FENOC Disclosure Update 8
ML12213A474
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 07/31/2012
From: Matthews T
FirstEnergy Nuclear Operating Co, Morgan, Morgan, Lewis & Bockius, LLP
To: Harris B, Lodge T
- No Known Affiliation, NRC/OGC
SECY RAS
References
RAS 23109, 50-346-LR, ASLBP 11-907-01-LR-BD01
Download: ML12213A474 (16)


Text

Morgan, Lew 1111 Pennsy Washington, Tel: 202-739 Fax: 202-739 www.morgan Timothy P 202.739.552 tmatthews@

July 31, 2 Via Elec Terry J. L 316 N. M Toledo, O Brian G.

Office of U.S. Nuc Washing RE:

E N

D Dear Cou Pursuant Boards O Nuclear O Contentio FENOC

  • Enclo whos may r opini will u
  • Enclo comp be rel wis & Bockius LLP ylvania Avenue, NW DC 20004 9-3000 9-3001 nlewis.com P. Matthews 27

@morganlewis.com 2012 ctronic Infor Lodge, Esq.

Michigan St.,

OH 43604 Harris, Esq.

f the General clear Regulat gton, DC 205 Eighth Updat Nuclear Oper Docket No. 5 unsel:

to 10 C.F.R Order modif Operating C on 4 as affirm s disclosure osure 1 is res se opinion FE rely as witne ions. FENO update Enclo osure 2 prov pilations, and levant to the W

m rmation Ex

, Suite 520 l Counsel tory Commi 555-0001 te to Mandat rating Co., L 0-346 R. § 2.336, th fying the Init Company (FE med by the C s consist of served for th ENOC will b esses, and a C has not ye osure 1 when vides a descri d tangible th e admitted co change ission tory Disclosu License Rene he Boards In tial Scheduli ENOC) is pro Commission the followin he names, ad base its posi copy of the et identified n it has ident iption, by ca hings in the p ontention. P ures Pursuan ewal for Dav nitial Schedu ing Order da oviding the e n on March 2 ng:

ddresses, and tions on the analyses and witnesses fo tified its witn ategory and l possession, c Per the Sched nt to 10 C.F.

vis-Besse Nu uling Order d ated Novemb enclosed dis 27, 2012 (CL d telephone n contention a d authorities or any hearin nesses.

location, of t custody, or c duling Order R. § 2.336; F uclear Power dated June 1 ber 2, 2011, sclosures for LI-12-18).

numbers of t and upon wh upon which ng on the con the documen control of FE r and our agr FirstEnergy r Station, 15, 2011, and FirstEnergy r Intervenors the persons u hom FENOC h they base th ntention, and nts, data ENOC that m reement, the d the y

s upon C

heir d

may ese

Terry J. Lodge, Esq.

Brian G. Harris, Esq.

July 31, 2012 Page Two disclosures do not include privileged documents, or publicly-available documents unless FirstEnergy expects to rely on them at hearing. If you determine that you would like a copy of any of these documents, please inform me of which documents you would like, and I will provide a copy to you.

  • Enclosure 3 provides an index of documents, data compilations, or tangible things that may be relevant to the contention but that contain proprietary information, Sensitive Unclassified Non-Safeguards Information (SUNSI), or otherwise protected information. Upon request, FENOC will provide a copy under the terms of a Protective Order issued by the Board.

In order to compile Enclosures 2 and 3, a search was conducted of documents in FENOCs possession, custody, or control. The attached affidavit attests that all relevant materials identified by this search that are required to be disclosed under the Scheduling Order have been disclosed.

When FENOC identifies additional relevant documents or the witnesses for any hearing on the contention, FENOC will update these disclosures as required by the Boards Scheduling Order.

FENOC has been conservative in identifying documents for inclusion in Enclosures 2 and 3. By identifying documents in those Enclosures, FENOC does not necessarily concede that the documents are in fact relevant or material to the admitted contention.

Sincerely, Executed in Accord with 10 C.F.R. § 2.304(d)

Signed (electronically) by Timothy P. Matthews Timothy P. Matthews 1111 Pennsylvania Ave. NW Washington, DC 2004 (202) 739-5527 tmatthews@morganlewis.com Counsel for FirstEnergy Nuclear Operating Co.

Enclosures

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD

)

In the Matter of

)

)

Docket No. 50-346-LR FIRSTENERGY NUCLEAR OPERATING COMPANY

)

)

(Davis-Besse Nuclear Power Station, Unit 1)

)

)

AFFIDAVIT OF CLIFF CUSTER

1.

My name is Cliff Custer. I am the Project Manager, License Renewal, at FirstEnergy Nuclear Operating Company (FENOC). Working with the attorneys for FENOC, I have been responsible for managing the collection of documents, data compilations, and tangible things to comply with the mandatory disclosure requirements in 10 C.F.R. § 2.336 and the Atomic Safety and Licensing Boards Initial Scheduling Order dated June 15, 2011 (Scheduling Order) in this proceeding, and the Licensing Boards Order Granting Motion for Modification of Initial Scheduling Order dated November 2, 2011 in this proceeding.

2.

FENOC conducted a search of documents, data compilations, and tangible things in its possession, custody, and control for information relevant to the admitted contention as modified by the Commission (CLI-12-08), and in the possession, custody, and control of its affiliated companies, as specified in 10 C.F.R. § 2.336(a). As provided in 10 C.F.R. § 2.336(c), this search encompassed information and documents reasonably available to FENOC and its affiliated companies, including:

a.

Both electronic and paper documents;

2

b.

Corporate records, Davis-Besse license renewal project files, and documents in the possession and control of individuals who have worked on the Davis-Besse license renewal project or on matters potentially relevant to the admitted contention; and

c.

Documents, data compilations, and tangible things in the possession and control of AREVA, Inc. (AREVA), which assisted FENOC in preparing portions of the Davis-Besse Environmental Report.

3.

Consistent with the Boards Scheduling Order, Enclosure 2 to this Affidavit provides an index of relevant, non-privileged, non-protected documents, data compilations, and tangible things that were located as a result of this search.

4.

Consistent with the Boards Scheduling Order, Enclosure 3 to this Affidavit provides the index of relevant documents, data compilations, and tangible things containing information that FENOC believes are proprietary to FENOC or its affiliated companies or third parties, or falls within the category of Sensitive Unclassified, Non-Safeguards Information (SUNSI).

5.

FENOC has been conservative in identifying documents for inclusion in the Enclosures.

Accordingly, FENOC is not suggesting that just because a document is listed on the Enclosure that it is indeed relevant to the admitted contention.

6.

These disclosures are reasonably accurate and complete as of June 30, 2012.

3 The statements made above are true to the best of my knowledge, information, and belief.

I declare under penalty of perjury that the foregoing is true and correct.

Executed in Accord with 10 C.F.R. §2.304(d)

Signed (electronically) by Cliff Custer___

Cliff Custer License Renewal Project Manager FirstEnergy Nuclear Operating Company Beaver Valley Nuclear Power Station Route 168 Shippingport, PA 15077 Phone: 724-682-7139 E-mail: custerc@firstenergycorp.com Executed this 30th day of July 2012.

(Reserved)

First Energy-Davis-Besse License Renewal Proceeding Mandatory Disclosure Log Eighth Update, July 31, 2012 Log No.

Category Location*

Document Title Date Contentions FEDB-000008336 Standard file;Standard file without attachment Morgan, Lewis &

Bockius PRA-DB1-11-017-R00 wo cover.doc 6/5/2012 Contention 4 FEDB-000008337 eMail;eMail with attachment Morgan, Lewis &

Bockius MAAP FLAASH

  1. 68 1/3/2012 Contention 4 FEDB-000008338 eMail;eMail with attachment Morgan, Lewis &

Bockius Transmittal of AREVA Doc ID 51-9182897-000 and 51-9124603-008 6/11/2012 Contention 4 FEDB-000008339 eMail;eMail with attachment Morgan, Lewis &

Bockius DB quantification notebook 6/7/2012 Contention 4

First Energy-Davis-Besse License Renewal Proceeding Proprietary Log Eighth Update, July 31, 2012 Log No.

Category Location*

Document Title Date Confidentiality Contentions FEDBPROP-00003725 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 86-9126346-001 DB Core Inventory (Mass)_2012-01-10 FINAL.pdf 7/25/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003726 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 15 1020236.pdf 6/25/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003727 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 32-9125650-005 L3.pdf 6/12/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003728 eMail;eMail with attachment Morgan, Lewis &

Bockius FW: 25 MAAP elements 1/3/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4); Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003729 Attachment Morgan, Lewis &

Bockius Element Sort for Client.xls 1/3/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4); Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003730 eMail;eMail without attachment Morgan, Lewis &

Bockius Jan 26 MAAP update 1/26/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003731 eMail;eMail without attachment Morgan, Lewis &

Bockius Re: Jan 31 MAAP update 1/31/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003732 eMail;eMail with attachment Morgan, Lewis &

Bockius TH NB R2 mass input 1/6/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4

First Energy-Davis-Besse License Renewal Proceeding Proprietary Log Eighth Update, July 31, 2012 Log No.

Category Location*

Document Title Date Confidentiality Contentions FEDBPROP-00003733 Attachment Morgan, Lewis &

Bockius MAAP Fission Produce mass.xls 1/6/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003734 Attachment Morgan, Lewis &

Bockius

_MAAP FLAASH 68.doc 1/3/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003735 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 25 MAAP kg.xls 1/11/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003736 Standard file;Standard file with attachment Morgan, Lewis &

Bockius Expert Panel Charter.doc 12/22/2011 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003737 Embedding Morgan, Lewis &

Bockius SAMA/_NRC RAIs/Expert Panel Charter.doc_embedding0 12/22/2011 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003738 eMail;eMail without attachment Morgan, Lewis &

Bockius Work Scope to Prepare DB TH Notebook, Rev. 2 for SAMA Support 12/19/2011 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003739 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 32-9125650-005 DB L3 PRA_2012 25 FINAL.pdf 7/25/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003740 eMail;eMail with attachment Morgan, Lewis &

Bockius Jun 2012 presentation on MAAP-FLASH#68 issue 6/27/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003741 Attachment Morgan, Lewis &

Bockius FREL.pptx 6/27/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003742 Attachment Morgan, Lewis &

Bockius 51-9182807-000_060612.doc 6/11/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003743 Standard file;Standard file without attachment Morgan, Lewis &

Bockius Assembled.pdf 6/5/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003744 Standard file;Standard file without attachment Morgan, Lewis &

Bockius PRA-DB1-11-017-R00.pdf 6/5/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4

First Energy-Davis-Besse License Renewal Proceeding Proprietary Log Eighth Update, July 31, 2012 Log No.

Category Location*

Document Title Date Confidentiality Contentions FEDBPROP-00003745 Standard file;Standard file without attachment Morgan, Lewis &

Bockius PRA-DB1-11-017-R00 wo cvr.doc 6/5/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003746 Attachment Morgan, Lewis &

Bockius 16_NB(Quant).signed.pdf 6/7/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003747 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 51-9124603-008 CBA.pdf 6/12/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003748 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 51-9182807-000.pdf 6/12/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003749 eMail;eMail without attachment Morgan, Lewis &

Bockius Davis-Besse SAMA 1/18/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003750 eMail;eMail without attachment Morgan, Lewis &

Bockius RE: 25 MAAP elements 1/10/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4); Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003751 eMail;eMail with attachment Morgan, Lewis &

Bockius Fw: Task Plan for the Update of Davis-Besse SAMA Basis Documents 2/2/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4); Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003752 Attachment Morgan, Lewis &

Bockius 108-9176280-000.pdf 2/2/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003753 Standard file;Standard file without attachment Morgan, Lewis &

Bockius P0390110002-4161 DB M406 TH Notebook_MainReport R2.pdf 2/6/2012 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4

First Energy-Davis-Besse License Renewal Proceeding Proprietary Log Eighth Update, July 31, 2012 Log No.

Category Location*

Document Title Date Confidentiality Contentions FEDBPROP-00003754 Standard file;Standard file without attachment Morgan, Lewis &

Bockius PRS-12-00003.pdf 2/7/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003755 eMail;eMail without attachment Morgan, Lewis &

Bockius Jan 31 MAAP update 1/31/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003756 eMail;eMail without attachment Morgan, Lewis &

Bockius Jan 31 MAAP update 1/31/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003757 eMail;eMail without attachment Morgan, Lewis &

Bockius Jan 31 MAAP update 1/31/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003758 eMail;eMail with attachment Morgan, Lewis &

Bockius fyi - MAAP inputs for MACCS2 1/16/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003759 Standard file;Standard file without attachment Morgan, Lewis &

Bockius D-B Source Term zip.doc 1/13/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003760 Standard file;Standard file without attachment Morgan, Lewis &

Bockius MAAP 25 Elements.pdf 12/30/2011 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003761 Standard file;Standard file without attachment Morgan, Lewis &

Bockius 86-9126346-001.pdf 1/11/2012 FE Proprietary - 10 C.F.R. § 2.390(a)(4); Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003762 Attachment Morgan, Lewis &

Bockius AREVA Transmittal Letter & Calc - DB Core Inventory_11-9-09.pdf 12/21/2011 Third-Party Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4

First Energy-Davis-Besse License Renewal Proceeding Proprietary Log Eighth Update, July 31, 2012 Log No.

Category Location*

Document Title Date Confidentiality Contentions FEDBPROP-00003763 eMail;eMail without attachment Morgan, Lewis &

Bockius RE:

10/18/2011 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4 FEDBPROP-00003764 eMail;eMail without attachment Morgan, Lewis &

Bockius RE:

10/18/2011 FE Proprietary - 10 C.F.R. § 2.390(a)(4)

Contention 4

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD

)

In the Matter of

)

)

Docket No. 50-346-LR FIRSTENERGY NUCLEAR OPERATING COMPANY

)

)

(Davis-Besse Nuclear Power Station, Unit 1)

)

July 31, 2012

)

CERTIFICATE OF SERVICE I hereby certify that, on this date, a copy of FENOCs Eighth Update to Mandatory Disclosures Pursuant to 10 C.F.R. § 2.336 was filed with the Electronic Information Exchange in the above-captioned proceeding on the following recipients:

Administrative Judge William J. Froehlich, Chair Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: wjf1@nrc.gov Administrative Judge Dr. William E. Kastenberg Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: wek1@nrc.gov Office of the Secretary U.S. Nuclear Regulatory Commission Rulemakings and Adjudications Staff Washington, DC 20555-0001 E-mail: hearingdocket@nrc.gov Administrative Judge Dr. Nicholas G. Trikouros Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 E-mail: nicholas.trikouros@nrc.gov Office of the General Counsel U.S. Nuclear Regulatory Commission Mail Stop O-15D21 Washington, DC 20555-0001 Edward L. Williamson Lloyd B. Subin Brian G. Harris Brian P. Newell Catherine E. Kanatas edward.williamson@nrc.gov; lloyd.subin@nrc.gov; brian.harris@nrc.gov; brian.newell@nrc.gov; catherine.kanatas@nrc.gov

2 Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Mail Stop: O-16C1 Washington, DC 20555-0001 E-mail: ocaamail@nrc.gov Kevin Kamps Paul Gunter Beyond Nuclear 6930 Carroll Avenue, Suite 400 Takoma Park, MD 20912 E-mail: kevin@beyondnuclear.org; paul@beyondnuclear.org Michael Keegan Dont Waste Michigan 811 Harrison Street Monroe, MI 48161 E-mail: mkeeganj@comcast.net Terry J. Lodge 316 N. Michigan St., Ste. 520 Toledo, OH 43604 E-mail: tjlodge50@yahoo.com Signed (electronically) by Jane T. Accomando Jane T. Accomando Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, N.W.

Washington, DC 20004 Phone: 202-739-3000 Fax: 202-739-3001 E-mail: jaccomando@morganlewis.com Counsel for FENOC