UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 September 11, 2012 Mr. Mano Nazar Executive Vice President and Chief Nuclear Officer Florida Power and Light Company P.O. Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

TURKEY POINT NUCLEAR POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION

Dear Mr. Nazar:

On October 22, 2012, the Nuclear Regulatory Commission (NRC) will begin inspection activities for Turkey Point Nuclear Plant at the NRC Region II office in Atlanta, GA, in accordance with Temporary Instruction (TI) 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. This in-office inspection is scheduled to be performed from October 22-26, 2012, and will address the inspection requirements for Phase 1 of this TI.

In order to minimize the impact to your on-site resources, and to ensure a productive inspection, we have enclosed a list of documents needed for the preparation and implementation of this inspection. The documents that are requested for this inspection include all relevant documents that will allow the inspector(s) to adequately complete Phase 1 of this inspection.

We have discussed the schedule for this inspection activity with your staff and understand that our licensing contact for this inspection will be Ms. Stavrula Mihalakea of your organization. If there are any questions about this inspection or the material requested, please contact the lead inspector Alexandra Vargas at 404-997-4657 or Alexanda.Vargas@nrc.gov.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide

M. Nazar 2 Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No.: 50-250, 50-251 License No.: DPR-31, DPR-41

Enclosure:

Temporary Instruction (TI 2515-182)

Inspection Document Request cc: (See page 3)

_________________________ G SUNSI REVIEW COMPLETE G FORM 665 ATTACHED OFFICE RII:DRS RII:DRS RII:DRS SIGNATURE RA RA RA NAME VARGAS FLETCHER VIAS DATE 9/11/2012 9/11/2012 9/22/2012 9/ /2012 9/ /2012 9/ /2012 9/ /2012 E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO M. Nazar 3 cc: Mitch S. Ross Alison Brown Vice President and General Counsel Nuclear Licensing Nuclear Florida Power & Light Company Florida Power & Light Company Electronic Mail Distribution Electronic Mail Distribution Larry Nicholson Cynthia Becker Director (Acting) Chief Licensing Florida Bureau of Radiation Control Florida Power & Light Company Department of Health Electronic Mail Distribution Electronic Mail Distribution Michael Kiley Senior Resident Inspector Site Vice President Turkey Point Nuclear Generating Station Turkey Point Nuclear Plant U.S. Nuclear Regulatory Commission Florida Power and Light Company 9762 SW 344th St.

Electronic Mail Distribution Florida City, FL 33035 Niel Batista Attorney General Emergency Management Coordinator Department of Legal Affairs Department of Emergency Management The Capitol PL-01 and Homeland Security Tallahassee, FL 32399-1050 Electronic Mail Distribution County Manager of Miami-Dade County Paul Freeman 111 NW 1st Street, 29th Floor Vice President Miami, FL 33128 Organizational Effectiveness Florida Power & Light Company George Gretsas Electronic Mail Distribution City Manager City of Homestead Peter Wells Electronic Mail Distribution Vice President Outage Support CFAM Florida Power & Light Company Electronic Mail Distribution Robert J. Tomonto Licensing Manager Turkey Point Nuclear Plant Florida Power & Light Company Electronic Mail Distribution Eric McCartney Plant General Manager Turkey Point Nuclear Plant Florida Power and Light Company Electronic Mail Distribution

Letter to Mano Nazar from Steven J. Vias dated September 11, 2012.

SUBJECT:

TURKEY POINT NUCLEAR POWER STATION - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION Distribution:

RIDSNRRDIRS PUBLIC RidsNrrPMTurkeyPoint Resource

INSERVICE INSPECTION DOCUMENT REQUEST Inspection Dates: October 22 - 26, 2012 Inspection Procedures: TI 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks Inspector: Alexandra Vargas, Reactor Inspector Information Requested for the Preparation and Completion of the In-Office Inspection

1. The following documents listed below are requested (electronic copy CD ROM if possible or SharePoint) by October 22, 2012, to facilitate the preparation for the inspection.

A. Site point(s) of contact responsible for the implementation of the underground piping and tanks program; and B. Schedule for completion of the following NEI 09-14, Guideline For The Management of Underground Piping and Tank Integrity, Revision 1, attributes:

Buried Piping

  • Procedures and Oversight
  • Risk Ranking
  • Inspection Plan
  • Plan Implementation
  • Asset Management Plan Underground Piping and Tanks
  • Procedures and Oversight
  • Prioritization
  • Condition Assessment Plan
  • Plan Implementation
  • Asset Management Plan C. Copy of EPRI document Recommendations for an Effective Program to Control the Degradation of Buried Pipe.

D. Copy of Site Underground Piping and Tanks Program.

E. Self or third party assessments of the Underground Piping and Tanks Program (if any have been performed).

F. For any of the NEI 09-14, Revision 1, or subsequent revision attributes identified below which have been completed prior to the NRCs Phase 1 inspection, provide written records that demonstrate that the program attribute is complete.

Enclosure

2 Buried Piping

  • Procedures and Oversight
  • Risk Ranking
  • Inspection Plan
  • Plan Implementation
  • Asset Management Plan Underground Piping and Tanks
  • Procedures and Oversight
  • Prioritization
  • Condition Assessment Plan
  • Plan Implementation
  • Asset Management Plan Inspector Contact Information Mailing Address Alexandra Vargas US NRC- Region 2 Reactor Inspector Attn: Alexandra Vargas 404.997.4657 245 Peachtree Center Avenue, Suite 1200 Alexandra.Vargas@nrc.gov Atlanta, GA 30303 Enclosure