UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 August 31, 2012 Mr. Larry Meyer Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION
Dear Mr. Meyer:
In a telephone conversation on August 31, 2012, Mr. D. Lauterbur, Training Director, and Mr. C. Moore, Operations Engineer, at the U. S. Nuclear Regulatory Commission (NRC) arranged to inspect a portion of your Requalification Training Program. Mr. Moore will observe the training departments administration of a requalification examination in accordance with Inspection Procedure 71111.11B. Mr. Moore will also review annual operating test pass-fail results. The inspection is planned for Tuesday, September 25, 2012, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please provide the operating test scheduled for the week of September 24, 2012. In addition, make available those documents at your earliest convenience. Mr. D. Lauterbur has been advised of this request and given the name of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018. The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of these information collections, including suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. C. Moore at 630-829-9732, or me at 630-829-9707.
Sincerely,
/RA by R. K. Walton Acting For/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266, 50-301 and 72-005 License Nos. DPR-24 and DPR-27 cc: Distribution via ListServ'
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. C. Moore at 630-829-9732, or me at 630-829-9707.
Sincerely,
/RA by R. K. Walton Acting For/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-266, 50-301 and 72-005 License Nos. DPR-24 and DPR-27 cc: Distribution via ListServ' Distribution:
Silas Kennedy RidsNrrDorlLpl3-1 Resource RidsNrrPMPointBeach RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck Allan Barker Christine Lipa Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak John McHale, NRR J. R. Kweiser, DRS D. Lauterbur, Training Department DOCUMENT NAME: G:\\DRSIII\\DRS\\Work in Progress\\Ltr 083112 Point Beach 7111111A Inspection Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII C RIII RIII RIII NAME CMoore:ls Kwalton for HPeterson DATE 08/31/12 08/31/12 OFFICIAL RECORD COPY