 Ohio State University - Nuclear Regulatory Commission Safety Inspection Report No. 50-150/2017-201 ML17285A4802017-10-18018 October 2017 the Ohio State University Nuclear Reactor Laboratory, Non-Acceptance of Amendment Request with Opportunity to Supplement, for the Renewed Facility License No. R-75 ML17244A2322017-08-22022 August 2017 Request for an Amendment to the Ohio State University Research Reactor Technical Specifications ML17118A3222017-05-0404 May 2017 Non-Power Reactor Closeout of Generic Letter 2016-01, Monitoring of Neutron Absorbing Materials in Spent Fuel Pools for the Ohio State University Research Reactor Docket No. 50-150 ML17088A1272017-03-23023 March 2017 the Ohio State University - Response to Generic Letter 2016-01 ML17086A0282017-03-22022 March 2017 Ohio State University Research Reactor - Updated Emergency Plan ML17081A4422017-03-20020 March 2017 Ohio State University, Response to Generic Letter 2016-01 IR 05000150/20162022016-10-20020 October 2016 Ohio State University - Nuclear Regulatory Commission Security Inspection Report No. 50-150/2016-202 (Letter Only) ML16273A0082016-09-30030 September 2016 Ohio State University - NRC Safety Inspection Report 05000150/2016201 ML16210A4042016-07-21021 July 2016 Ohio State University, Administrative Change Update ML16200A3542016-07-13013 July 2016 the Ohio State University - Submittal of Updated Emergency Plan for the Ohio State University Research Reactor (Osurr), License R-75, Docket 50-150 ML16084A0012016-04-0101 April 2016 CAL closure letter for Ohio State ML16060A1032016-02-23023 February 2016 Request to Closeout the Compensatory Measures for the Ohio State University Research Reactor IR 05000150/20152012015-12-0404 December 2015 IR 05000150/2015201, November 2-5, 2015, Ohio State University ML15265A5212015-09-18018 September 2015 Ohio State University - Annual Report for Fy 2014/2015 ML14290A4862015-06-0303 June 2015 Y020140127 - Withdrawal of Order EA-05-007, Order Imposing Additional Security Measures IR 05000000/20001502014-11-0606 November 2014 IR 05000000-150-2014-201 on October 6-9, 2014, Ohio State University, NRC Routine Inspection Report ML14272A0942014-09-24024 September 2014 Ohio State University Research Reactor,Submittal of Annual Report for Fy 2013/2014 ML14133A7222014-05-27027 May 2014 Ohio State University - Change of Facility Project Managers 2024-09-18
[Table view] |
Text
October 16, 2012 Mr. Andrew Kaufmann, Associate Director OSU Nuclear Reactor Laboratory Ohio State University 142 Hitchcock Hall 2070 Neil Avenue Columbus, OH 43210
SUBJECT:
EXAMINATION RESULTS LETTER NO. 50-150/OL-12-01, THE OHIO STATE UNIVERSITY
Dear Mr. Kaufmann:
This letter forwards to you personal privacy information associated with the operator licensing examinations administered during the week of September 17, 2012. This information supplements the publicly available information in the examination report. Enclosure 1 lists individual grades for the candidate. Enclosure 2 includes individual candidate summaries for the candidate (licenses and supporting documentation).
If you have any questions regarding the examination please contact Gary Morlang at 301-415-4092, or via e-mail at gary.morlang@nrc.gov.
Sincerely,
/RA/
Gregory T. Bowman, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-150
Enclosures:
As stated
October 16, 2012 Mr. Andrew Kaufmann, Associate Director OSU Nuclear Reactor Laboratory Ohio State University 142 Hitchcock Hall 2070 Neil Avenue Columbus, OH 43210
SUBJECT:
EXAMINATION RESULTS LETTER NO. 50-150/OL-12-01, THE OHIO STATE UNIVERSITY
Dear Mr. Kaufmann:
This letter forwards to you personal privacy information associated with the operator licensing examinations administered during the week of September 17, 2012. This information supplements the publicly available information in the examination report. Enclosure 1 lists individual grades for the candidate. Enclosure 2 includes individual candidate summaries for the candidate (license/denial letters and supporting documentation).
If you have any questions regarding the examination please contact Patrick Isaac at 301-415-4092, or via e-mail at gary.morlang@nrc.gov.
Sincerely,
/RA/
Gregory T. Bowman, Chief Research and Test Reactors Oversight Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-150
Enclosures:
As stated DISTRIBUTION w/ encls.:
PUBLIC PROB r/f GBowman Facility File (CRevelle)
ADAMS ACCESSION #: ML12286A042 OFFICE PROB:CE IOLB:LA PROB:BC NAME GMorlang CRevelle GBowman DATE 10/09/2012 10/15/2012 10/16/2012 OFFICIAL RECORD COPY