UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
245 PEACHTREE CENTER AVENUE NE, SUITE 1200
ATLANTA, GEORGIA 30303-1257
August 9, 2012
Mr. Joseph W. Shea
Manager, Corp. Nuclear Licensing Programs
Tennessee Valley Authority
Chattanooga, TN 37402-2801
SUBJECT:
SEQUOYAH NUCLEAR PLANT- NOTIFICATION OF LICENSED OPERATOR
INITIAL EXAMINATION 05000327/2012302 AND 05000328/2012302
Dear Mr. Shea:
In a telephone conversation on August 3, 2012, between Mr. Michael Buckner, Exam Project
Manager, and Mr. Edwin Lea, Jr., Senior Operations Examiner, arrangements were made for
the administration of licensing examinations at the Sequoyah Nuclear Plant. The operating test
is scheduled to be administered during the weeks of December 3, 2012. The written
examination is scheduled to be administered the week of December 10, 2012. The on-site
preparatory week is scheduled for the week of November 12, 2012.
As agreed during the telephone conversation, your staff will prepare both the operating test and
written examination based on the guidelines in Revision 9, Supplement 1, of NUREG-1021,
"Operator Licensing Examination Standards for Power Reactors." The U.S. Nuclear Regulatory
Commission (NRC) regional office will discuss with your staff any changes that might be
necessary before the examinations are administered. Your staff has also agreed to make
copies of all examination materials that are necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the operating test
outline by September 14, 2012. Mr. Lea provided the written examination outline to your staff in
March of 2012. The operating test, written examination, and the supporting reference materials
identified in Attachment 3 to ES-201, will be due by October 10, 2012. Pursuant to Title 10,
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the outline, examination, and test before
they are submitted to the NRC for review and approval. All materials shall be complete and
ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked. Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled. In order to conduct the
requested written examinations and operating tests, it will be necessary for your staff to provide
adequate space and accommodations in accordance with ES-402, and to make the simulation
facility available on the dates noted above. In accordance with ES-302, your staff should retain
the original simulator performance data (e.g., system pressures, temperatures, and levels)
generated during the dynamic operating tests until the examination results are final. Appendix E
of NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while
the written examinations and operating tests are being administered.
J. Shea
2
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications, medical certifications, and waiver
requests (if any), at least 30 days before the first examination date. If the applications are not
received at least 30 days before the examination date, a postponement may be necessary.
Signed applications certifying that all training has been completed should be submitted at least
14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of
Management and Budget (OMB) under approval number 3150-0018, which expires on February
28, 2013. The public reporting burden for this collection of information is estimated to average
500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining
the data needed, writing the examinations, and completing and reviewing the collection of
information. Send comments on any aspect of this collection of information, including
suggestions for reducing the burden, to the Information and Records Management Branch (T-6
F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet
electronic mail at infocollectsresource@nrc.gov; and to the Desk Officer, Office of Information
and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget,
Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its
enclosures will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of the NRCs document
system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. Mr. Buckner has been advised of the policies and
guidelines referenced in this letter. If you have any questions regarding the NRC's examination
procedures and guidelines, please contact Mr. Lea at (404) 997-4567, (Internet E-mail:
edwin.lea@nrc.gov), or me at (404) 997-4436, (Internet E-mail: mark.franke@nrc.gov).
Sincerely
/RA M. Widmann For/
Mark E. Franke, Chief
Operations Branch 2
Division of Reactor Safety
Docket No.
50-327, 50-328
License No.
cc w/encl: (See page 3)
X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED
OFFICE
RII: DRS/OL2
RII: DRS/OL2
SIGNATURE
RA/MW For EL
RA/MW For MF
NAME
E. LEA
M. FRANKE
DATE
08/09/2012
08/09/2012
E-MAIL COPY?
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
J. Shea
3
cc w/encl:
J. T. Carlin
Site Vice President
Sequoyah Nuclear Plant
Tennessee Valley Authority
Electronic Mail Distribution
P. R. Simmons
Plant Manager
Sequoyah Nuclear Plant
Tennessee Valley Authority
Electronic Mail Distribution
G. M. Cook
Manager
Licensing
Sequoyah Nuclear Plant
Electronic Mail Distribution
C. D. Mackaman
Tennessee Valley Authority
Electronic Mail Distribution
Edward J. Vigluicci
Assistant General Counsel
Tennessee Valley Authority
Electronic Mail Distribution
County Mayor
Hamilton County Courthouse
208 Courthouse
625 Georgia Avenue
Chattanooga, TN 37402-2801
Tennessee Department of Environment &
Conservation
Division of Radiological Health
401 Church Street
Nashville, TN 37243
Senior Resident Inspector
U.S. Nuclear Regulatory Commission
Sequoyah Nuclear Plant
2600 Igou Ferry Road
Soddy Daisy, TN 37379-3624
Tennessee Valley Authority
ATTN: Ms. Coleen Ware
Training Manager
Sequoyah Nuclear Plant
P. O. Box 2000
Soddy-Daisy, TN 37384-2000
Ann Harris
341 Swing Loop
Rockwood, TN 37854
J. Shea
4
Letter to Joseph W. Shea from M. Franke dated August 9, 2012.
SUBJECT:
SEQUOYAH NUCLEAR PLANT- NOTIFICATION OF LICENSED OPERATOR
INITIAL EXAMINATION 05000327/2012302 AND 05000328/2012302
Distribution w/encl:
C. Evans, RII EICS (Part 72 Only)
L. Douglas, RII EICS (Linda Douglas)
OE Mail (email address if applicable)
RIDSNRRDIRS
PUBLIC
R. Pascarelli, NRR ((Regulatory Conferences Only))
RidsNrrPMSequoyah Resource