ML12220A437

From kanterella
Jump to navigation Jump to search
Lr Hearing - FW: Draft RAIs - Followup to Partial Response of June 14, 2012
ML12220A437
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 08/07/2012
From:
Office of Nuclear Reactor Regulation
To:
Division of License Renewal
References
Download: ML12220A437 (3)


Text

IPRenewal NPEmails From: Daily, John Sent: Tuesday, August 07, 2012 1:12 PM To: IPRenewal NPEmails

Subject:

FW: Draft RAIs - followup to partial response of June 14, 2012 John Daily Senior Project Manager, Division of License Renewal Office of Nuclear Reactor Regulation USNRC John.Daily@NRC.Gov (301) 415-3873 From: Walpole, Robert W [1]

Sent: Wednesday, August 01, 2012 10:12 AM To: Daily, John

Subject:

Re: Draft RAIs - followup to partial response of June 14, 2012 Thanks John, We are on track to respond to the other open MRP-227a items as stated in our earlier letter (end of Sept).

Bob Sent from my BlackBerry Wireless Handheld From: Daily, John [2]

Sent: Wednesday, August 01, 2012 08:26 AM To: Walpole, Robert W Cc: Turk, Sherwin <Sherwin.Turk@nrc.gov>

Subject:

Draft RAIs - followup to partial response of June 14, 2012

Bob, Attached please find three follow-up RAIs resulting from our initial review of your RAI response of June 14, 2012.

Please have your staff review these and indicate to me if you desire a conference call to discuss them.

As a reminder, the staff typically sends out SER-related RAIs in this format to allow about 7 days for a clarifying conference call, which the applicant can request.

Following that, and in any case within about 7-10 days, the formal RAIs will be issued to the applicant.

Also, recall that, as of issuance by the staff of the GALL Report, Revision 2, and the associated Standard Review Plan-License Renewal, Revision 2 (both in December 2010), these are the current standards by which the staff evaluates AMP programs, items requiring further evaluation, associated AMR review line items, and TLAAs. Currently-issued staff ISGs such as ISG-LR-2011-01 (for example) and/or other generic communications should also be consulted by applicants as required, if the document is applicable to the issue being addressed by the applicant.

If you have any questions, please contact me.

Thanks!

John Daily 1

Senior Project Manager, Division of License Renewal Office of Nuclear Reactor Regulation USNRC John.Daily@NRC.Gov (301) 415-3873 2

Hearing Identifier: IndianPointUnits2and3NonPublic_EX Email Number: 3603 Mail Envelope Properties (0046140293E11F408991442DB4FE25CA95845B1FA2)

Subject:

FW: Draft RAIs - followup to partial response of June 14, 2012 Sent Date: 8/7/2012 1:12:06 PM Received Date: 8/7/2012 1:12:09 PM From: Daily, John Created By: John.Daily@nrc.gov Recipients:

"IPRenewal NPEmails" <IPRenewal.NPEmails@nrc.gov>

Tracking Status: None Post Office: HQCLSTR01.nrc.gov Files Size Date & Time MESSAGE 2232 8/7/2012 1:12:09 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: