UNITED STATES NUCLEAR REGULATORY COMMISSION REGION II 245 PEACHTREE CENTER AVENUE NE, SUITE 1200 ATLANTA, GEORGIA 30303-1257 August 31, 2012 Mr. T. A. Lynch Vice President Southern Nuclear Operating Company, Inc.
Joseph M. Farley Nuclear Plant P.O. Drawer 470, BIN B500 Ashford, AL 36312
SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Lynch:
On October 2, 2012, the Nuclear Regulatory Commission (NRC) will begin inspection activities for the Joseph M. Farley Nuclear Plant at the NRC Region II office in Atlanta, GA., in accordance with Temporary Instruction (TI) 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks. This in-office inspection is scheduled to be performed from October 2-4, 2012, and will address the inspection requirements for Phase 1 of this TI.
In order to minimize the impact to your onsite resources, and to ensure a productive inspection, we have enclosed a list of documents needed for the preparation and implementation of this inspection. The documents that are requested for this inspection include all relevant documents that will allow the inspector(s) to adequately complete Phase 1 of this inspection.
We have discussed the schedule for this inspection activity with your staff and understand that our regulatory contact for this inspection will be Lisa Hogg of your organization. If there are any questions about this inspection, or the material requested, please contact the lead inspector Matt Endress at 404-997-4524 or Matthew.Endress@nrc.gov.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its Enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide
T. Lynch 2
Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/ adams.html (the Public Electronic Reading Room).
Sincerely
/RA/
Steven J. Vias, Chief Engineering Branch 3 Division of Reactor Safety Docket No.
50-348 and 50-364 License No.
Enclosure:
Temporary Instruction (TI 2515-182) Inspection Document Request cc: (See page 3)
ML12244A196 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII:DRS RII:DRS RII:DRS SIGNATURE MXE2 CMF1 SJV NAME M. ENDRESS C. FLETCHER S. VIAS DATE 8/ 27 /2012 8/ 28 /2012 8/ 29 /2012 E-MAIL COPY YES NO YES NO YES NO
T. Lynch 3
cc:
C. Russ Dedrickson Fleet Support Supervisor Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Cheryl A. Gayheart Plant Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution S. Kuczynski Chairman, President and CEO Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Leigh Perry SVP & General Counsel-Ops & SNC Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution D. G. Bost Chief Nuclear Officer Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Dennis R. Madison Vice President Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Paula Marino Vice President Engineering Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution T. E. Tynan Site Vice President Vogtle Electric Generating Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution M. J. Ajluni Nuclear Licensing Director Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Mark Williams Commissioner Georgia Department of Natural Resources Electronic Mail Distribution B. D. McKinney, Jr.
Regulatory Response Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution D. W. Daughhetee Licensing Engineer Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution T. D. Honeycutt Regulatory Response Supervisor Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. Mike Stinson Vice President Fleet Operations Support Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution N. J. Stringfellow Licensing Manager Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. P. Hill Licensing Supervisor Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution L. L. Crumpton Administrative Assistant, Sr.
Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution William D. Oldfield Principal Licensing Engineer Joseph M. Farley Nuclear Plant Electronic Mail Distribution (cc w/encl contd - See page 4)
T. Lynch 4
(cc contd from page 3)
Todd L. Youngblood Vice President Fleet Oversight Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution John G. Horn Site Support Manager Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company, Inc.
Electronic Mail Distribution Senior Resident Inspector U.S. Nuclear Regulatory Commission Joseph M. Farley Nuclear Plant P. O. Box 620 Ashford, AL 36312 Cynthia A. Sanders Radioactive Materials Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution James C. Hardeman Environmental Radiation Program Manager Environmental Protection Division Georgia Department of Natural Resources Electronic Mail Distribution Mr. Mark Culver Chairman Houston County Commission P. O. Box 6406 Dothan, AL 36302 James L. McNees, CHP Director Office of Radiation Control Alabama Dept. of Public Health P. O. Box 303017 Montgomery, AL 36130-3017 Donald E. Williamson State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 30317 Montgomery, AL 36130-3017 Chuck Mueller Manager Policy and Radiation Program Georgia Department of Natural Resources Electronic Mail Distribution
Enclosure TI 2515-182 INSPECTION DOCUMENT REQUEST Inspection Dates:
October 2 - 3, 2012 Inspection Procedures:
TI 2515-182, Review of Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks Inspector:
Matt Endress, Reactor Inspector Information Requested for the Preparation and Completion of the In-Office Inspection
- 1. The following documents listed below are requested (electronic copy or CD ROM if possible) by September 20, 2012, to facilitate the preparation for the inspection.
A. Site point(s) of contact responsible for the implementation of the underground piping and tanks program; and B. Schedule for completion of the following NEI 09-14, Guideline For The Management of Underground Piping and Tank Integrity, Revision 1, attributes:
Buried Piping Procedures and Oversight Risk Ranking Inspection Plan Plan Implementation Asset Management Plan Underground Piping and Tanks Procedures and Oversight Prioritization Condition Assessment Plan Plan Implementation Asset Management Plan C. Copy of Site Underground Piping and Tanks Program.
D. Self or third party assessments of the Underground Piping and Tanks Program (if any have been performed).
E. For any of the NEI 09-14, Revision 1, or subsequent revision attributes identified below which have been completed prior to the NRCs onsite inspection, provide written records that demonstrate that the program attribute is complete.
Buried Piping Procedures and Oversight Risk Ranking Inspection Plan
2 Plan Implementation Asset Management Plan Underground Piping and Tanks Procedures and Oversight Prioritization Condition Assessment Plan Plan Implementation Asset Management Plan