ML12139A132

From kanterella
Jump to navigation Jump to search
G20120172 - Ltrs from (27) Individuals Co-petition with the Alliance for a Green Economy and Beyond Nuclear'S March 9, 2012 Emergency Enforcement Petition to Suspend the Operation of the James A. FitzPatrick Nuclear Plant
ML12139A132
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 05/08/2012
From: Ciordia-Morandeira A, Kaier A, Morse B
- No Known Affiliation
To: Borchardt R, Bhalchandra Vaidya
NRC/EDO, Office of Nuclear Reactor Regulation
References
2.206, G20120172
Download: ML12139A132 (27)


Text

,.. To..Le_ S, \Ju Mr. James Borchardt Executive Director for Operations

&' ~ ~

DEDMRT

)1 U.S. Nuclear Regulatory Commission DEDR Washington, DC 20555-0001 DEDR DEDCM AO Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York ma' Je~, W

Dear Mr. Borchardt:

Barifu t IZI I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency !c4ow-enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant. BOWMflWO

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: A / V oý ca, e "

Address: *."r " r i p46k 1 L( IO/qLp)

Email:

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: _________________

Address: q61* V/At.-, * *5': AjC(..C/'L"ý I3;2I.,

Email: bqwta(V_ 24Y.k

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: APeiVwro -

Address: bg)y W~~Q_ 'ýOS 4 SL0ts r-. 6ý66&se. M~Y Email: C ~ ~

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, 7 Name: (*-i 1tC_. -. C(J Address: t . . ,. " -/(/ ' 3)(t Email: AA -I~

li /?Y" t . ( / ,

/ I

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRCto process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, F LýNKý

-C Name: '(T'-A Address: I <

Email: ) eci(1 cw

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Name: 6 , _ ý I-Address:  ?-3 J&2 -Vt Email:_

)

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Ailiance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: ' L 1.--P Address: 5o s  ?- ,- I1 ,

Email:

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: VVYJ*L-. -J )Joi(W, Address: :__ _ _Z___ __ __ __ ___3__*

Email: V2V:'.ttQ *L 5-L@ ,-1 . C O"\

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: WdIOLJ (_ *OLA4t Address: to-7 De Email: G 'q6-oo.

I

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank Name:__________________

Address: ,1 A:VTLf" - "' I3Z, Email:

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident, Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:
1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name:"I Address: -

Email: VAT V t\r" n0 QI )_

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reafssessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you,Name: '&' 14 /K Address: 1hQ1jk/i~ kv7

~V1fp, S 4 /4/cui f\\'~~ZT1C)

Email:

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: (4,rc - ,-'/\k Address: 0-Email: I.e4.Vf-t-rt

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.
  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: JHA r) VI) alo d ,!'

__J_"

Address: S ir,_ t ,/,_t , _

Email: S'-/t-- ._

U

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their o0anizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity a cip te in a public meeting with the NRC Petition Review Board.

Thank yu Name:

Address: ý1. ,

Email:

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: i A ,

Address:

Email: _

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

, The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: MWcz-g. V-o::-,q.-iy Address: c, r KNk, 3,-1 Email: n\c."oA.j aAO  !, .

-I - J

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20*55-0001 Attn: Bhalchandra K.Vaidy~, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish tb co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the Jame, A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Tor~us Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "preo existing" venting systemn that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator an4. the NRC relied upon assumptions that now place public health and safety dt an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacoeptabte consequences posed by the -current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

" Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should beileld oan the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double dobr§ to release a radiologicat, accident to the outside environment at ground level. The public must be afforded dUe process to address the unacceptable risks to publiC health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

'he t analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

It should also include a reassessment of the assumptio#t of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

J wish the NRC to process my request using the 2.206 process, and I understand that under this process, the conterits of this message and my identity will be made public. The Alliance for a Green Economy iq my point of contact for this petition, and their organizer, Jessica Azulay, will keep meinformed about the developments of the petition and the opportunity to participate in ý public meeting with the NRC Petition Review Board.

Thank you, Name: RA0 I. A ,

Address: -30 TA ~IyICE S1'liEgT 4 PY ,I1roRC1CTR Ni )lI~

Email: f~i)ia~e.- Ork~e- ql I' COMr CU

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.
  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thankyou Name: "D...  !- .,'A Address: '7 'S C--v , Y3cr V Email: oXr Mý V I

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.
  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: r-ý* Ok z-_

Address: Co a\an\o e- . (.)

~. ~ u~V'io EmailjkC&

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Addriess:

Email: LA la C6U9/(s0ao c0c')

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: Ia- 6 -"lA1 Address: --- (/I (yJ Email:'I

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.
  • The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.
  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: C A*\-Cv*v*a*eO- (

Address:/OIS *U C-/ l*_ A

.4f ,(clz 1 ,Nis" d,-(C Email:

U

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.
  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.
  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: & a-.J-L7 t?,.

Address: 7 1* ( /./O.4i Ave JSy r -s 3.2/6 Email: _Art~e_ //7e1e71IL40 PC ACr

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K. Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

  • In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

" The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.

  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of

-hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, I/

Name: ... _ 5"/ i,' F Li/-

Address: 24- /s 4ou Email: 5FLECD5( VEki.;Z~f, IV7

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York Dear Mr. Borchardt I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

  • The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

" It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: L..,I Address: 1J0" fAV\ D)- , V',

Email: 1A-t AXD 4A

Mr. James Borchardt Executive Director for Operations U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attn: Bhalchandra K.Vaidya, NRC Petition Manager In the Matter of the James A. FitzPatrick Nuclear Plant in Scriba, New York

Dear Mr. Borchardt:

I wish to co-petition with the Alliance for a Green Economy and Beyond Nuclear's March 9, 2012 emergency enforcement petition to suspend the operation of the James A. FitzPatrick Nuclear Plant.

" The FitzPatrick plant is the only GE Mark I boiling water reactor in the US that did not install a Direct Torus Vent System as requested by the NRC in 1989 and instead, to save money, relies upon a "pre-existing" venting system that is not fully hardened against a severe accident.

" In deciding not to install such a vent, the FitzPatrick operator and the NRC relied upon assumptions that now place public health and safety at an undue risk.

  • The hydrogen explosions at the Fukushima reactors show the dangers and unacceptable consequences posed by the current FitzPatrick severe accident venting plan, since the plan was approved on the assumptions that venting would prevent containment failure, and that there are "no likely" ignition sources along the vent path. Neither of these assumptions was correct during the Fukushima nuclear catastrophe.
  • Subsequent to the Fukushima accident, the NRC inspected FitzPatrick and identified a "vulnerability, in that current procedures do not address hydrogen considerations" during a severe accident.

Therefore, I request NRC immediately suspend the FitzPatrick operating license until the following emergency enforcement actions are approved by the NRC:

1) Public hearings should be held on the continued operation of Entergy Nuclear Operations' Fitzpatrick plant and the adequacy of its plan to vent through a pre-existing path into the adjacent Standby Gas Treatment System building, blowing off the double doors to release a radiological accident to the outside environment at ground level. The public must be afforded due process to address the unacceptable risks to public health and safety -posed by the FitzPatrick severe accident plan.
2) Entergy Nuclear Operations should publicly document for independent review its post-Fukushima re-analysis for the reliability and capability of the FitzPatrick pre-existing containment vent system.

" The analysis should include the reassessment of all assumptions regarding the reliability of the pre-existing containment venting and specifically address non-conservative assumptions behind the cost-benefit analysis used to justify not installing a fully hardened vent system.

  • It should also include a reassessment of the assumption of "no likely ignition points" during emergency venting that would otherwise present catastrophic consequences associated with the detonation of hydrogen gas and the release of radioactivity generated during a severe accident.

I wish the NRC to process my request using the 2.206 process, and I understand that under this process, the contents of this message and my identity will be made public. The Alliance for a Green Economy is my point of contact for this petition, and their organizer, Jessica Azulay, will keep me informed about the developments of the petition and the opportunity to participate in a public meeting with the NRC Petition Review Board.

Thank you, Name: . _ _ _.._ _,.._

Address: 2_M " -. /  ;/*,Li *'V Email: bit ~kA~L4 re-)

I - J