2012 Fermi Power Plant Initial License Examination Proposed Revised Forms ES-301-5 and ES-301-6
ML12156A313
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/29/2012
From: Bielby M
Operations Branch III
To:
Detroit Edison, Co
Shared Package
ML11354A138 List:
References
Download: ML12156A313 (3)


Text

ES-301 Administrative Topics Outline Form ES-301-1 Facility: Fermi-2 Date of Examination: 03/19/12 Examination Level: RO SRO Operating Test Number: 2012-1 Administrative Topic Type Describe activity to be performed (See Note) Code*

Perform Thermal Limit Verification (MAPRAT)

Conduct of Operations RD JP-OP-802-4101-406 Perform Drywell Air Temperature Calculations Conduct of Operations RD JP-OP-802-4101-408 Perform 24.202.03, "HPCI Piping Filled and Valve Position Equipment Control SD Verification" JP-OP-802-4101-427 Notify Hospital for Contaminated Injured Worker Radiation Control RD JP-OP-802-4101-435 Emergency Classification for a SAE Emergency Plan SM JP-OP-802-4101-448 NOTE: All items (5 total) are required for SROs. RO applicants require only 4 items unless they are retaking only the administrative topics, when 5 are required.

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank (< 3 for ROs; < 4 for SROs & RO retakes)

(N)ew or (M)odified from bank (> 1)

(P)revious 2 exams (< 1; randomly selected)

ES 301, Page 22 of 27

ES-301 Transient and Event Checklist Form ES-301-5 Facility: Fermi-2 Date of Exam: 3/19/2012 Operating Test Number: 2012-1 A E Scenarios P V P E 1 2 3 4 T M L N O I I T T N C CREW CREW CREW CREW A I A T POSITION POSITION POSITION POSITION N Y L M S A B S A B S A B S A B U T P R T O R T O R T O R T O E M(*)

O C P O C P O C P O C P R I U RO RX 1 1 1 1 0 SRO-I NOR 10 1,2 3 1 1 1 SRO-U I/C 3,4,5,7,8 2,5,6,7, 2,3,5,6,8 10 11 16 4 4 2 MAJ 4,7,9 6 6,9,10 7 2 2 1 TS 2,3 2 0 2 2 RO RX 1 1 1 1 0 SRO-I NOR 10 1 1 3 1 1 1 SRO-U I/C 345789 2,3,5,7, 2,8 10 11 14 4 4 2 MAJ 4,7,9 6 6,9,10 7 2 2 1 TS 3,4 2 0 2 2 RO RX 3 1 1 1 0 SRO-I NOR 1 1,2 1 4 1 1 1 SRO-U I/C 4,5,7,8,9 3,5,6 10 7,8 11 4 4 2 MAJ 4,7,9 6 6,9,10 7 2 2 1 TS 3,4 2 0 2 2 RO RX 1 1 0 SRO-I NOR 1 1 1 SRO-U I/C 4 4 2 MAJ 2 2 1 TS 0 2 2 Instructions:

1. Check the applicant level and enter the operating test number and Form ES-D-1 event numbers for each event type; TS are not applicable for RO applicants. ROs must serve in both the at-the-controls (ATC) and balance-of-plant (BOP) positions. Instant SROs must serve in both the SRO and ATC positions, including at least two instrument or component (I/C) malfunctions and one major transient, in the ATC position. If an instant SRO additionally serves in the BOP position, one (I/C) malfunction can be credited toward the two (IC) malfunctions required for the ATC position.
2. Reactivity manipulations may be conducted under normal or controlled abnormal conditions (refer to Section D.5.d) but must be significant per Section C.2.a of Appendix D. (*) Reactivity and normal evolutions may be replaced with additional instrument or component malfunctions on a 1-for-1 basis.
3. Whenever practical, both instrument and component malfunctions should be included; only those that require verifiable actions that provide insight to the applicants competence count toward the minimum requirements specified for the applicants license level in the right-hand columns.

ES-301, Page 26 of 27

ES-301 Competencies Checklist Form ES-301-6 Facility: Fermi-2 Date of Examination: 3/19/2012 Operating Test No.: 2012-1 APPLICANTS RO RO RO RO SRO-I SRO-I SRO-I SRO-I Competencies SRO-U SRO-U SRO-U SRO-U SCENARIO SCENARIO SCENARIO SCENARIO 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Interpret/ Diagnose 2,3,4,7, 4,6,7,8, 245679 2,4,7,8, 3,4,5,7, 1,2,3,4, 6,7,9, 3,4,5,6, 3,4,6,7, 1,3,6,8, 8,9,10 9,10 ,10,11 9,10 9,10 7,9 9,10 10,11 Events and Conditions 10,11 Comply With and Use 2,3,4,7, 1,2,6,8, 2,4,5,6, 1,2,7 1,4,5,9, 1,2,3,4, 3,4,5,6, 1,3,4,5, 1,3 9,10 10 7 10 5,6,7 7,9 8,10 Procedures (1)

Operate Control N/A 1,2,6,8 2,5,6,7, 1,2,4,7, 1,4,5,9, N/A 3,4,5,6, N/A 3,7,8 10 8,10 10 7,9 Boards (2)

Communicate 123456 1.2,3,4, 1,2,4,5, 2,3,4,8 1,3,4,5, 1,2,3,4, 3,4,5,6, 1,2,3,4, 1,3,4,9, 78910 5,6,8, 6,7,9, 7,9,10 5,6,7,9, 7,8,9 6,10 10 and Interact 10 10,11 10,11 Demonstrate 1,3,4,9, N/A N/A N/A N/A 1,2,3,4, 5,6,7,8, N/A 1,2,3,4, NA 10 5,10 Supervisory Ability (3) 9,10 Comply With and 2,3 N/A N/A N/A N/A 2,3,4 N/A 3,4 N/A Use Tech Specs. (3)

Notes:

(1) Includes Technical Specification compliance for an RO.

(2) Optional for an SRO-U.

(3) Only applicable to SROs.

Instructions:

Check the applicant's license type and enter one or more event numbers that will allow the examiners to evaluate every applicable competency for every applicant.

ES-301, Page 27 of 27