June 28, 2012
David J. Bannister, Vice President
and Chief Nuclear Officer
Omaha Public Power District
Fort Calhoun Station FC-2-4
P.O. Box 550
Fort Calhoun, NE 68023-0550
SUBJECT:
FORT CALHOUN STATION - NOTIFICATION OF NRC RETAKE OPERATOR
LICENSING EXAMINATION 05000285/2012302
Dear Mr. Bannister:
In a telephone conversation on June 6, 2012, between Messrs. Tom Giebelhausen, Manager
Operations Training and Simulator, and Chris Steely, Chief Examiner, arrangements were made
for the administration of licensing examinations at Fort Calhoun Station on September 21, 2012.
As agreed during the telephone conversation, your staff will prepare the examination based on
the guidelines in NUREG-1021, Operator Licensing Examination Standards for Power
Reactors, Revision 9, Supplement 1, and NUREG-1122, Knowledge and Abilities Catalog for
Nuclear Power Plant Operators, Revision 2, Supplement 1. The NRCs regional office will
discuss with your staff any changes that might be necessary before the examinations are
administered.
To meet the above schedule, it will be necessary for your staff to furnish the examination outline
by July 13, 2012. The written examination and reference materials identified in Attachment 3 to
ES-201 will be due by August 13, 2012. Pursuant to Title 10, Section 55.40(b)(3), of the Code
of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility
licensee shall approve the outline, examination, and tests before they are submitted to the NRC
for review and approval. All materials shall be complete and ready-to-use. We request that any
personal, proprietary, sensitive unclassified, or safeguards information in your response be
contained in a separate enclosure and appropriately marked. Any delay in receiving the
required examination and reference materials, or the submittal of inadequate or incomplete
materials, may cause the examinations to be rescheduled.
In order to conduct the requested written examinations, it will be necessary for your staff to
provide adequate space and accommodations in accordance with ES-402.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations are being administered.
UNITED STATES
NUCLEAR REGULATORY COMMISSION
RE GIO N I V
1600 EAST LAMAR BLVD
ARLINGTON, TEXAS 76011-4511
D. Bannister
- 2 -
To permit timely NRC review and evaluation, your staff should submit preliminary operator and
senior operator license applications (Office of Management and Budget (OMB) approval
number 3150-0090), medical certifications (OMB approval number 3150-0024), and waiver
requests (if any) (OMB approval number 3150-0090) at least 30 days before the first
examination date. If the applications are not received at least 30 days before the examination
date, a postponement may be necessary. Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act
of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on February 28, 2013. The public reporting burden
for this collection of information is estimated to average 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> per response, including the
time for reviewing instructions, gathering and maintaining the data needed, writing the
examinations, and completing and reviewing the collection of information. Send comments
regarding this burden estimate or any other aspect of these information collections, including
suggestions for reducing the burden, to the Records and FOIA/Privacy Services Branch
(T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet
electronic mail to INFOCOLLECTS@NRC.GOV.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an
information collection, unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRCs Public Document Room or from the
Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access
and Management System (ADAMS). ADAMS is accessible from the electronic Reading Room
page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Giebelhausen has been advised of the
policies and guidelines referenced in this letter. If you have any questions regarding the NRCs
examination procedures and guidelines, please contact Mr. Steely at 817-200-1432, or myself
at 817-200-1159.
Sincerely,
/RA/
Mark S. Haire, Chief
Operations Branch
Division of Reactor Safety
Docket: 50-285
License: DPR-40
Distribution made electronically to Fort Calhoun
ADAMS: No 6 Yes
6 SUNSI Review Complete
Reviewer Initials: CDS