Strategy Meeting Seabrook ASR 10:00am 12/9/11; Seabrook Concrete Degradation
ML12174A042
Person / Time
Site: Seabrook  NextEra Energy icon.png
Issue date: 12/09/2011
From:
NRC Region 1
To:
References
FOIA/PA-2012-0119
Download: ML12174A042 (9)


Text

Seabrook Concrete Degradation PRD* ISIONAL INF*R.MATION.

Strategy Meeting Seabrook ASR 1000am 12/9/11 Attendees: Chris Miller, Darrell Roberts, Peter Wilson, Art Burritt, Rich Conte Location: Darrell Robert's Office

Purpose:

1. Briefly summarize developments in the last 2 months (see details Attachment 1 item 5)
2. Briefly discuss potential activity for January 2012 on key issues (see details Attachment 1 item 1)
3. Formulate short actions to January 31, 2012 (before holiday vacations set in).
4. Discuss longer term actions, need for action plan beyond January 2012 in which other inspection plans and side issues can be address (Att. 1 and 2 parking lot issues for now)

Success:

1. Management understanding by questions addressed each of the purposes above.
2. Development of key actions for short term action plan.
3. Collection of parking lot issues for longer term plan.
4. Time to discuss details of Att. 1 and 2 if needed, Status of Goals Est. in Aug. 2011 and Timeline Agenda (Process):

T)ME LEAD ACTIVITY

$:5 min Conte/Burritt Alignment on purpose, success, and process

  • 10 min Conte Developments in last 2 months (including key issues)
  • 10 min Burritt/Conte Potential Activity to January 31, 2012
  • 5 min Conte Summarize Short Term Action Plan
  • 10 min Conte Long Term Action Plan

+. Time left All Details on Attachment '1 and 2 (side issues)

I mntormation in this record was deleted in accordance with the F Act, exemptio of Information 5/

Seabrook Concrete Degradation - Updated Status of Previous Goals for NRC - To June 30, 2012 See attachment 2 for overall time line and core sampling time line Goals for NRC staff wrt ASR issue as of September 2011 [additional TIAs may be needed(*)]:

1. Ensure NextEra progress on final ODs as evidence by:
a. *Completed ODs before January 2012 OR
b. Appropriately update ODs with a clear path to resolution for which the NRC agrees before March 2012 Status:

Update occurred October 2011 based on shortcomings found by NRC staff (Region I, DE and DLR)

Al - Issue Standalone Inspection Report < 45 days of November 29, 2011 (Timing might be everything, Due Out January 13, 2012 Al - Next POD will be final after Engineering Evaluation of March 2012 Prognosis on the Engineering Evaluation being delayed or acceptable per the date (tensile strength white paper to be completed with final plans) ???

2. *Review Hydrology study - solicit HP advice Status:

Coordination completed with PSB 2, Jim Noggle Al - to review when available in January 2012 (TIA assistance to NRR may be needed Al - assess how this study affects ASR - most likely part of mitigation action

3. Review as PIR sample the apparent cause for MR violation -in Fall 2011 Status:

Completed the Week"of 11/28/11 - Feeder to resident report - good review of cause, extent of conditions, and corrective actions

4. Review as PIR sam~ple theeroot cause of ASR issue in February 2012 - [it appears to be key input to the engineering evaluation]

Status: /

Al - Schedule week in February or March 2012 to review in parallel with review of Eng.

Eval. March 2012.

2

Seabrook Concrete Degradation PFREDECtST0NAL INI-RUvATON-

5. Issue stand. alone report on interim status with clear messages by TBD (January 15, 2012) - per objectives and scope of review outlined above
a. *Need to establish criteria for final OD review (potential branch technical position or interim staff guidance in the area of license renewal)
b. *Application of criteria to control building
c. *Expansion of review to extent of condition buildings
d. Better understand any connection between ODs and Engineering Evaluation Status:

Completed initial assessment the week of September 28, 2011 on control building only, extent of condition buildings done by inference Complete week 11/14 review of laboratory work, no issues of concern Complete inspection week of 11/28 (DRS Manager tour):

review of crazed cracking in primary containment no evidence of ASR effect on primary containment started review of procurement control of contractors Clearly the Final ODs are tied to the Engineering Evaluation along with AMR to AMP review:

Al - Issue Standalone Inspection Report < 45 days of November 29, 2011 (Timing might be everything, Due Out January 13, 2012 Comm plan Lots of internal review Al - TIA draft due out 12/31/11 -Will it reflect a branch technical position ?

How much input from Industry/NextEra is needed Status call of 11/30/11, additional firm commitment needs identified to be reflected in specific action plan by NextEra - How to we get it?

Inspection vehicle similar to Wk 9/28 Conference call Meeting onsite or in area and value of public observation Meeting in region I and hdqrtrs and value of public observation.

3

Seabrook Concrete Degradation PrEDnECiSrONAl* IINFORMATIONl Al - Need to strategize Should we be doing more wrt Regulatory Footprint ????:

How much planning for success do we need?

Immediate safety concerns, if any and if not why not.

What ifthey want an extension of March 2012, will need to be processed through DLR and License Renewal schedule, the current only regulatory hold on them.

7(b)(5 Role of Licensing v's. Inspection forums and what is the proper sequencing RAls via Part 50 or Part 54 Need for 50.54f, but before we embark, what is the basis; and, if not, why not Need for Order; but before we embark, what is the basis; and, if not, why not.

6. Start plarfring review of Engineering Evaluation and potential impact on
a. Part 50 Operability
b. Part 54 Aging Effect
c. Need for addition 71002 LRI on ASR aging management program
d. ???? others Status:

Al - No joy on progress with other developments, most likely to be formulated after strategy session

7. Be ready to respond to what if's:
a. Contentions
b. Demonstrations
c. Public meetings surrounding the ASR issue - DEIS Sept 15, 2011 Status:

Comm Plan from License Renewal report to be updated for standalone report Barkley responding to C-10, considerable effort Draft TIA should be available to comprehensively deal with open issues such as for Tensile Strength Tesing.

Possible reaction to visible results of any strategy session to be implement such as for cover letter message in standalone report 4

Seabrook Concrete Degradation SRENAVN-O RMA-N-ý

8. Longer Term and Others ????

Status:

Need to be formulated with March 2012 evaluation 5

Seabrook Concrete Degradation

--PRErC]ST0AL iNFORrlMATION- - Updated Timeline Background - for where we were in order to move forward - Seabrook Concrete ASR Issue Date/Time ACTIVITY June 2009 Walkdowns as part of license renewal application preparations June 1,2010 License Renewal Application (LRA) received July 21, 2010 LRA found acceptable for docketing, opportunity for hearing October 2010 License Renewal Audit results pointed to need for a good number of requests for additional information in this area (conference calls with Region I and DLR started discussion on need to regularly communicate at the branch and division levels, one more frequently than the other)

Fall 2010 Immediate and Prompt Operability Review (POD) based on core samples taken in Control Building (August 2010)

December 31, 2010 End of resident quarterly report period - POD reviewed -

Inspection Report 05000443/2011002, issued Feb. 201 ion POD - No findings noted since laboratory results determined compressive strength and modulus of elasticity met UFSAR values (degradation into reserve strength NOT design margin)

February 15, 2011 ASLB Memorandum and Order (several issues accepted for hearing

- not associated with the concrete Issue March 31, 2011 End of resident quarterly report period - POD reviewed -

Inspection Report 05000443/2011002, issued May 12, 201 1, with two violations in the structures monitoring area wrt 50.65 a(1) and b(2)

April 8, 2011 Last day of License Renewal Inspection (IP71002) -

Inspection Report 05000443/2011007 issued May 19, 2011 and notes in cover letter: "Except for Structures Monitoring Program, results support a reasonable assurance determination for license renewal.

May 8, 2011 Executive Brief May 26, 2011 DLR coordinated ASR seminar in headquarters 6

Seabrook Concrete Degradation F'REL)ICISICJNAL INF&RMvATIO Date/Time ACTIVITY (cont'd)

June 2011 Status Calls with NextEra revealed change in plans Control Building (CB) POD is on hold for final 9/30/11

-. Extent of condition review was to finalize CB POD Extent of Condition Building review has new POD open pending 9/30/11

- Compressive strength going up for extent of condition review (different labs involved)

- Modulus of elasticity degraded but not as bad at Control Building.

NextEra digesting DE questions and DLR RAI questions June 29, 2011 RAI issued by DLR - extensive questions on three major areas (structure monitoring, spent fuel pool, containment concrete)

June 30, 2011 End of quarterly resident report period - related URIs/NCV (green) raised Inspection Report 05000443/2011003, issued August 12, 2011

- open PODs;

- 50.59 screen issue;

- NCV (green) on timely Initial and Prompt ODs for results on extent of condition review for other buildings

- another NCV (green) issued related to the adequacy of the OD, unrelated system NextEra Response to RAI dated June 29, 2011 - under DLR review August 11, 2011 ASR Project Plans not specific September 8, 2011 Executive Brief Week of 9/28/2011 Standalone Inspection Started - Shortcomings found on PODs for CB and EOC Buildings

-September 30, 2011 NextEra issued notice to INPO on ASR for industry review October, 2011 DLR coordinated ASR seminar in headquarters Wk of 11/14/11 Compressive Strength Testing in Illinois for 15/20 concreter cores from the Control Building - Tests observed by Region Ill inspector November 18,2011 Information Notice issued on ASR by NRC (2011-XX)

"7

Seabrook Concrete Degradation

  • PREDECiSiONAL INFORMA-I IUN Wk of 11/28/11 DRS Feeder inspection for PIR sample and review of contractor work

- review of primary containment crazed cracking and

- evidence of no corrosion based on external surfaces and

- rebar inspection November 29, 2011 Exit for Standalone report 2011-010 November 30, 2011 Status Call and coordination for Management Meeting of Jan. 19 started.

December 2011 NextEra contemplating additional testing on remaining 5/20 concrete cores See next timeline related to the pace of core samples coming from the building (input from resident inspectors). Although it appeared to be slow the issue was not an issue for the latest round of 20 concrete core samples from the control building.

NextEra Timeline for CB Operability Determination EOC Cores -5 Building Date/Time ACTIVITY Aug-10 CB I ET test results & petrographic analysis complete - confirm ASR Sep-10 CB / CT POD & C-S-1-10150 - operable 12/3/10 Quote from Altran for QA and SGH for Lab Testing 12/9/10 Issue EC for Coring & PRT 12/10/10 Quote from Miller Engineering for Cores & PRT 12/20/10 Submit to PRB for Request Funds (CAR) 1/7/11 Contract to Miller for Cores & PRT 1/19/11 PRB approves funding Jan-11 Prepare WO for cores and develop work schedules Jan-Feb 2011 Miller clearance, badging & training for site access 2/10/2011 Issue contract to Altran (QA) and SGH (Lab) 2115/2011 Start inplant coring 2/17/2011 4 RCAW cores to SGH for petrographic and physical testing 3/7-25/11 License Renewal Inspection 3/15/2011 Complete coring in all buildings 3/17/2011 Initial transfer of 16 cores to SGH - Tritium concerns cause 3 week delay 3/20/2011 Send core sample to GEL lab for tritium analysis 3/31/2011 Approve Miller Engineering PRT report 4/1/2011 Approve GEL report of tritium analysis 4/1/2011 Start OR14 4/4-8/11 License Renewal Inspection 4/7/2011 Deliver 16 cores to SGH 4/21/2011 AR1644074 - CEB low modulus 4/25/2011 EC250348 / Calc C-S-1-10156 - CEB integrity intact/ OPERABLE 5/23/2011 End OR14 5/27/2011 Receive draft SGH report physical testing (not peer checked, QA cert'd) 8

Seabrook Concrete Degradation PREDBECIS IONAL INFORMATION.

6/16/2011 Initial vendor certified test data (EFW, EV, EDG) available to NextEra 6/27/2011 AR1664399 - low modulus 4EOC buildings - SM expectation OPERABLE 6/28/2011 EC250348 / Calc C-S-1 -10160 & POD for AR1 664399 - Buildings Operable 6/30/2011 Comitment to NRC to complete Control Building OD EOC Reviews 7/1/2011 Receive SGH draft report - petrographs (dated 7/1/11) 7/14/2011 Approve SGH petrograph report 8/3/2011 Approve SGH report (compressive strength & modulus) dated 7/27/11 9