June 20, 2012 Summary of Open House Meeting to Discuss the Fermi, Unit 2, End-of-Cycle Plant Performance Assessment
ML12179A300
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 06/27/2012
From: Jamnes Cameron
NRC/RGN-III/DRP/B6
To:
References
Download: ML12179A300 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 27, 2012 LICENSEE: Detroit Edison Company FACILITY: Fermi Nuclear Power Station, Unit 2

SUBJECT:

SUMMARY

OF THE JUNE 20, 2012, OPEN HOUSE TO DISCUSS THE FERMI POWER PLANT, UNIT 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On June 20, 2012, an open house/poster session was held at the Monroe County Board of Commissioners' Chambers County Courthouse, Monroe, Michigan, between the U.S. Nuclear Regulatory Commission (NRC) and the public to discuss NRC activities, nuclear power issues, and the Fermi Power Plant, Unit 2, performance for the period of January 1, 2011, through December 31, 2011. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML12151A192 and ML12151A198, respectively. A list of the open house attendees who signed the attendance sheet is enclosed.

The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-341 License No. NPF-43

Enclosure:

As Stated cc w/encl: Distribution via ListServ

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 27, 2012 LICENSEE: Detroit Edison Company FACILITY: Fermi Nuclear Power Station, Unit 2

SUBJECT:

SUMMARY

OF THE JUNE 20, 2012, OPEN HOUSE TO DISCUSS THE FERMI POWER PLANT, UNIT 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On June 20, 2012, an open house/poster session was held at the Monroe County Board of Commissioners' Chambers County Courthouse, Monroe, Michigan, between the U.S. Nuclear Regulatory Commission (NRC) and the public to discuss NRC activities, nuclear power issues, and the Fermi Power Plant, Unit 2, performance for the period of January 1, 2011, through December 31, 2011. The NRC letter and meeting notice for this open house can be found in the Agencywide Documents Access and Management System (ADAMS) as ML12151A192 and ML12151A198, respectively. A list of the open house attendees who signed the attendance sheet is enclosed.

The open house/poster session consisted of the NRC listening to comments and answering questions from the public. In addition, licensee staff was present to address any end-of-cycle performance questions from the public.

Sincerely,

/RA/

Jamnes L. Cameron, Chief Branch 6 Division of Reactor Projects Docket No. 50-341 License No. NPF-43

Enclosure:

As Stated cc w/encl: Distribution via ListServ DOCUMENT NAME: G:\DRPIII\1-Secy\1-Work In Progress\EOC CY 2011 (Issued 2012)

Meeting Summary & Slides\Fermi 2011 EOC Open House Summary.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME PSmagacz:dtp JCameron DATE 06/27/12 06/27/12 OFFICIAL RECORD COPY

Letter to Detroit Edison Company from Jamnes L. Cameron dated June 27, 2012.

SUBJECT:

SUMMARY

OF THE JUNE 20, 2012, OPEN HOUSE TO DISCUSS THE FERMI POWER PLANT, UNIT 2, END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT DISTRIBUTION:

Mike McCoppin RidsNrrDorlLpl3-1 Resource RidsNrrPMFermi2 Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports.Resource@nrc.gov

Enclosure Open House Principle Attendees June 20, 2012 Nuclear Regulatory Commission Jamnes Cameron R. Mike Morris Bob Jones Detroit Edison Company Joseph Pendergast Todd Conner Rod Johnson Guy Cerullo Stephen Tait Archana Manoharan Robin Thompson Colleen Walker Mathew Caragher Molly L. Coy Others Barbara Yugovich, RIC Committee Jo Ann Capaul, RIC Committee Ed Steinkampf, Citizen Richard Meyer, Citizen Charles Slat, Monroe News Tom Stephens, Citizen Michael Keegan, Citizen Esther Marcus, Resident Keith Gunter, Citizen Ethyl Rivera, Citizen Henry Newnan, Citizen Kevin Kamps, Beyond Nuclear Victoria Gasidlo, Citizen Ed McArdle, Sierra Club Michigan Royce Maniko, Monroe County Administrator Jessica Miskena, Citizen