ES-201, Rev. 9 Examination Preparation Checklist Form ES-201-1 Facility: Prairie Island Nuclear Generating Plant Date of Examination: May 14, 2012 Developed by: Written - Facility NRC
// Operating - Facility NRC Target Date*
Task Description (Reference)
Chief Examiner=s Initials
-180
- 1.
Examination administration date confirmed (C.1.a; C.2.a and b) dm
-120
- 2.
NRC examiners and facility contact assigned (C.1.d; C.2.e) dm
-120
- 3.
Facility contact briefed on security and other requirements (C.2.c) dm
-120
- 4.
Corporate notification letter sent (C.2.d) dm
[-90]
[5. Reference material due (C.1.e; C.3.c; Attachment 2)]
dm
{-75}
- 6.
Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and ES-401-4, as applicable (C.1.e and f; C.3.d) dm
{-70}
{7. Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)}
n/a
{-45}
- 8.
Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, and any Form ES-201-3 updates), and reference materials due (C.1.e, f, g and h; C.3.d) dm
-30
- 9.
Preliminary license applications (NRC Form 398s) due (C.1.l; C.2.g; ES-202) drm
-14
-14
- 11. Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f) drm
-14
- 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) drm
-7
- 13. Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h) drm
-7
- 14. Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; Attachment 4; ES-202, C.2.e; ES-204) drm
-7
- 15. Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k) drm
-7
- 16. Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i) drm
- Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[Applies only] {Does not apply} to examinations prepared by the NRC.