MEMORANDUM TO:
FROM:
SUBJECT:
DATE & TIME:
LOCATION:
PURPOSE:
CATEGORY'll:
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 July 11,2012 Michael T. Markley, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Balwant K. Singal, Senior Project Manager 'b -t:.O~ 1:.s,~
Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FORTHCOMING CONFERENCE CALL - PRE-LICENSING PUBLIC MEETING WITH LUMINANT GENERATION COMPANY LLC (TAC NOS. MEB615 AND MEB616)
Monday, August 6,2012 2:00 p.m. - 3:30 p.m. EDT (Eastern Daylight Time)
U.S. Nuclear RegUlatory Commission 11555 Rockville Pike, Room 0-OBB6 Rockville, Maryland Follow-up discussion on the proposed license amendment request in support of a plant modification to install a backup transformer (XST1) for an offsite alternating current (AC) power source at Comanche Peak Nuclear Power Plant, Units 1 and 2. The work involved for implementing the plant modification will require an extended Completion Time for Technical Specification 3.B.1, "AC Sources - Operating," in order to support the transformer outage during power operations.
This is a Category 1 Meeting via conference call. The public is invited to participate in this meeting and will have one or more opportunities to communicate with the NRC after the business portion, but before the meeting is adjourned.
- Commission's Policy Statement on "Enhancing Public PartiCipation in NRC Meetings" (67 FR 36920). May 28. 2002.
M. Markley
- 2 PARTICIPANTS:
Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).
NRC Luminant Generation Company LLC M. Snodderly J. Lamarca G.Waig T. Hope RLi R Slough J. Andersen T. Walker J. Hyslop N. Larson J. Patel F. Madden B. Beasley B. Singal, et al.
Interested members of the public can participate in this meeting via a toll-free audio teleconference. Please e-mail or call (e-mail preferred) one of the meeting contacts listed below before August 2,2012,3:00 p.m. (Eastern Daylight Time), to get the telephone number and the pass code.
MEETING CONTACTS:
Balwant K. Sing ai, NRR Kaly Kalyanam, NRR 301-415-3016 301-415-1480 Balwant. Singal@nrc.gov Kaly.kalyanam@nrc.gov*
The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need a reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact. Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.htm!.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same web address above.
Docket Nos. 50-445 and 50-446
Enclosure:
Agenda cc w/encl: Distribution via Listserv
AGENDA FORTHCOMING CONFERENCE CALL - PRE-LICENSING PUBLIC MEETING WITH LUMINANT GENERATION COMPANY LLC AND U.S. NUCLEAR REGULATORY COMMISSION COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 DOCKET NOS. 50-445 AND 50-446 MONDAY, AUGUST 6, 2012 2:00 p.m. - 3:30 p.m. EDT Introductions.
Luminant Generation Company LLC (Luminant) to discuss the proposed plant modification to install a backup transformer (XST1) for an offsite alternating current (AC) power source at Comanche Peak Nuclear Power Plant and explain the basis for the request to extend the Completion Time for Technical Specification 3.8.1, "AC Sources Operating," This will be a follow-up discussion from the public meeting held at NRC headquarters on June 26,2012.
NRC staff input.
Public comments.
Adjourn.
Enclosure
ML12191A147 OFFICE DORULPL4/PM DORULPL4/LA DORULPL4/BC DORULPL4IPM NAME BSingal JBurkhardt MMarkley BSingal DATE 7/11/12 7/9112 7/11/12 7/11112